WORLD ENERGY, LLC, WORLD ENERGY LOS ANGELES, LLC, ALTAIR PARAMOUNT, LLC, аnd PARAMOUNT PIPELINE, LLC, Plaintiffs, v. AIR PRODUCTS AND CHEMICALS, INC., and AIR PRODUCTS MANUFACTURING LLC, Defendants.
C.A. No. 2025-0912-MTZ
IN THE COURT OF CHANCERY OF THE STATE OF DELAWARE
Date Submitted: January 16, 2026 Date Decided: July 6, 2026
ZURN, Vice Chancellor.
Lauren Dunkle Fortunato, Jason W. Rigby, Alyssa T. Atkisson McKeever, YOUNG CONAWAY STARGATT & TAYLOR, LLP, Wilmington, Delaware; Matthew G. Mrkonic, Tucker R. Hunter, HONIGMAN LLP, Detroit, Michigan, Attorneys for Plaintiffs. John L. Reed, Michael A. Carbonara, Jr., DLA PIPER LLP (US), Wilmington, Delaware; Steven M. Rosato, DLA PIPER LLP (US), New York, New York, Attorneys for Defendants.
MEMORANDUM OPINION
ZURN, Vice Chancellor.
I. BACKGROUND2
Plaintiffs World Energy, LLC (“WE LLC“), World Energy Los Angeles, LLC (“WELA“), AltAir Paramount, LLC (“AltAir“), and Paramount Pipeline, LLC (“Paramount Pipeline,” and together with WE LLC, WELA, and Alt Air, “World Energy“) operate biodiesel manufacturing plants throughout the United States.3 World Energy is a pioneer in the production of sustainable aviation fuel.4 AltAir owns and operates the Paramount, California-based fuel refinery at the center of this
World Energy needed a hydrogen supplier for the Paramount Facility.7 In 2019, it entered into a supply agreement with defendant Air Products and Chemicals, Inc. (“APC,” and together with defendant Air Products Manufacturing LLC “Air Products“), a global industrial gases supplier and leader in energy transition.8
World Energy and Air Products saw additional opportunity to develop the Paramount Facility together.9 In March 2020, AltAir and Air Products entered into an agreement by which Air Products would “optimize existing Paramount Facility operations” on what would be called “Plant A,” and “design, engineer, and construct certain expansions” on what would be called “Plant B.”10 The project got off to a rough start, with delays and cost overruns continuing well into 2023.11 World
Yet World Energy opted to entrust Air Products with more responsibility. In early 2023, the parties began exploring a path for World Energy to sell the Plant A assets and “hand over daily operations” at the Paramount Facility to Air Products.13 On November 14, the parties executed a suite of agreements to that effect.14 The Master Project Agreement and the Credit Agreement are central to this action.
A. The Master Project Agreement And Credit Agreement
The Master Project Agreement amended and restated the 2020 agreement in its entirety.15 Air Products would perform optimization and expansion work on Plant A and Plant B.16 Air Products was also required to “use commercially reasonable efforts to cooperate with World Energy, as reasonably requested by World Energy,” to “assist World Energy to secure working capital finance.”17
World Energy would help pay for Air Products’ work through two monthly payments: (1) a monthly operating fee (the “MOF“), consisting of Air Products’
The monthly payments were material to the Master Project Agreement. Section 8.2(B) expressly conditioned Air Products’ performance on timely payments of all undisputed MOF and MFF invoice amounts.24 If World Energy failed to pay
Under Section 18.1(B), “[i]f a non-breaching Party believes that the other Party is in Material Breach,” it must “promptly notify the other Party in writing, and in reasonable detail, of the substance of, and basis for, its belief that a Material Breach . . . has occurred.”27 If a Material Breach remained unremedied throughout the applicable notice and cure period, the non-breaching party could then “immediately terminate” the Master Project Agreement upon providing a termination notice.28 Under Section 18.2, the parties must also provide written notice of, and an opportunity to cure, any “Ordinary Breach.”29
Under the Credit Agreement, Air Products also agreed to loan World Energy up to $270 million.30 The principal amount was split up into two tranches: $180
The interest rate on the loan “[p]rior to the Plant B Commencement Date” was set at 15%.33 Interest payments were due on the last day of each calendar month.34 Nonpayment, coupled with a failure to remedy the default within three business days, constituted an “Event of Default.”35 Per Section 8, upon an Event of Default, Air Products was entitled to terminate its commitments and “declare the Loans then outstanding to be due and payable in whole,” with the aggregate principal, accrued interest, and other fees “automatically [] due and payable, without presentment, demand, protest or other notice of any kind.”36
