Plaintiff seeks to enforce a lien against a parcel of ground in the city of St. Louis and the six-story building on it, both belonging to the Christian Peper Tobacco Company, for material furnished to be used in the building. This material consisted of
Our statute gives a person who furnishes “material, fixtures, engine, boiler or machinery for any build: ing, erection or improvements upon land, or for repairing the same, under or by virtue of any contract with the owner or proprietor thereof, or his agent, trustee, contractor, or subcontractor,” a lien on the building, erection or improvement for the materials and machinery. [R. S. 1899, sec. 4203.] The description of the channels or sill castings demonstrates they were not material or machinery within the meaning of that section as construed by the courts. They were not attached
The judgment is affirmed.