Roy Woolard was injured by the collapse of an aerial work platform (or “lift”). He subsequently filed this diversity action against JLG Industries, Inc. (“JLG”), the lift’s manufacturer, and Young Enterprises (“Young”), the lift’s owner at the time of the accident, alleging the defective manu *1164 facture, design, distribution, and sale of the lift. Mr. Woolard later joined Primeco Inc., the distributor that sold the lift to Young, alleging Primeco and its predecessor-in-interest, American Hi-Lift (together, “Primeco”) failed to properly maintain and repair the lift and failed to warn that the lift was unsafe. Young, as a third-party plaintiff, filed a cross-claim against Primeco seeking indemnification for liability based on theories of breach of contract, negligence, and strict products liability.
Prior to trial, Mr. Woolard settled his products liability claim against JLG. His negligence claims against Young and Pri-meco proceeded to trial. Specifically, Mr. Woolard asserted that (1) Young owed him a duty to maintain, inspect, and provide safe and reliable equipment; (2) Young breached that duty through its failure to perform the required inspections; (3) Pri-meco, as the maintenance agent under a Distributor and Sales Agreement (the “Distributor Agreement”) with JLG, was responsible for maintaining and repairing the lift; (4) Primeco, having performed repairs to an electrical switch shortly before the accident, knew that the lift was unsafe, and failed to notify either Mr. Woolard, or his employer, Young Electric, of the lift’s condition or of the need for annual inspection of the lift; (5) Primeco failed to notify Young of the required annual inspections and failed to perform the required annual inspections; (6) Primeco had a duty to Mr. Woolard and his employer to inform them of the need for inspection of the lift as a third-party beneficiary of the Distributor Agreement; and (7) Pri-meco’s predecessor installed unsafe replacement pins into the lift, the failure of which contributed to the accident.
At trial, the jury found that Young was forty percent negligent and that Primeco was sixty percent negligent, and awarded Mr. Woolard $1.5 million in damages. The district court entered judgment for Mr. Woolard, reducing his damages by $300,-000.00 (the amount of his settlement with JLG) and calculated a prejudgment interest award based on the reduced figure.
Primeco now appeals, arguing that the district court erred in denying its motion for judgment as a matter of law and its motion for a new trial. Primeco raises the following arguments and defenses to support its claim that its alleged negligence did not cause the accident: (1) Primeco did not breach its common law duty to exercise ordinary care in repairing and maintaining the lift; (2) because Mr. Woolard was not a third-party beneficiary of the Distributor Agreement, the Distributor Agreement did not impose a contractual duty upon Primeco to warn of the lift’s dangerous condition; (3) Primeco was not the proximate cause of Mr. Woolard’s injuries; (4) the district court erred when it denied Primeco’s motion for remittitur; and (5) the district court improperly altered one of the jury instructions after closing arguments. Mr. Woolard cross-appeals, arguing that the district court erred in calculating prejudgment interest under Oklahoma law.
In addition, Young, as cross-appellant, appeals on its cross-claims against Prime-co. During this appeal, Young settled all of its claims with Mr. Woolard for $400,-000.00. Young argues that it was entitled to either judgment as a matter of law and restitution in the form of indemnification or contribution based on its cross-claims against Primeco. Young’s cross-claims sought to hold Primeco liable for any claims Mr. Woolard successfully lodged against Young based on theories of negligence, strict products liability, and breach of contract. In the alternative, Young argues that the district court erred when it failed to properly instruct the jury on these cross-claims.
We exercise jurisdiction under 28 U.S.C. § 1291 and affirm in part and reverse in part. In particular, we hold that the district court properly denied Primeco’s motion for a judgment as a matter of law and its motion for a new trial. Further, we hold that the district court did not err in amending the jury instructions after closing arguments. In Mr. Woolard’s cross- *1165 appeal, we hold that the district court improperly calculated prejudgment interest, and we remand for recalculation. Finally, on Young’s appeal of its cross-claims, we hold that the district court properly denied the motion for judgment as a matter of law and did not err in refusing Young’s requested instructions on its cross-claims.
I. BACKGROUND
JLG is the designer and manufacturer of the lift that collapsed and caused Mr. Woolard’s injuries. The lift consisted of a base, a telescoping arm (or “boom”), and a basket attached to the end of boom. With a worker in the basket, the boom could extend outward and upward 110 feet and swing side to side, providing a stable platform.
On April 2, 1996, Mr. Woolard was working as a journeyman electrician for a private electrical repair company. He had been hired as a subcontractor for a construction project at Altus Air Force Base in Altus, Oklahoma. In connection with this project, Mr. Woolard’s employer leased two JLG aerial hits from co-defendant Young. While working on the project, Mr. Woolard was injured when one of the lifts collapsed, causing him to fall approximately seventy feet.
At trial, Mr. Woolard submitted evidence explaining the collapse of the boom. Mr. William Munsel, a mechanical engineer and metallurgist, testified that the boom contained a defective sheave pin that failed, causing the collapse of the boom. See Aplts’ App. vol. VIII, at 174, 177-80. He explained that two pins hold a single eye bolt in place and that this mechanism is critical to the telescoping of the boom. See id. at 180. According to Mr. Munsel, one of the sheave pins was made of an inferior, chrome-plated soft metal. See id. at 184-86. The recommended JLG pin is made of hardened steel. See id. at 184-85. Mr. Munsel concluded that the soft-metal wore excessively, causing the pin’s eye bolt to fail and the boom to collapse. He testified that the difference between a proper hardened steel pin and a soft metal pin was visually obvious. See id. at 185-86.