B. World Energy Defaults; The Parties Execute a Forbearance Agreement.
World Energy defaulted immediately and repeatedly. The parties memorialized that reality in a Forbearance Agreement dated July 10, 2024.37 World Energy “acknowledge[d] and agree[d]” that it had breached its payment obligations under both the Master Project Agreement and the Credit Agreement since November 2023, and that it would likely remain in default through September 2024.38 As of July 2024, World Energy‘s missed payments totaled nearly $19 million.39 World Energy also acknowledged that Air Products had “fully and timely performed all of [its] obligations and duties under the Agreements . . . and ha[d] acted reasonably and in good faith under the circumstances.”40
“In reliance upon” those acknowledgements, Air Products agreed to “forbear from exercising any rights or remedies that it may have against [World Energy] or [its] respective assets and properties, in each case solely as a result of the occurrence of the Specified Defaults,” until September 30, 2024.41
C. Activist Investors Target Air Products, And The Parties Execute The Second Amendment To The Credit Agreement.
In mid-2024, Air Products became the target of activist investor campaigns.42 One campaign assailed the World Energy project as “Exhibit A” of Air Products’ mismanagement.43 Air Products focused on monetizing that project.44 It pushed for an amendment to the Credit Agreement that would change certain provisions governing the disposition and distribution of assets.45 According to the Complaint, Air Products threatened to “stop working with World Energy to obtain working capital financing,”46 and promised to provide another forbearance agreement if World Energy executed the Second Amendment.47
The parties executed the Second Amendment to the Credit Agreement on September 30, 2024.48 It recites that “the Borrower [i.e., AltAir] has requested that [Air Products] amend certain provisions of the Credit Agreement.”49 The parties did not enter into another forbearance agreement.50
D. World Energy Continues To Default; Air Products Exercises Its Remedies.
World Energy remained in default after the forbearance period. Between October 2024 and February 2025, Air Products sent World Energy nine default notices pursuant to the Master Project Agreement, and six default notices pursuant to the Credit Agreement.51 The Master Project Agreement notices explained that World Energy had not provided any grounds to dispute the invoiced amounts, that Air Products was entitled to suspend performance after forty-five days, and that Air Products was entitled to terminate the Master Project Agreement after ninety.52 The Credit Agreement notices explained that Air Products “expressly reserve[d] the right” to exercise any and all remedies available under the Credit Agreement “at any time.”53
In latе January 2025, a new slate of directors was elected to Air Products’ board.54 The new leadership commanded a shift away from energy transition projects.55 In early February, Air Products told World Energy it was not going forward with the Plant A optimization work.56 On February 24, Air Products
Later that week, the parties elected to move forward with a planned “February 2025 turnaround” so that Air Products could “hand back the keys” to World Energy.60 World Energy claims Air Products promised as part of that turnaround work to repair the “12-D Rack,” a “support rack that holds up utility lines” necessary for Plant A‘s operations.61 Air Products and its subcontractor “completed the necessary pre-work for the 12-D Rack repair,” including the removal of external bracing and scaffolding.62 But Air Products did not complete the repair.63 The 12-
On March 26, over a month after Air Products’ termination notice, World Energy sent two letters challenging the termination.65 The first claimed the “sole purported ground” for termination—the MFF payments—was invalid because the payments were “the subject of a good faith dispute by World Energy and therefore [we]re not due.”66 It also claimed Air Products, not World Energy, “Materially Breached the [Master Project Agreement] and, through its own wrongful conduct, prevented World Energy from being able to pay the [MFF].”67 The letter demanded that “Air Products immediately withdraw its repudiation and improper termination of the [Master Project Agreement] and confirm in writing that it will comply with all of its contractual obligations.”68
World Energy also sent Air Products a formal notice of breach of the Master Project Agreement.69 The notice advised of: (1) a matеrial breach of Section 2.1(D) by failing to complete and fund, and then by repudiating, the Paramount Facility
Air Products responded on March 31.72 It raised World Energy‘s failure to meet its financial commitments, properly dispute the MFF invoiced amounts, or provide notice of any breach prior to termination.73 It maintained the termination was valid because “[f]or some time, Air Products has been the only party performing under the [Master Project] Agreement.”74 That same day, Air Products also sent written notice that it was accelerating all amounts due under the Credit Agreement.75 Air Products demanded immediate payment of $313,568,095.01.76 World Energy refused to pay.77
