876 N.E.2d 1260 | Ohio Ct. App. | 2007
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *724 {¶ 1} Thomas and Amy Wooten appeal from the judgment of the Champaign County Court of Common Pleas granting summary judgment in favor of Republic Savings Bank.
{¶ 2} On May 22, 1998, the Wootens obtained a convertible construction loan from Republic Savings Bank to build a new house in Champaign County, Ohio. The loan was secured by a mortgage on the real property owned by the Wootens and located at 12233 State Rte. 55, Paris, Ohio. The home was to be constructed on this site by the original contractor, Southwest Builders, Inc. ("Southwest") for $129,220.
{¶ 3} Also on May 22, 1998, the bank paid the first draw in the amount of $6,400 to Southwest pursuant to a settlement statement signed by the Wootens on May 22, 1998. Before disbursing the first draw to Southwest, however, the bank had not received an original contractor affidavit as required by R.C.
{¶ 4} "(a) That the original contractor has paid in full for all labor and work performed and for all materials furnished by the original contractor and all subcontractors, material suppliers, and laborers prior to the date of the closing of the purchase or during and prior to the payment period, except such unpaid claims as the original contractor specifically sets forth and identifies both by claimant and by amount claimed;
{¶ 5} "(b) That no claims exist other than those claims set forth and identified in the affidavit required by division (B)(4) of this section."
{¶ 6} On June 6, 1998, the Wootens authorized a second draw in the amount of $18,423 to be paid to Southwest. The bank received the progress draw-release authorization signed by the Wootens on the same day. Furthermore, Southwest *725
submitted an original contractor's affidavit pursuant to R.C.
{¶ 7} On June 13, 1998, an officer and builder of Southwest, Mr. Gasaway, died. The Wootens were in contact with Southwest several days following Mr. Gasaway's death, at which time they were informed that construction would be delayed for two to three months. Southwest performed no further work on the Wootens' property.1
{¶ 8} On June 24, 1998, the bank paid the second draw in the amount of $10,700 to Southwest. The bank made no subsequent draw payments on the Wootens' construction loan to Southwest after this June 24, 1998 disbursement.
{¶ 9} Early in July 1998, the Wootens met with the bank's agent, Craig R. Johnson, to discuss the status of their construction loan account following the death of Mr. Gasaway. Johnson told the Wootens that they could continue to build, acting as their own contractors; they could find another contractor; or they could continue with Lou Gasaway, Mr. Gasaway's wife, as builder/contractor for Southwest. Moreover, in response to a question regarding the Wootens' authorization for payment from the second draw, Johnson stated that all assets of Southwest were frozen. The Wootens eventually decided to act as their own contractors and continue building.
{¶ 10} Subsequent to their meeting with Johnson, the Wootens received a receipt from the bank indicating that Southwest had been paid from the second draw on June 24, 1998. Consequently, they contacted the bank by telephone to discuss that payment. The Wootens spoke to the bank's representative, Mr. Hyland, who informed them that they should seek advice from an attorney. It wasn't until the following year that they sought the legal advice of attorney Anthony Kohler. On April 9, 1999, Kohler sent a letter to Mr. Hyland regarding a March 23, 1999 conversation in which they discussed claims against Southwest directly involving the bank. Mr. Wooten testified in a deposition that he had met with Kohler prior to April 9, 1999, concerning the dispute with the bank.
{¶ 11} Four mechanics' liens were placed on the Wootens' property by materialmen and subcontractors. First, Julie Schwartz, d.b.a. C.E. Ment, filed a mechanics' lien on July 17, 1998, for materials and labor provided between June 1 and June 3, 1998, in the amount of $2,308.66. The Wootens received a copy of the lien on July 17, 1998. They also received a letter from the company in January 1999, indicating that a lien had been placed on the property. Following receipt of the letter, the Wootens contacted the lienholder. Next, Ernst Enterprises recorded its lien on July 28, 1998. The lien stated that it covered materials *726 furnished on June 2, 1998, in the amount of $995.46. The Wootens received a copy of this lien on July 28, 1998. They also discussed the lien with the company's secretary. Third, Bryce Hill, Inc., recorded a lien on the property on August 14, 1998. The lien indicated that it was for labor and materials provided between June 2 and June 3, 1998, in the amount of $1,162.77. The Wootens received their copy of the lien on August 14, 1998. Finally, Easter Masonry Construction Company recorded its lien on August 14, 1998. The lien stated that the last date the company furnished materials and labor was June 20, 1998, in the amount of $1,725. The Wootens received a copy of this lien on August 14, 1998. They also discussed the lien with a representative from the company following receipt of their copy. In total, the Wootens paid $6,191.89 to release all of the mechanics' liens from their property.