Mr. Woolard argued that Primeco, which rents, sells, and services industrial equipment, was responsible for the accident. In 1989, Primeco purchased the lift from its manufacturer, JLG. Mr. Woolard contended that Primeco negligently rebuilt the lift and installed the inferior soft metal pins. He presented evidence that Primeco performed a complete overhaul of the unit in 1990. See id. at 280. As part of the overhaul, Primeco replaced the factory-installed “sheave pins” with new pins. See id. vol. IX, at 296-97. In 1993, Primeco sold the lift to Young. Although Primeco asserted that it used JLG-authorized parts during the overhaul, Mr. Woolard presented evidence indicating that Primeco may not have received the hardened steel metal pins it ordered and that it used one of the chrome-plated soft-metal pins instead. See id. vol. VIII, at 280-84.
Further, Mr. Woolard argued that Pri-meco failed to notify him or his employer about the need for an annual inspection, which would have revealed the defects. Mr. Woolard submitted evidence that, on March 7, 1996, just a few weeks before the lift collapsed, Young hired Primeco to service the lift. Primeco’s field service mechanic, Philip Barker, traveled to Altus, Oklahoma and repaired an electrical switch that was malfunctioning. See id. vol. VII, docs. 60 and 68 (Primeco’s held service report and billing invoice); vol. VIII, at 88, 91 (testimony of Phillip Barker). The repairman testified that the lift was in need of further repairs (in addition to the malfunctioning switch) and an annual inspection. He testified that in his opinion, even with the switch repaired, the lift should have been taken out of service. See Aplts’ App. vol. VIII, at 105. However, he did not advise anyone of his opinions or observations. See id. at 94.
On this point, Mr. Woolard submitted evidence that the manufacturer, JLG, advised that the lift be inspected annually and provided its distributors with maintenance manuals and annual machine inspection forms. See id. vol. VI, doc. 18; vol. *1166 VII, doc. 24. Mr. Munsel testified that JLG’s manual requires that, as part of an annual inspection, the sheave pins must be checked for excessive wear and that, had this been done, the worn pin would have been discovered and replaced. See id. vol. VIII, at 192-93. Further, Mr. Barker testified that to check the pins for wear, the inspector “could physically look, pull and loosen the chain off and examine for wear and mold in them.” Id. at 108; see id. at 95. Accordingly, Mr. Woolard argued that, had Primeco conducted an annual inspection or notified him or his employer of the need for an annual inspection or of the need for the boom’s removal from service, the defective pins would have been discovered and the accident prevented.
Additionally, Mr. Woolard argued that Primeco breached a contractual duty to inform him and his employer that the lift was unsafe. Primeco was an authorized distributor for JLG, and the two were parties to the Distributor Agreement. The Distributorship Agreement provided, among other things, that Primeco “shall notify the owner and user of said product” if Primeco became aware that “any product is being improperly operated or that any Product requires maintenance or service for its continued safe operation.” Id. vol. VII, doc. 32 at ¶ 11-A. Mr. Woolard contended that he and his employer, as “users,” were third-party beneficiaries of the Distributor Agreement between Pri-meco and JLG and, as such, Primeco had a duty to warn each of them of the need for further repairs and an annual inspection.
Mr. Woolard also argued that Young’s negligence caused his injuries. He presented testimony from Charles Smith, a superintendent for Young, who stated that he knew that annual inspections were necessary. Mr. Woolard maintained that Young failed to perform the required inspections and failed to assure that these inspections were completed.
Primeco argued that it was not responsible for the accident. First, it presented evidence that the pins it installed during the overhaul were (1) new pins, (2) obtained from an authorized supplier of JLG parts, and (3) came with JLG tags attached. See id. vol. IX at 290-91, 305-06, 313-14, 525, 537. Primeco presented testimony that a purchaser of a manufacturer’s authorized parts should not be required to verify that the integrity of the parts meets the manufacturer’s standards. See id. at 525. Thus, Primeco argued, it fulfilled its duty by installing what it believed to be JLG-authorized parts.
In addition, Primeco submitted evidence that it could not have discovered the worn pins. Primeco’s expert testified that because the pins were located on the inside of the frame of the boom, Mr. Barker’s performing repairs on the electrical switch would not have revealed that the pins needed to be replaced. See id. vol. VIII, at 89, 92. In addition, Primeco’s expert testified that an annual inspection would not have revealed the worn pins either. According to the expert, an annual inspection would include an assessment of the functioning of the boom chain assembly and the telescoping of the boom. See id. at 82-83. Any wobble or play in one of the chain sheaves would alert the inspector of a problem warranting further inquiry by disassembling part of the boom. See id. at 82-83, 108-09. However, absent observation of such wobble or play, the inspector was not required to disassemble the boom to check the pins for wear.
Primeco also noted that the JLG owner’s manual, as well as the American National Standards Institute (“ANSI”), which sets out the “industry standards,” did not require or suggest a complete dismantling of the lift during an annual or periodic inspection. See id. vol. VI, doc. 17; vol. VIII, at 108, vol. IX, at 429-30, 437-38, 446-47, 452, 478-79, 492, 543. Finally, Pri-meco submitted evidence that the disas-sembly necessary to discover the pins would “inject” contamination into the parts and compromise the tolerance of the equipment. See id. vol. IX, at 543-44.
At the close of both the plaintiffs case and its own case, Primeco moved for judg *1167 ment as a matter of law, arguing that it had not breached its duty to exercise ordinary care in repairing and maintaining the boom, that the Distributor Agreement did not impose additional duties upon Primeco, and that, even if Primeco did have such a duty, the evidence failed to establish that Primeco’s actions were the cause of the accident. In turn, the district court denied both motions.