E. Air Products Files Suit In New York.
On April 29, Air Products filed a motion for summary judgment in lieu of complaint against World Energy in New York state court.78 The motion sought a $312 million judgment under a guaranty agreement (the “Guaranty“), in which WE LLC irrevocably and unconditionally guaranteed all payments owed by AltAir under the Credit Agreement.79 Both the Credit Agreement and the Guaranty contain New York forum selection and choice of law provisions.80
On September 19, 2025, the New York court granted the motion in its entirety.81 Relevant here, the court rejected World Energy‘s argument that “the applicable interest rate was 4.5%, not 15%” under the Credit Agreement.82 Specifically, it concluded “the Credit Agreement unambiguously sets the ‘Applicable Rate’ at 15% and permits modifications only through a signed writing.”83
F. This Litigation
On August 8, 2025, World Energy filed a Verified Complaint (the “Complaint“), along with a motion for preliminary injunction.86 Counts I and II are breach of contract claims seeking specific performance of the Master Project Agreement. Both counts also seek preliminary and permanent injunctive relief requiring Air Products to “restore and maintain the status quo operations of the Paramount facility,” with a focus on restoring the 12-D Rack to operation.87
Count III alleges a breach of the implied covenant of good faith and fair dealing. Count IV alleges mutual mistake and seeks reformation of the Credit Agreement, particularly its 15% interest rate before the Plant B Commencement Date. Count V alleges Air Products fraudulently induced World Energy into executing the Second Amendment. Count VI seeks a declaration that World Energy has not breached any of its agreements with Air Products, that Air Products’ default
Air Products moved to dismiss the Complaint on September 2, 2025.88 The parties briefed the motion for preliminary injunction and motion to dismiss by November 18.89 I heard oral argument on January 16, 2026.90 I denied the motion for preliminary injunction from the bench, with a promise to provide a subsequent explanation, and took the motion to dismiss under advisement the same day.91
II. ANALYSIS
World Energy seeks relief for breach of contract, including a mandatory injunction requiring Air Products to fix the 12-D Rack and perform other work at the Paramount Facility.92 To obtain that extraordinary and final relief, World Energy must state a claim for breach of contract, then prevail on its merits as a matter of law on undisputed facts.93 World Energy has done neither. Air Products properly
A. Merits
The pleading standards under Delaware law are “minimal.”94 On a motion to dismiss under Rule 12(b)(6), the Court must “accept all well-pleaded factual allegations in the complaint as true, accept even vague allegations in the complaint as well-pleaded if they provide the defendant notice of the claim, [and] draw all reasonable inferences in favor of the plaintiff.”95 The Court will grant a Rule 12(b)(6) motion if the “plaintiff could not recover under аny reasonably conceivable set of circumstances susceptible of proof.”96 The Court need not “accept as true conclusory allegations without specific supporting factual allegations.”97 The Court
1. Breach of Contract
The elements of a claim for breach of contract are familiar: “(i) a contractual obligation, (ii) a breach of that obligation by the defendant, and (iii) a causally related injury that warrants a remedy, such as damages or in an appropriate case, specific performance.”99 No path to recovery is available unless the plaintiff “demonstrate[s] that it substantially complied with all of the provisions of the contract.”100
World Energy did not substantially comply with its obligations under the Master Project Agreement. World Energy‘s primary obligation was to pay the MOF
World Energy responds by invoking the prevention doctrine, arguing its nonperformance is excused because Air Products engaged in conduct that prevented it from making timely payments: specifically, that Air Products did not do the work necessary to make the Paramount Facility profitable.105 It is well settled that “the failure of a plaintiff to have performed his own obligation will be excused if he was
For defaults before September 30, 2024, the Forbearance Agreement is fatal to World Energy‘s argument.110 There, World Energy acknowledged that Air
Wells v. Lee Builders, Inc. is instructive.112 There, a buyer sought specific performance of a land sale contract, even though he was required to move a house off the parcel before closing and had not done so.113 The buyer argued his nonperformance should be excused because the sellers had prevented the buyer from moving the house.114 The Delaware Suрreme Court concluded any prevention of the buyer‘s performance by the seller “was made immaterial by” an intervening agreement.115 The agreement contained a “recital of fact” that “certain unforeseen difficulties have caused unavoidable delays in the fulfillment by both the sellers and the buyer of their respective obligations.”116 Its effect “was to wipe out . . . any action on [the sellers‘] part which tended to prevent performance by the plaintiff of