{¶ 12} The Wootens filed a complaint against the bank on May 19, 2003, including causes of action for negligence, gross negligence, unjust enrichment, breach of obligations of good faith and fair dealing, breach of contract, breach of implied contract, promissory estoppel, fraud, and constructive fraud. The Wootens claimed that subsequent to the death of Mr. Gasaway and the bankruptcy of Southwest Builders, Inc., and after being advised that their construction loan account with Southwest was "frozen," the bank paid Southwest $10,700 from the Wootens' account.2 Specifically, the Wootens alleged that the bank failed to control payment of the construction phase and assure that subcontractors and material suppliers were paid for labor and material. Furthermore, they argued that the bank's agent, Craig Johnson, made a fraudulent representation that Southwest's assets were frozen following the death of Mr. Gasaway and that the bank would not pay draws without assuring potential lienholders were paid. As part of this fraud, the Wootens contend that the bank negligently disbursed $10,700 from the second draw to Southwest. According to the Wootens, the earliest date at which they discovered or should have discovered the alleged fraud of the bank was December 2002. At that time, they received a letter from the Federal Deposit Insurance Corporation acknowledging the receipt of their complaint against the bank and indicating that the bank was pursuing internal discovery and a proposed resolution of the matter.
{¶ 13} Both parties filed a motion for summary judgment. On June 30, 2006, the trial court granted the bank's motion. It is from this decision that the present appeal comes. *727
{¶ 14} As an appellate court, our review of trial court decisions on summary judgment is de novo, which means that "we apply the standards used by the trial court."Brinkman v. Doughty (2000),
{¶ 15} Upon review of the record, we find that the Wootens' assignments of error are without merit. Accordingly, the judgment of the trial court is affirmed.
{¶ 17} Under their second assignment of error, the Wootens contend that the trial court erred in holding that statutory immunity from liability for all claims except gross negligence and fraud is not dependant upon compliance with the affidavit procedure in R.C.
{¶ 18} R.C.
{¶ 19} "(a) That the original contractor has paid in full for all labor and work performed and for all materials furnished by the original contractor and all subcontractors, material suppliers, and laborers prior to the date of the closing of the purchase or during and prior to the payment period, except such unpaid claims as the original contractor specifically sets forth and identifies both by claimant and by amount claimed;
{¶ 20} "(b) That no claims exist other than those claims set forth and identified in the affidavit required by division (B)(4) of this section."
{¶ 21} Furthermore, R.C.
{¶ 22} Here, the bank paid the first draw to Southwest in the amount of $6,400 on May 22, 1998, without first obtaining a contractor affidavit per R.C.
{¶ 23} The Ohio Supreme Court decidedThompson Elec, Inc. in the context of whether lending institutions owe a duty to a subcontractor to obtain affidavits under R.C.
{¶ 24} In Takach, the court held that lending institutions have a statutory duty to homeowners not to make any payments to the original contractor until the contractor has given the lending institution the required affidavits.
{¶ 25} Blanchester Lumber Supply, Inc.v. Cardinal State Bank (1988),
{¶ 26} In this case, the first draw was paid to Southwest in the amount of $6,400 on May 22, 1998, pursuant to the Wootens' authorization of the settlement statement. The bank paid this draw without obtaining a contractor affidavit, and thus, was in violation of its statutory duty under R.C.
{¶ 27} Furthermore, with the exception of Easter Masonry's lien filed on August 14, 1998, all liens attached to the property between July and August 1998 provided that they covered labor and materials after May 22, 1998. Easter Masonry's lien states that it was for materials and labor furnished prior to June 20, 1998, in the amount of $1725. In light of the settlement statement and progress report, it may reasonably be inferred that Easter Masonry provided its materials and labor subsequent to the first draw payment on May 22, 1998.
{¶ 28} Finally, we note that the complaint alleges that two draws were made on or about June 5, 1998. The Wootens argue that these draws were not used to pay materialmen, amounting in costs of $6,191.89 to pay for the release of the mechanics' liens. They also claim that the draws resulted in the improper payment of $10,700 after the death of the original contractor and the advice from the bank that Southwest's account was frozen. It is apparent from the complaint that the bank's failure to obtain a contractor's affidavit with the first draw payment on May 22, 1998, did not result in any of the damages the Wootens are seeking.
{¶ 29} Thus, we find no merit in any of the claims the Wootens have alleged against the bank regarding improper disbursement of funds from the first draw on May 22, 1998. Although the trial court misinterpreted ThompsonElec, Inc. in holding that R.C.
{¶ 31} The complaint alleges that the bank's payment of $6,400 from the first draw on May 22, 1998, without first obtaining an original contractor's affidavit and payment of $10,700 from the second draw on June 24, 1998, amounted to gross negligence. Generally, the Wootens claim that the bank failed to properly assure that Southwest had paid for all labor and materials before disbursing funds to Southwest from the construction loan account. The trial court applied the four-year limitations period under R.C.
{¶ 32} R.C.
{¶ 33} "(A) For trespassing upon real property;
{¶ 34} "(B) For the recovery of personal property, or for taking or detaining it;
{¶ 35} "(C) For relief on the ground of fraud;
{¶ 36} "(D) For an injury to the rights of the plaintiff not arising on contract nor enumerated in sections
{¶ 37} "(E) For relief on the grounds of a physical or regulatory taking of real property. *731
{¶ 38} "If the action is for trespassing under ground or injury to mines, or for the wrongful taking of personal property, the causes thereof shall not accrue until the wrongdoer is discovered; nor, if it is for fraud, until the fraud is discovered."