The case was submitted to the jury, which found that Young was forty percent negligent, that Primeco was sixty percent negligent, and awarded Mr. Woolard $1.5 million in damages. Although Young.had asserted cross-claims against Primeco seeking contribution or indemnification, the district court did not instruct the jury on those cross-claims. The jury thus made no findings regarding Primeco’s liability, if any, to Young.
Primeco then filed a combined post-trial motion that moved for the following: a judgment as a matter of law, a new trial, and/or alteration of the judgment. In its motion for judgment as a matter of law, Primeco argued that it did not breach its duty to exercise ordinary care and that Primeco owed no duty to Mr. Woolard under the Distributor Agreement. In its motion for a new trial, Primeco argued that it was entitled to a new trial because: (1) even if Primeco had a legal duty to Mr. Woolard, the evidence failed to establish Primeco was the cause of the accident; (2) the evidence failed to support the jury’s $1.5 million damage award (in the alternative arguing for a remittitur of damages consistent with the evidence); and (3) the jury was improperly instructed. Finally, Primeco argued that, if the district court denied these motions, Primeco was entitled to a set off for the $300,000.00 JLG settlement.
The district court denied Primeco’s motion for judgment as a matter of law and its motion for a new trial. However, the district court agreed that Primeco was entitled to a set off for the $300,000.00 settlement with JLG. Accordingly, the district court reduced the $1.5 million judgment to $1.2 million.
Young filed a motion analogous to Pri-meco’s for an amendment of the entry of the judgment. In addition, Young sought a judgment as a matter of law and a new trial pursuant to Federal Rules of Civil Procedure 50 and 59 based on the trial judge’s failure to instruct on its cross-claim. The district court amended the amount of the judgment, as noted above, and denied the remainder of Young’s motions.
On appeal, Primeco argues that the district court erred in denying its motion for judgment as a matter of law and its motions for a new trial or remittitur. Mr. Woolard cross-appeals, arguing that the district court erred in calculating prejudgment interest under Oklahoma law. In addition, co-defendant Young, as cross-appellant, appeals on its cross-claims against Primeco. For the reasons set forth below, we affirm each of the district court’s decisions, with the exception of its calculation of prejudgment interest; we remand this claim for recalculation in accordance with this opinion.
II. DISCUSSION
A. Primeco’s appeal
On appeal Primeco argues that the district court should have granted its motion for judgment as a matter of law under Fed.R.Civ.P. 50(a)(1) and its motions for a new trial under Fed.R.Civ.P. 59. In particular, Primeco advances four distinct challenges to the district court’s denial of these motions. It argues that the district court erred in concluding that: (1) a reasonable jury could find that Primeco breached its duty to Mr. Woolard as a third-party beneficiary of the Distributor Agreement between Primeco and JLG; (2) a reasonable jury could also find that Pri-meco breached its common law duty of ordinary care to Mr. Woolard; (3) a reasonable jury could find that Primeeo’s acts were the proximate cause of Mr. Woolard’s *1168 injuries; and (4) the $1.5 million damage award is supported by the evidence. Pri-meco also argues that the district court erroneously altered an instruction before submitting the case to the jury.
When we review a district court’s denial of a motion for judgment as a matter of law, federal law governs whether a judgment as a matter of law is appropriate.
See Brown v. McGraw-Edison Co.,
As to Primeco’s motion for a new trial, “[fjederal law governs the granting or denial of a motion for a new trial in diversity actions in federal court.”
Blanke v. Alexander,
Mindful of these standards, we proceed to examine Primeco’s arguments that it did not breach a contractual or common law duty. Then, we turn to its arguments regarding proximate cause and the amount of the damages award.
1. Breach of Duty Arising under Contract
Under Oklahoma law, to establish a claim based on negligence, the plaintiff must establish (a) the existénce of a duty owed by defendant to plaintiff; (b) that the defendant failed to perform that duty; and (c) that the defendant’s failure caused the plaintiff injury.
See Krokowski v. Henderson Nat’l Corp.,
Under the Distributor Agreement, Pri-meco agreed to provide a variety of services, including installation and inspection services. Specifically, Primeco agreed “to promptly render installation and inspection service ... with respect to all Products and Parts Sold to a customer....” Aplts’ App. vol. VII, doc. 32, at ¶ 5.E. The Distributor Agreement defines the “Installation and Inspection Services” to comprise: “Inspection, starting and testing ... of Products and Parts, as specified in the applicable installation and inspection report forms, [illegible] to insure successful operation and resultant customer satisfaction....” Id. ¶ 1. This section suggests that Primeco’s duty extended beyond simple installation of authorized parts and extended to its customers.
Oklahoma law provides that a tort may arise in the course of the performance of a contract and that tort may then be the basis for recovery even though it is the contract that creates the relationship between the parties.
See Hall Jones Oil Corp. v. Claro,
Conduct that is merely a breach of contract is, of course, not a tort. Nevertheless, a tort may arise in the course of the performance under a contract so that a breach of the contract may not be the gravamen of the action, but an intentional wrong may be. The contract in such case is the mere incident creating the relation furnishing the occasion for the tort and giving rise to an action ex delicto.... [It] is well established that, where a breach of contract is permeated with tort, the injured person may elect to waive the contract and recover in tort; or, differently stated, although the relation between the parties may have *1169 been established by contract, express or implied, if the law imposes certain duties because of the existence of that relation, the contract obligation may be waived and an action in tort maintained for the violation of such imposed duties.
Id. at 861-62 (citations omitted) (emphasis supplied). Under these principles, the district court concluded that there was sufficient evidence that Primeco owed Mr. Woolard a duty, ex delicto, under the Distributor Agreement between JLG and Pri-meco because Mr. Woolard was a third-party beneficiary of the contract.
A person may sue for damages resulting from the breach of a contractual obligation, even though he was not a party to the contract and had no knowledge of it when it was made, if he was an intended beneficiary of that obligation.