That leaves Air Products’ conduct after September 30, 2024, until Air Products terminated the Master Project Agreement.120 World Energy‘s primary argument is that Air Products “starve[d] World Energy of revenue that [it] needed” to make its monthly payments, and then, having breached the contract itself, improperly repudiated its obligations.121
First, it contends Air Products breached by failing to complete the “2024 Plant A Expansion Shutdown“—which is how the Master Project Agreement labels the overall Plant A expansion work—by the end of 2024.122 But nothing in the contract mandates that deadline. World Energy relies entirely on the “2024” in the defined term to infer a December 31, 2024 deadline. But the Master Project Agreement explicitly states “that Air Products is not providing any schedule guarantee for the
More fundamentally, World Energy‘s payment obligations were not tied to the fruits of Air Products’ work.125 The obligations arose as soon as World Energy began working on Plant A, without regard to any operational milestones.126 If the
From there, World Energy argues Air Products breached its obligation to assist with working capital financing.129 That contention is not supported by the Complaint or the record. World Energy does not plead or identify a single instance after the forbearance period where it “requested,” but failed to receive, Air Products’ assistance in securing capital.130
The Master Project Agreement excused MFF payments in two scenarios: (1) upon the occurrence of a “MFF Deferral Event” which, by definition, must “occur[] after the completion of the 2024 Plant A Expansion Shutdown“; and (2) upon a “Material Breach” by Air Products, followed by its failure to cure the breach within sixty days of receiving a default notice. Master Project Agreement §§ 1.1, 18.1(A)(iii). Neither scenario applied to World Energy. The first did not apply because the 2024 Plant A Expansion Shutdown had not yet been completed. The second did not apply because World Energy did not provide Air Products notice or an opportunity to cure any purpоrted breaches, as required by Section 18.1(A)(iii).
World Energy presses that none of the missed MFF payments triggered a termination right because they were never “due” in the first place: World Energy contends they were “the subjeсt of a good faith dispute.”136 Not so. The contract
Air Products’ performance under the Master Project Agreement was unambiguously conditioned on receiving monthly payments from World Energy.143 World Energy failed to make those payments. And it failed to plead any circumstances excusing its defaults. Counts I and II are dismissed.
It follows that Count VI, which seeks a declaration that World Energy has not breached any of the relevant agreements and is entitled to have Air Products’ termination withdrawn, fails as well. Count VI is dismissed.
2. Breach Of The Implied Covenant
Count III asserts a claim for breach of the implied covenant of good faith and fair dealing. The implied covenant “inheres in every contract and requires a party in a contractual relationship to refrain from arbitrary or unreasonable conduct which has the effect of preventing the other party . . . from receiving the fruits of the bargain.144 “To state a claim for breach of the implied covenant, [a plaintiff] ‘must allege a specific implied contractual obligation, a breach of that obligation by the defendant, and resulting damage to the plaintiff.‘”145 “General allegations of bad faith conduct are not sufficient.”146
3. Estoppel
In Count VII, World Energy asserts a single claim for both promissory and equitable estoppel.158 It alleges that after terminating the Master Project Agreement,
“[P]romissory estoppel is fundamentally a narrow doctrine, designed to protect the legitimate expectations of parties rendered vulnerable by the very processing of attempting to form commercial relationships.”160 To plead a promissory estoppel claim, the plaintiff must allege that:
- (1) a promise was made; (2) it was the reasonable expectation of the promisor to induce action or forbearance on the part of the promisee; (3) the promisee reasonably relied on the promise and took action to his detriment; and (4) such promise is binding because injustice can be avoided only be enforcement of the promise.161
At oral argument, World Energy explained that the 12-D Rack repairs are “part and parcel” of Air Products’ “obligations to fund and complete the work and to maintain the plant under the [Master Project Agreement].”162 But as our Supreme Court noted in SIGA Technologies, Inc. v. PharmAthene, Inc., promissory estoppel is inapplicable “where a fully integrated, enforceable contract governs the promise
The question is therefore whether World Energy has pled Air Products made a cognizable promise about the 12-D Rack after it terminated the Master Project Agreement. Promissory estoppel requires “a real promise, not just mere expressions of expectation, opinion, or assumption.”165 The promise must be “reasonably definite and certain.”166 World Energy has fallen short of pleading a definite promise.