{¶ 39} In Investors REIT One, the Ohio Supreme Court stated that "R.C.
{¶ 40} Here, the Wootens' gross-negligence claim is governed by R.C.
{¶ 41} We note that the Wootens argued in their appellate brief that R.C.
{¶ 43} First, the parties and the trial court do not disagree that the statute of limitations for fraud claims is four years pursuant to R.C.
{¶ 44} Next, in Bossey, this court determined that reasonable minds could differ on the question of when an appellant discovered the fraud on the part of a car dealership. Id. at 669,
{¶ 45} Based on their interpretation ofBossey, the Wootens are asking this court to override the summary-judgment standard and make every factual question that may arise in a particular case one solely for a jury to determine. We disagree. Instead, we believe it is fundamental to follow the proper standard of review: Summary judgment is appropriately granted when (1) there is no genuine issue as to any material fact, (2) the moving party is entitled to judgment as a matter of law, and (3) reasonable minds can come to but one conclusion, and that conclusion is adverse to the party against whom the motion for summary judgment is made, who is entitled to have the evidence construed most strongly in his favor. See Harless v. Willis Day Warehousing Co.
(1978),
{¶ 46} Thus, this court's inquiry becomes whether a genuine issue of material fact exists as to when the Wootens reasonably should have discovered the alleged fraud or were put on sufficient notice of the fraud that would lead a reasonable person to immediately begin an investigation. Doyle v. OhioCo. (Sept. 9, 1994), Clark App. No. 94-CA-16,
{¶ 47} Here, the fraudulent conduct alleged by the complaint is Craig Johnson's representation that the Wootens' construction account with Southwest would be frozen after the death of Mr. Gasaway. The Wootens argue that in spite of this representation, the bank paid $10,700 to Southwest from the second draw on June 24, 1998. According to the Wootens, they did not become aware of the bank's allegedly fraudulent conduct until they were notified by the FDIC in December 2002. In contrast, the record indicates that the Wootens received a receipt for the second draw payment in the amount of $10,700 shortly after their July 1998 meeting with the bank's agent, Johnson. They also received copies of the mechanics' liens on their property between July and August 1998. Moreover, the Wootens sought the legal advice of attorney Anthony Kohler, who sent a letter to Mr. Hyland of Appellee Republic Savings Bank on April 9, 1999, regarding a prior conversation in which they discussed claims against Southwest directly involving the bank. Mr. Wooten testified that he had met with Kohler prior to April 9, 1999, concerning the dispute with the bank.
{¶ 48} The trial court found that reasonable minds could come to but one conclusion — the Wootens should have discovered the fraud prior to May 19, 1999. We agree. We find that the Wootens had a duty of inquiry when they received a receipt for the second draw payment in the amount of $10,700 early in July 1998 and notice of the mechanics' liens attached to their property, as these events constituted reasonable opportunities to discover the misrepresentation. Thus, we find that the trial court did not err in holding that the Wootens discovered or should have discovered the bank's alleged fraud prior to May 19, 1999. The fourth assignment of error is overruled.
{¶ 50} "1. When did Wooten discover the fraudulent activities of Bank?
{¶ 51} "2. Did Bank make distribution to the contractor contrary to Ohio law? *734
{¶ 52} "3. Did Bank charge Wooten's account for distribution to the contractor after the death of contractor and after Wooten had been advised of the death and that the account was frozen? Was that act fraudulent or negligent?
{¶ 53} "4. Did Wooten suffer damages, and if so, how much?
{¶ 54} "5. Did Bank have a fiduciary duty to Wooten and if so, was that fiduciary duty violated?
{¶ 55} "6. Is Bank estopped from raising defenses to fraud because of its violation of higher law, and its promises to Wooten (i.e. promissory estoppel)?
{¶ 56} "7. Did Bank commit fraud or constructive fraud?
{¶ 57} "8. Did Bank violate and breach a lending contract with Wooten?
{¶ 58} "9. Was Bank unjustly enriched by its actions herein?
{¶ 59} "10. Did Bank breach its obligation of good faith and fair dealing pursuant to §
{¶ 60} In the alternative, the Wootens contend that a determination that the bank was not immunized from liability for all claims supports a finding of summary judgment in their favor.
{¶ 61} Upon review, we find that the questions of fact, in addition to the questions of law, that the Wootens assert remain unresolved have been answered and/or rendered moot by our disposition of the present matter. The record on appeal demonstrates that there are no genuine issues of material fact and that the bank is entitled to judgment as a matter of law. Civ.R. 56(C). Accordingly, the Wootens' first and fifth assignments of error are overruled.
{¶ 62} For the foregoing reasons, appellants' assignments of error are over-ruled. The judgment of the trial court is affirmed.
Judgment affirmed.
FAIN and DONOVAN, JJ., concur.