See Hesser v. Central Nat’l Bank & Trust Co.
Whether an individual is a third-party beneficiary of a contract is determined by the intent of the contracting parties.
See G.A. Mosites Co. v. Aetna Cas. & Sur. Co.,
Primeco argues that “it is obvious from the contractual language” that Primeco and JLG did not intend to benefit any third parties. Primeco’s First Br. at 23. In support of its argument, Primeco asserts that Mr. Woolard is not directly mentioned in the Distributor Agreement.
After reviewing the Distributor Agreement, we agree with the district court that Mr. Woolard is expressly and unambiguously a third-party beneficiary of the contract and, as such, entitled to enforce the duty created thereunder. The relevant provision of the contract states:
11. Product Safety
A. Distributor [Primeco] and JLG agree that product safety and improvement are goals to which each is committed .... As and to the extent that Distributor becomes aware that any Product is being improperly operated or that any Product requires maintenance or service for its continued safe operation, Distributor shall notify the owner and user of said Product of such and use its best efforts to have the owner and user of the Product contact the same.
Aplts’ App. vol. VII, at doc. 32, at ¶ 11.A.
It is clear from this provision that the parties intended the owners and users of JLG products to be a beneficiary of Prime-co and JLG’s commitment to safety. The Distributor Agreement expressly states terms that the distributor “shall notify the owner and user” if it is aware that a JLG product requires maintenance or service. Id. It is undisputed that Mr. Woolard and the company for which he was working at the time of the accident were users of the lift.
Primeco also argues that the Distributor Agreement’s non-assignment clause, which states that Primeco’s obligations under the agreement cannot be assigned, supports its argument that the contract conferred no third-party beneficiary status. The Distributor Agreement’s non-assignment clause provides the following language:
*1170 This Agreement shall be binding upon, and shall enure to the benefit of the parties and their respective heirs, successors, and assigns; provided, however that [Primeco]’s rights and obligations hereunder cannot be assigned, in whole or in part, directly or indirectly, by [Pri-meco], by operation of law or otherwise, to any person, firm or corporation without the prior written consent of JLG.
Id. ¶ 12.F.
Although the assignment of a contract will confer rights and obligations upon a third-party, the assignment is unrelated to one’s status as a third-party beneficiary. The non-assignment clause serves to protect JLG and its successors from Primeco’s unauthorized transfer of rights and obligations and does not speak to the intended third-party beneficiary status conferred upon Mr. Woolard in paragraph 11 of the Distributor Agreement.
2. Breach of Common Law Duty
Regardless of the third-party beneficiary theory, there is another source of liability, that being Primeco’s common law duty to exercise ordinary care. Aside from the provisions of the Distributor Agreement, Primeeo also argues that the district court erred in concluding that a reasonable jury could properly find that it breached its common law duty to exercise ordinary care in maintaining and inspecting the lift. Pri-meco addresses both instances of alleged negligence identified by Mr. Woolard: (a) the 1990 overhaul of the lift, when Prime-co’s predecessor replaced the factory installed sheave pins with new pins; and (b) Primeco’s failure to take the lift out of service and conduct an annual inspection after Mr. Barker repaired the electrical switch in March 1996.
According to Primeeo, it did not breach its duty to Mr. Woolard on either occasion. Primeeo maintains that, in 1990, its predecessor-in-interest installed proper replacement pins in the lift, and that, in March 1996, its repairman exercised ordinary care in repairing the electrical switch. As to the latter instance of alleged negligence, Primeeo acknowledges that it did not take the lift out of service or conduct an annual inspection. However, it maintains that an annual inspection would not have revealed the defect in the pins.
Under Oklahoma law, “the existence of a duty depends on the relationship between the parties and the general risks involved in the common undertaking.”
Wofford v. Eastern State Hosp.,
In the context of performing repairs, “one who is paid to repair [chattels] owes a duty of care to both the owner ... and to the general public to assure that the repair is properly performed or the owner is warned of its dangerous condition, where the dangerous condition is discoverable in the exercise of ordinary care.”
Delbrel v. Doenges Bros. Ford, Inc.,
*1171
Importantly, that duty "to inspect and test" the chattel, see Stuckey,
Indeed, chattels are often made by independent contractors from materials furnished by their employers. In such a case, the contractor is not required to sit in judgment on the plans and specifications or the materials provided by his employer. The contractor is not subject to liability if the specified design or material turns out to be insufficient to make the chattel safe for use, unless it is so obviously bad that a competent contractor would realize that there was a grave chance that his product would be dangerously unsafe. The same is true in regard to materials furnished by the employer.
Restatement (Second) of Torts (1965) § 404 cmt. a. Our sister circuit has noted, "it would ... be a singular doctrine" if we were to hold that an installation contractor had a duty to inform its customers that there might be some defects in the equipment, "`in the absence of circumstances whereby any dangerous defects were known or readily foreseeable by a reasonably prudent contractor.'" Ackerman v. York Corp.,
Applying these principles, we first conclude that the district court properly ruled that a jury could reasonably find that Primeco breached its duty of ordinary care to Mr. Woolard when its predecessor conducted the overhaul of the lift in 1990. Although Primeco offered evidence that its predecessor replaced the original pins with JLG-authorized pins, Mr. Woolard presented evidence to controvert Primeco's contentions. In particular, Mr. Woolard presented expert testimony that one of the sheave pins installed by Primeco's predecessor was made of an inferior chrome-plated soft metal rather than the authorized hardened steel. According to Mr. Woolard's expert, the difference between a proper hardened steel pin and a soft metal pin was visually obvious. Relying on this testimony, a jury could reasonably conclude that Primeco's predecessor failed to exercise ordinary care by installing a defective sheave pin in the lift.