World Energy alleges that after Air Products terminated the Master Project Agreement, “[b]oth parties planned and agreed that Air Products would permanently repair the 12-D Rack during [a] February 2025 turnaround.”167 It further alleges Air completed “pre-work” for the repairs, and that “[t]hroughout [] daily communications, Air Products consistently communicated that they were moving forward with the 12-D Rack and other repairs.”168 Those allegations do not amount
World Energy‘s equitable estoppel theory fares no better. To state a claim for equitable estoppel, a plaintiff must allege:
- (1) conduct by the party to be estopped that amounts to a false representation, concealment of material facts, or that is calculated to convey an impression different from, and inconsistent with that which the party subsequently attempts to assert, (2) knowledge, actual or constructive, of the real facts and the other party‘s lack of knowledge and the means of discovering the truth, (3) the intention or expectation that the conduct shall be acted upon by, or influence, the other party and good faith reliance by the other, and (4) action or forbearance by the other party amounting to a change of status to his detriment.173
World Energy has not pled circumstances that support justifiable reliance on any purported representations about the 12-D Rack repairs. When the 2025 February turnaround allegedly began, World Energy was well aware of Air Products‘s exit from the Paramount Facility project. It knew Air Products suspended performance in early February, sent a formal termination notice later that month, and publicly announced the termination.175 The termination notice referenced the impending “demobilization and winding-down” of Air Products’ work, and explained Air Products was walking away because it was not getting paid.176 Even if World Energy questioned the termination‘s validity, it could not have reasonably relied on informal onsite communications and “pre-work” on a job Air Products had just called off.177
Count VII is dismissed.
4. Mutual Mistake And Reformation
Count IV asserts a mistake claim seeking reformation of the Credit Agreement.178 Specifically, it seeks a reformation that would swap the Credit Agreement‘s unambiguоus 15% interest rate179 with a 4.5% rate used in the Master
Reformation is a narrow equitable remedy. It is “not an equitable license for the Court to write a new contract at the invitation of a party who is unsatisfied with his or her side of the bargain; rather, it permits the Court to reform a written contract that was intended to memorialize, but fails to comport with, the parties’ prior agreement.”182 “The Court may reform a contract ‘only when the contract does not represent the parties’ intent because of fraud, mutual mistake or, in exceptional circumstances, a unilateral mistake coupled with the other parties’ knowing silence.‘”183
World Energy advances a mutual mistake theory. That theory imposes a heavy burden. A plaintiff alleging mutual mistake “must show that both parties were mistaken as to a material portion of the written agreement.”184 To survive a motion to dismiss, the plaintiff must allege: (1) the parties reached a definite agreement
The claim fails at the first step: pleading a definite prior agreement. “Reformation requires the existence of a specific prior contractual understanding that conflicts with the terms of the written agreement.”187 While that prior understanding “need not constitute a complete contract in and of itself,”188 it must be sufficiently definite to specify for the Court “exactly what terms to insert in the contract.”189 World Energy alludes to an oral agreement between the parties about charging a 4.5% interest rate on the Credit Agreement loan until Air Products completed its Plant A optimization work.190 As pled, that agreement is far from definite.
