196 Pa. 281 | Pa. | 1900
Opinion by
Defendant, in 1895, was the owner of a lot of ground in the city of Scranton, and desired to build upon it a house at a cost of about $2,500. She secured the services of E. G. Worden, a resident architect, to design and prepare a plan and specifications, and also to supervise the work; when the plan was prepared, bids for the work, a frame dwelling, were solicited. There were a number of bidders, and the architect with the consent of Mrs. Connell, accepted that of his brother, M. E. Worden, and the contract was awarded to him; accordingly a writing was executed between them dated August 5, 1895, by which work was to be commenced immediately, and be made to conform to the plans and specifications, subject to changes according to red lines upon the plan made by the architect, and subject, also, to such explanations and changes as should be directed by him; his decision, as to the true “ intent of the drawings and specifications ” was to be conclusive, and thereby become part of the contract; any alterations or additions made during the progress of the work were to be appraised fairly by him and allowance made therefor to the contractor. Free access to the work, for purpose of inspection, while it was going on, by both owner and architect, was stipulated for.
The price, $2,500, was to be paid as follows : $1,200 when the house was under roof; $500 when ready for plastering; $400 when plastering was finished; balance when contract was completed. The contractor commenced work; in less than two months, a dispute as to its interpretation arose between him and Mrs. Connell; this dispute was not referred to the architect, but both parties agreed, in writing, to submit it to arbitrators, one to be chosen by each party, and these two, in case
There was evidence that the contractor undertook in good faith to complete the building in accordance with the terms of the award, but that the owner failed to make payment as stipulated in the agreement, and because of her failure, he stopped the work; he also offered evidence that she directed him to stop, saying she would have the building finished by another builder, but at the same time promised to pay him for the work already done. The defendant alleged the work was not being done according to the contract, and at least insinuated, if she did not directly charge, that the architect was in collusion with his brother, the contractor, to cheapen the work by inferior material and workmanship, and that while she paid him $400 of the first payment, she deferred paying, according to the strict terms of the contract, until he performed the work in accordance with its terms. The evidence was contradictory and the court below submitted it to the jury to ascertain the trufh, instructing them: 1. That if the contractor was in good faith endeavoring to perform his contract, as pointed out by the contract and arbitrators, and that if when he insisted on the payments being made as promised, the defendant ordered him to quit work, then he was entitled to a verdict for the balance of the value of the work and material furnished at the date he stopped. 2. That if they should find, that defendant had substantially complied with her contract, and did not, without excuse, withhold payment justly due him, and did not peremptorily discharged him, they should find a verdict in her favor. Under these instructions, the jury found for plaintiff the balance due him when he quit the work. We have now this appeal by defendant, assigning thirteen errors, four of them to rulings on offers of evidence, and nine to the charge.
Taking up those to the charge of the court first, we fail to discover any substantial error. It will be noticed that the parties, with a full knowledge to the effect of such action, submitted their dispute to arbitrators mutually chosen. It seems,
As to the first assignment, which alleges error in admitting evidence, that the contract had been complied with up to the date Avhen the first payment was due, and that defendant had expressed herself as satisfied therewith, that was an assential part of plaintiff’s case. The submission of the disputed interpretation ' of the plans to arbitrators, in no way relieved him from the duty of performing his contract before that time, and on the interpretation of both parties, he was not at that time in default. The second exception, to admission of testimony, that the owner, at the date of her discharge of the contractor, promised to pay his demand, is not sustained; the testimony tended to show an admission of the justice of his claim then, by the same person who at the trial denied it. As to the testimony of George W. Finn, a witness who had twenty years of experience as a carpenter and builder, that the charge of $693 was a reasonable one for the carpenter work, plumbing and trimming, it was competent and relevant; he had carefully examined the building, and his estimate was evidence, even if only an estimate. True, the exact cost of material, piece by piece, and wages of labor, day by day, would have been, perhaps, more convincing, if such testimony had been produced, but that does not stamp an estimate by an experienced builder
On the whole case we discover no error warranting, a reversal, therefore the judgment is affirmed.