We reach a almilar conclusion as to Primeco's failure to conduct an annual inspection after repairing the electrical switch in March 1996. As noted above, Primeco did present evidence suggesting that during an annual inspection, disas-sembly of the lift was not required. According to Primeco's witnesses, an inspector would test the sufficiency of the pins by assessing the functioning of the boom. Primeco's evidence indicated that, because its mechanic observed no obvious wobble or play in the chain sheaves after he repaired the electrical switch, an annual inspection (if conducted prior to the accident) would not have led the inspector to disassemble the lift and discover the defective pin.
However, Mr. Woolard presented substantial evidence to rebut Primeco's theory of the scope of an annual inspection. In particular, JLG's Annual Machine Inspection Report requires that an inspector check all "pins, shafts, bearings . chains and sprockets (or sheaves) for proper installation, tightness, excessive wear, cracks or distortion." Apits' App. vol. VII, doe 24 (emphasis added). JLG's operating manual provided similar instructions. See id. vol. VI, doe. 17, at 1860 ("Check pins for damage or excess wear."). In addition, Primeco's mechanic testified that to check the pins for wear, they would need physical examination. Contrary to Primeco's theory, the Report does not cx- *1172 plain that such inspection of the pins should be done indirectly — ie. by checking the functioning of the boom. This evidence is sufficient for the jury to have concluded that an inspection, required by the JLG Annual Inspection Report and the JLG maintenance manual, would have revealed the excessively worn sheave pin.
The record thus supports the inference that Primeco owed Mr. Woolard a duty “as a person who could foreseeably be injured by [its] negligent failure to repair or warn against a dangerous condition concerning the [lift].”
Delbrel,
3. Proximate Cause
Primeco also contends that, even if the jury could have properly found that it breached its duties to Mr. Woolard under the Distributor Agreement and the common law, the evidence is still insufficient to support the conclusion that Primeco’s breach of those duties proximately caused the accident. In particular, Primeco argues that: (1) Primeco was not a proximate cause of Mr. Woolard’s injuries because an annual inspection would not have revealed the defective pin, and (2) Young (rather than Primeco) was the proximate cause of those injuries because Young knew of the need for annual inspections and allowed the lift’s continued use.
Under Oklahoma law, a proximate cause is defined as one that, “ ‘in the natural and continuous sequence, produces [the plaintiffs] injury and without which the injury would not have happened.’ ”
Dirickson v. Mings,
The first of these arguments — that an annual inspection would not have revealed the defective pin in the lift — reprises the same points advanced by Primeco in challenging the evidence regarding the breach of its duties to Mr. Woolard. For the reasons set forth above, we conclude that the jury could have reasonably rejected Primeco’s contention that an annual inspection would not have revealed the defective pin. In light of the additional evidence presented by Mr. Woolard (that Primeco’s predecessor installed the defective pin, that Primeco had a duty under the Distributor Agreement to inform the lift’s owner and user of the need for maintenance or service and that Primeco knew of the need for an annual inspection but did not perform one), the record supports the inference that Primeco proximately caused Mr. Woolard’s injuries.
Primeco’s second proximate cause argument — that Young rather than Prime-co was the proximate cause of Mr. Woo-lard’s injuries — is based on the testimony of Mr. Charles Smith, a superintendent for Young, who testified that he knew annual inspections were necessary. Mr. Smith explained that on the date Young took possession of the lift in 1993, he assumed all necessary annual inspections had been performed, although he did not request any documents supporting this. In light of this testimony, Primeco maintains that it is relieved from liability because the defect or hazard was already known.
See Pickens v. Tulsa Metro. Ministry,
Primeco’s argument is undermined by the principle that an injury may have more than one proximate cause.
See Kirkpat
*1173
rick,
Accordingly, the district court did not err in rejecting these proximate cause arguments in denying Primeco's motions for judgment as a matter of law and for a new trial. 2
4. Damages
Primeco maintains that the damage award of $1.5 million to Mr. Woo-lard is excessive and contrary to the evidence and that the district court abused its discretion in denying Primeco's motion for a new trial and its alternative motion for a remittitur. "Federal law governs the decision whether a remittitur should be granted in a diversity case. `Under federal law, whether the trial court properly refused to
*1174
grant remittitur or a new trial on the ground of an excessive damage award is tested by an abuse of discretion standard.’ ”
K-B Trucking Co. v. Riss Int’l Corp.,
Here, the record supports the jury’s verdict. Mr. Woolard presented evidence that his medical bills totaled nearly $100,000.00. His future estimated medical expenses would be in the range of about $35,000.00. The record indicates that his loss of past and future earnings totaled nearly $300,000.00. Mr. Woolard’s counsel sought an additional $410,000.00 for pain and suffering and another $410,000.00 for Mr. Woolard’s permanent physical impairment. Damages for pain and suffering are not susceptible to proof by a specific dollar amount, and accordingly, the jury has wide discretion in rendering a particular amount.
See Blanke,
5. Jury Instructions
Primeco also argues that the district court erroneously altered a jury instruction prior to the case’s submission to a jury. “When deciding whether a possible error in a jury instruction mandates reversal, ‘we review the record as a whole to determine whether the instructions state the law which governs and provided the jury with an ample understanding of the issues and the standards applicable.’ ”
Comcoa v. NEC Tels., Inc.,
After closing arguments and while the district court judge was instructing the jury, Mr. Woolard objected to instruction 17 and its corresponding verdict form B. 3 Mr. Woolard argued that the jury form *1175 was fundamentally incorrect because it instructed the jury that if it found one defendant liable, but not the other, the jury must find in favor of both defendants.