From there, World Energy points to statements by Air Products executives after the parties executed the Credit Agreement.195 When World Energy allegedly broached the interest rate issue to Air Products, one executive explained the 15% interest rate “may be a mistake.”196 Another explained that rate “did not sound
And World Energy itself agreed the 15% interest rate was not a mistake. In the Forbearance Agreement, executed eight months after the Credit Agreement, World Energy unconditionally acknowledged the Credit Agreement “is legal, valid, binding, and enforceable . . . in accordance with its terms.”200 And it acknowledged that under those terms, it owed no less than $18,460,000 in overdue interest payments.201 Those acknowledgements undermine any theory of mistake here.
Count IV is dismissed.
5. Fraud
Count V asserts a claim for fraud, alleging Air Products promised “a reasonable cure or forbearance agreement” if World Energy executed the Second
- (1) a false representation, usually one of fact; (2) the defendant‘s knowledge or belief that the representation was false, or was made with reckless indifference to the truth; (3) an intent to induce the plaintiff to act or to refrain from acting; (4) the plaintiff‘s action or inaction taken in justifiable reliance upon the representation; and (5) damage to the plaintiff as a result of such reliance.203
Under Court of Chancery Rule 9(b), “[i]n alleging fraud or mistake, a party must state with particularity the circumstances constituting fraud or mistake.”204 To satisfy Rule 9(b), a plaintiff must allege: “(1) the time, place, and contents of the false representation; (2) the identity of the person making the representation; and (3) what the person intended to gain by making the representations.”205
World Energy‘s fraud claim is not premised on false representations of fact. Instead, it is premised on an allegedly false promise—i.e., to “enter into a separate cure or forbearance agreement” if World Energy agreed to execute the Second
“This Court looks with particular disfavor at allegations of fraud when the underlying utterances take the form of unfulfilled promises of future performancе.”208 That is because usually, “statements which are merely promissory in nature and expressions as to what will happen in the future are not actionable as fraud.”209 A claim of promissory fraud thus entails “a heightened burden to plead ‘particularized facts that allow the Court to infer that, at the time the promise was made, the speaker had no intention of keeping it.‘”210 That is, the plaintiff “must plead specific facts that lead to a reasonable inference that the promissor had no intention of performing at the time the promise was made.”211 “[A] party‘s failure to keep a promise does not prove the promise was false when made.”212
With no other specific facts to rely on, World Energy falls back on its argument that Air Products simply “had no intention of providing World Energy relief, as evidenced by its immediate refusal to honor the promise once the Second Amendment was signed.”218 Again, “a party‘s failure to keep a promise” is not “evidence” of an intent to break that promise at the outset.219 World Energy has failed to state a claim for promissory fraud. Count V is dismissed.
B. Irreparable Harm and Balance of the Equities
At oral argument, I told the parties there were several reasons I would not order the mandatory injunction World Energy requested. This case must be dismissed for failure to state a claim; further ruminations on why final relief is not granted stray into dicta. But for the sake of explaining my reasoning for denying the preliminary injunction when I did, I will note that World Energy also failed to demonstrate the sine qua non of injunctive relief: irreparable harm.
“A mandatory injunction will only issue if the plaintiff demonstrates it is necessary to prevent irreparable harm.”220 While not dispositive, the availability of a remedy at law in the form of compensatory damages tips against a finding of irreparable harm.221
World Energy sees irreparable harm from the 12-D Rack‘s current condition in the potential loss of customer relationships, the potential loss of its “first-mover and industry-leader status” in the sustainable aviation fuel market, and damage to both the Paramount Facility and the city‘s economy.222 But by World Energy‘s own
Oral argument injected some question as to whether World Energy can hire somebody else to repair the 12-D Rack and seek to shift the costs to Air Products. There, World Energy asserted that engaging another entity would be infeasible given Air Products’ ownership of the land, structures, and equipment at issue.225 It argued Air Products has cut off access to the Paramount Facility.226 Counsel for Air Products represented that is not true, referencing a letter it sent World Energy on July 8, 2025.227 That letter makes clear “the access offer remains open.”228 I cannot conclude World Energy will suffer irreparable harm absent the requested relief.
III. CONCLUSION
World Energy is not entitled to the mandatory injunctive relief it seeks, and Air Products’ motion to dismiss is GRANTED.