Young disagreed, arguing that the jury instruction was correct and that Mr. Woo-lard had waived any objection to the wording of the instruction. Further, Young argued that the proposed change would have removed the possibility of the jury finding that JLG or Young Electric was the cause of the accident. Primeco similarly objected. The district court overruled the objection and adopted Mr. Woo-lard's proposed changes. 4
Primeco, who joined Young in objecting before the district court, raises similar arguments on appeal: (1) that the amendment to the jury instruction was incorrect; and (2) that because the change to the instruction followed closing arguments, Primeco was deprived of an opportunity to adequately focus the jury on the liability of the nonparties.
When we view the instructions as a whole, particularly in conjunction with their relevant verdict forms and with the direct cause instructions, we note that Pri-meco could still argue, and in fact did argue, that the nonparties were the direct cause of the accident and injuries. See Aplts' App. vol. IX, at 652 (Primeco's closing argument) ("A broken bolt, JLG; failure to grease, Young Electric. . . . [I]f in fact, . . [Primeco~, were the two pieces of bread, then there is only one piece of meat between them, and that's JLG."); vol. I at 236 (Jury Instruction No. 13) ("Defendants Young Enterprises and Pri-meco claim that the negligence of JLG and Young Electric ... was the direct cause of plaintiff's damages, or at least had some causal connection with them."). Similarly, even though the verdict forms did not require specific findings as to the liability of nonparties, the instructions and verdict forms provided the jury with ample opportunity to conclude that the nonparties were the negligent parties. Our review of the jury instructions indicates that the instructions adequately reflect the law and do not provide grounds for reversal.
As to the timing of the changes to the instructions and the verdict form, we note that it would have been preferable for the district court to have made these changes before closing arguments. However, Primeco has failed to establish that it suffered any prejudice as a result of this eleventh-hour amendment. Because Pri-meco's attorneys adequately presented its defenses to the jury, the fact that the district court made the subject changes after closing argument does not entitle Primeco to a new trial.
B. Mr. Woolard's Cross-Appeal for Recalculation of Prejudgment Interest
Mr. Woolard's cross-appeal questions the district court's calculation of prejudgment interest. The district court granted Mr. Woolard's motion for prejudgment interest under Okia. Stat. tit. 12, § 727. The district court also granted motions by Pri-meco and Young to amend the judgment to reflect the offset of Mr. Woolard's pretrial *1176 settlement with JLG, pursuant to Okla. Stat. tit. 12, § 832. In its calculation of prejudgment interest, the district court determined that the calculation should be based on the reduced amount of $1.2 million. Mr. Woolard contends that the district court erred in failing to include the $300,000.00 in its calculation of prejudgement interest.
Generally, we will uphold a district court's award of prejudgment interest absent an abuse of discretion. See Driver Music Co. v. Commercial Union Ins. Cos.,
Section 727(E) of Title 12 provides that in personal injury actions, "the court in rendering judgment shall add interest on the verdict at a rate prescribed ... from the date the suit resulting in the judgment commenced. . . ." Okla. Stat. Ann. tit. 12, § 727(E) (emphasis supplied). We have previously considered setoffs in the context of an analogous Oklahoma statute, Section 3629(B) of Title 36. Section 3629(B) addresses the award of prejudgment interest in an insurance context: "[i]f the insured is the prevalhing party, the court in rendering judgment shall add interest on the verdict at the rate of fifteen percent (15%) per year from the date the loss was payable.. . ." Okla. Stat. Ann. tit. 36, § 3629(B) (emphasis supplied). In Driver; we recognized that an award of prejudgment interest based on the entire verdict comports with Section 3629(B)'s express command to add interest "on the verdict."
However, several Oklahoma decisions have indicated that the statutory provision that interest should be awarded on "the verdict" does not foreclose the deduction of amounts received in settlement before the interest calculation is made. For example, in Landrum v. National Union Ins. Co.,
Here, we may harmonize the statute's language with Oklahoma's authoritative application of the statute. In this case, Mr. Woolard received no pre-litigation benefit from the JLG settlement. See id. Mr. Woolard entered the settlement agreement approximately one month before the trial in this case, and subsequently received the settlement payment.
To deduct the $300,000.00 JLG settlement amount in full before calculating prejudgment interest appears to be prohibited from the plain language of Section 727(E), which requires calculation of prejudgment interest on the entire verdict. To award interest on the entire verdict, however, would do more than simply compensate Mr. Woolard for the loss of the use of funds between the filing of the suit and the entry of the judgment. See Landrum,
We agree with the Second Circuit's reasoning in In re Joint E. Dist. & S. Dist. Asbestos Litig. (Bauman v. Keene Corp.),
Accordingly, we reverse the district court’s calculation of prejudgment interest and remand to the district court for recalculation of the judgment by (1) adding prejudgment interest at the legal rate to the entire verdict pursuant to Section 727; (2) adding interest at the legal rate to the settlement sum from the date of the receipt of the settlement payment made until the date of judgment; and (3) subtracting the second calculation from the first to determine the amount owed to Mr. Woo-lard.
C. Young Enterprises’s Appeal of its Cross-Claims Against Primeco
Young argues that the district court erred in refusing to give its proposed instructions regarding its cross-claims against Primeco and seeks a directed verdict or a new trial. The district court’s decision whether to give a particular jury instruction is within its sound discretion, while we review its legal conclusions de novo.
See City of Wichita v. United States Gypsum Co.,
Young’s cross-claims against Primeco sought indemnification and/or contribution for any and all claims asserted by Mr. Woolard against Young. Young’s theories are threefold: (1) that it was entitled to an instruction regarding strict product liability indemnity; (2) that as a third-party beneficiary of the Distributor Agreement it was entitled to an instruction regarding Primeco’s breach of its duties to Young under the Distributor Agreement; and (3) that it was entitled to a supervening cause instruction stating that Primeco’s awareness of the need for an inspection of the lift within a month of the accident supervened any previous failure of Young to properly inspect the lift.
*1178 Primeco responds that Young's settlement agreement with Mr. Woolard precludes it from pursuing this appeal of its cross-claims. It also contends that Young asserts no recognized right to indemnity, that Young is not a third-party beneficiary of the Distributor Agreement, and that Young's requested supervening cause instruction is incongruent with the jury's comparative negligence finding.
Before addressing its specific theories, we note that we agree with Young that its settlement with Mr. Woolard does not bar Young's appeal. The order dismissing all claims between Mr. Woolard and Young explicitly states that "[a]ll claims ... as between Young and Primeco remain active on appeal." Dist. Ct. Order (filed July 29, 1998) at 4. Young is not attacking the jury verdict, as Primeco suggests. The cases on which Primeco relies do not estop Young from appealing the district court's refusal to instruct on Young's cross-claim. However, Young's settlement with Mr. Woolard does impact its ability to seek contribution, as discussed below.
1. Strict Product Liability
We begin with Young's argument that the district court erred in refusing to instruct the jury on its claim for indemnification or contribution against Primeco on a product liability theory. Young maintains that Primeco supplied it with a defective product because the lift's design was flawed and because it contained an improper sheave pin that caused the eyebolt to fail. According to Young, those deficiencies render Primeco strictly liable as the seller of the lift for damages incurred by Young. As damages, Young identifies the jury verdict obtained by Mr. Woolard (finding Young forty percent responsible for $1.5 million in damages) and the subsequent $400,000.00 settlement that Young made with him. We will first discuss Young's indemnification claim. Then, we will address its claim for contribution.
Under Oklahoma law, indemnity may arise out of an express contractual provision. Okla. Stat. Ann. tit. 15, § 421 (stating that "[i]ndemnity is a contract by which one engages to save another from a legal consequence of the conduct of one of the parties, or of some other person"). Alternatively, "`[n]oncontractual or equitable indemnity'" may arise from a legal relationship between the parties. National Union Fire Ins. Co. v. A.A.R. W. Skyways, Inc.,
Under a strict liability theory, a party who has a role in the distribution of a product may seek indemnity from the entity from which it purchased the product. See Booker v. Sears Roebuck & Co.,
Here, Young cannot be characterized as a party “in no manner responsible for the harm.”
Braden,
In its appellate brief, Young invokes decisions from other jurisdictions allowing a negligent party to recover indemnity on a products liability claim.
See
Young’s Br. for Cross-Appellant at 24-25 (noting that “[cjourts in other jurisdictions have allowed indemnification under circumstances where the downstream user fails to discover a defect in the product that they sold”). Young’s argument is supported not only by the decisions that it cites but by several other authorities.
See, e.g,
Restatement of Torts (Second) § 886B(d) (stating that an indemnitee is entitled to indemnity if “[t]he indemnitor supplied a defective chattel or performed defective work upon land or buildings as a result of which both were liable to the third person, and the indemnitee
innocently or negligently
failed to discover the defect”) (emphasis supplied);
Schneider Nat’l, Inc. v. Holland Hitch Co.,
However, other courts have disagreed, concluding (like the Oklahoma decisions set forth above) that a finding that a party has proximately caused the injuries in question precludes that party’s claim for indemnity.
See, e.g., Frazer v. A.F. Munsterman, Inc.
Although the issue is an important one, we need not here decide between these contrasting views. Under the Oklahoma law that we must apply, the jury’s finding that Young was the proximate cause of forty percent of Mr. Woolard’s injuries bars Young’s claim to equitable indemnity from Primeco on a products liability theory. 6
Young’s argument that it is entitled to recover under the related doctrine of contribution is also unpersuasive. Under Oklahoma law, a party who has been found jointly and severally liable in tort may be entitled to contribution.
See
Okla. Stat. Ann. tit. 12, § 832(A), (B) (“When two or more persons become jointly or severally liable in tort for the same injury to person ..., there is a right of contribution among them.... No tort-feasor is compelled to make contribution beyond their pro rata share of the entire liability.”). “The right of contribution exists only in favor of a tort-feasor who has paid more than their pro rata share of the common liability....”
Id.
§ 832(B). Contribution thus represents a sharing of joint and several liability by providing for proportional reimbursement from other parties who are liable to the plaintiff.
See National Union Fire Ins. Co.,
Although before the case went to the jury, Young may have been entitled to a contribution instruction, Oklahoma’s contribution statute allows only parties “who ha[ve] paid more than their pro rata share of the common liability” to seek contribution. Okla. Stat. Ann. tit. 12, § 832(B). Young’s cross-claim cannot survive, because Young’s settlement with Mr. Woo-lard was for an amount less than Young’s pro rata share. In addition, under the statute, “[a] tort-feasor who enters into a settlement with a claimant is not entitled to recover contribution from another tort-feasor whose liability for the injury ... is not extinguished by the settlement nor in respect to any amount paid in a settlement which is in excess of what was reasonable.” Id. § 832(D). As such, the district court’s failure to instruct on Young’s cross-claim for contribution under a strict liability theory does not require correction.
We therefore conclude that the district court properly denied Young’s motions for a new trial and for judgment as a matter of law on its claims for products liability indemnity and for contribution.
2. Cross-Claim for Breach of Contract
Young also argues that the district court erred in refusing to instruct the jury on its breach of contract claim against Primeco. For the same reasons we have set forth in discussing Young’s claim for indemnity on a strict products liability theory, Young’s argument is not supported by Oklahoma law. Although Young may avail itself of the Distributor Agreement’s benefits and pursue its claims for breach of
*1181
contract based on breach of warranty or other theories,
see Hesser,
3. Supervening Cause Instruction
Finally, Young contends that the trial court erred in refusing to instruct on supervening cause. In particular, Young maintains that, because the district court did not give such an instruction, Young was deprived of the opportunity to argue that Primeco’s conduct was a supervening cause of Mr. Woolard’s injuries and that, as a result, Young should not be held liable for them. We conclude that the district court did not abuse its discretion in declining to give Young’s requested instruction and in denying its motion for a directed verdict.
Under Oklahoma law, “[i]f an unforeseeable event intervenes between the breach of duty, and that event directly causes the injury completely independent of the original breach, then the intervening cause becomes the supervening cause and breaks the causal nexus between the initial breach and the subsequent injury.”
Tomlinson,
Upon review of the evidence presented at trial and the district court’s instructions to the jury, we conclude that Young was given an adequate opportunity to advance its argument that Primeco was a supervening cause of Mr. Woolard’s injuries. The jury was given instructions regarding direct cause, comparative negligence, concurrent tortfeasors, multiple defendants and the potential negligence of nonparties. The court’s direct cause instruction stated that “[f]or negligence to be a direct cause it is necessary that some injury to a person in plaintiffs situation must have been a reasonably foreseeable result of negligence.” Aplts’ App. vol. I, at 234. Young argued to the jury that JLG, Primeco, Mr. Woolard’s employer, and Mr. Woolard — -rather than Young itself — caused Mr. Woolard’s injuries. Although the jury found that Young’s independent act or acts of negligence, along with Primeco’s acts, were the proximate cause of Mr. Woolard’s injuries, the jury could have concluded — had it assessed the evidence differently — that Primeco’s acts “ ‘intervene^] so as to exclude the negligence of [Young] as one of the proximate causes of the injury.’ ”
Rawl v. United States,
Accordingly, we hold that the district court’s refusal to give the supervening cause instruction requested by Young was not reversible error.
Cf. In re Brooklyn Navy Yard Asbestos Litig.,
III. CONCLUSION
We AFFIRM the district court’s denial of Primeco’s motion for a judgment as a matter of law and its motion for a new trial. We REVERSE the district court’s calculation of prejudgment interest and we REMAND for recalculation. We AFFIRM the denial of Young’s motion for judgment as matter of law and its appeal of the district court’s refusal to grant instructions based on Young’s claims for indemnification or contribution stemming from Primeco’s product liability, breach of contract or supervening cause.
Notes
. The Restatement (Second) of Torts § 404 provides the identical language.
. Primeco also submits that application of Oklahoma's "accepted work doctrine" relieves Primeco of liability. The "accepted work doctrine," which emanated from the English case Winterbottom v. Wright, 10 M & W 109, 11 L.J. Ex. 415, 152 Eng. Rep. 402 (1842), requires privity of contract for a party to sue on a claim of breach of a duty arising out of the contract. See Pickens,
an independent contractor who has turned over his work and had it accepted by the owner is not subject to liability to third parties injured by the defective condition of the work. Liability if any, is placed on the owner who has maintained or used the property in its defective condition....
Id. at 1088.
Primeco should know that this doctrine has largely been abandoned by Oklahoma courts in contractor liability cases in favor of Justice Cardozo's opinion in MacPherson v. Buick Motor Co.,
Moreover, even if the accepted work doctrine's demise has been exaggerated, a well-established exception is applicable here.
"[W]here the contractor has wilfully created a condition which he knows, or by the exercise of ordinary diligence should have known, to be immediately and certainly dangerous to persons other than the con-tractee, who will be necessarily exposed to such danger, considerations of public policy do not require the application of the general [accepted work doctrine] rule."
Creamer v. Bucy,
. As amended, Instruction 17 stated:
If you find that plaintiff's injuries were directly caused by the contributory negligence of plaintiff, and not by any negligence on the part of the defendants, or, if you find that plaintiff has failed to prove that both defendants were negligent, then you shall use Section "B" of the verdict form and find in favor of both defendants.
In this connection you are advised that no specific finding need be made by you as to JLG and/or Young Electric, since they are not parties to this lawsuit.
Id. vol. I at 241 (emphasis supplied). The revised verdict form provided:
USE THIS SECTION `B" ONLY IF you find that the plaintiff's injuries were directly caused by the contributory negligence of plaintiff, and not by any negligence on the part of the defendants Young Enterprises and Primeco, or, if you find that plaintiff has failed to prove that both defendants were negligent. In this connection you are advised that no specific finding need be made by you as to JLG and/or Young Electric, since they are not parties to this lawsuit.
Id. at 247 (emphasis supplied).
. There, the court’s formula was:
(1) Add to each settlement hypothetical interest at the prejudgment interest rate from the time of the settlement until the time of the judgment. This interest is hypothetical because it is added to the settlement for calculation purposes only. This step converts each settlement into judgment-time dollars.
(2) Aggregate the resulting amounts (settlements plus hypothetical interest).
(3) Add prejudgment interest to the verdict.
(4) From the total arrived at in step 3, subtract the greater of either (a) the aggregate of the settlements converted into judgment-time dollars (the result from step 2), or (b) the settling defendants' total equitable shares of liability including prejudgment interest (i.e., the percentage of liability attributed by the factfinder to all settling defendants, in the aggregate, multiplied by the result from step 3 (i.e., the verdict increased by prejudgment interest)).
(5)The amount arrived at in step 4 is the amount of the judgment against the nonset-tling defendant.
. We note that a different result might be warranted if Young's claim was based on a contractual provision.
See Wallace v. Sherwood Constr. Co.,
