Woodrock, Inc. and Bakken Aggregates, LLC, v. McKenzie County, North Dakota
No. 20200066
IN THE SUPREME COURT STATE OF NORTH DAKOTA
August 27, 2020
2020 ND 182
McEvers, Justice
Filed 8/27/20 by Clerk of Supreme Court
Woodrock, Inc. Plaintiff and Appellant
and
Bakken Aggregates, LLC, Plaintiff
v.
McKenzie County, North Dakota, Defendant and Appellee
Appeal from the District Court of McKenzie County, Northwest Judicial District, the Honorable Robin A. Schmidt, Judge.
AFFIRMED.
Opinion of the Court by McEvers, Justice.
Thomas R. Olson, West Saint Paul, MN, for plaintiff and appellant Woodrock, Inc.
Brian D. Schmidt (argued) and Scott K. Porsborg (on brief), Bismarck, ND, for defendant and appellee.
[¶1] Woodrock, Inc. appeals from a summary judgment dismissing its negligence and other claims against McKenzie County. Woodrock argues the district court erred in concluding a project to stockpile aggregate materials was not a public improvement and the bond requirement under
I
[¶2] In September 2018, Woodrock sued the County for violations of
[¶3] The County moved for summary judgment, arguing
[¶4] The district court granted the County‘s motion and entered summary judgment in its favor. The court concluded there were two issues: 1) whether the project was a public improvement project as defined in
II
[¶5] Woodrock contends the district court erred in granting summary judgment in favor of the County. Woodrock argues the aggregate stockpile project was a “public improvement project” as defined in
[¶6] Our standard for reviewing a district court‘s summary judgment is well established:
Summary judgment is a procedural device under
N.D.R.Civ.P. 56(c) for promptly resolving a controversy on the merits without a trial if there are no genuine issues of material fact or inferences that can reasonably be drawn from undisputed facts, or if the only issues to be resolved are questions of law. The party seeking summary judgment must demonstrate there are no genuine issues of material fact and the case is appropriate for judgment as a matter of law. In deciding whether the district court appropriately granted summary judgment, we view the evidence in the light most favorable to the opposing party, giving that party the benefit of all favorable inferences which can reasonably be drawn from the record. A party opposing a motion for summary judgment cannot simply rely on the pleadings or on unsupported conclusory allegations. . . . When reasonable persons can reach only one conclusion from the evidence, a question of fact may become a matter of law for the court to decide. A district court‘s decision on summary judgment is a question of law that we review de novo on the record.
Wachter Dev., Inc. v. Martin, 2019 ND 202, ¶ 8, 931 N.W.2d 698 (quoting Frontier Fiscal Servs., LLC v. Pinky‘s Aggregates, Inc., 2019 ND 147, ¶ 6, 928 N.W.2d 449). The interpretation of a statute is a question of law, which is fully reviewable on appeal. Hughes v. Olheiser Masonry, Inc., 2019 ND 273, ¶ 8, 935 N.W.2d 530.
[¶7] We seek to ascertain the legislature‘s intent when we interpret a statute. Rocky Mountain Steel Founds., Inc. v. Brockett Co., LLC, 2019 ND 252, ¶ 11, 934 N.W.2d 531. Words are given their plain, ordinary, and commonly understood meaning, unless they are specifically defined or contrary intention plainly appears.
[¶8] Section 48-01.2-10, N.D.C.C., governs bonds from contractors for public improvements. When this action commenced the statute provided:
Unless otherwise provided under this chapter, a governing body authorized to enter a contract for the construction of a public improvement in excess of one hundred fifty thousand dollars shall take from the contractor a bond before permitting any work to be done on the contract. The bond must be for an amount equal at least to the price stated in the contract. The bond must be conditioned to be void if the contractor and all subcontractors fully perform all terms, conditions, and provisions of the contract and pay all bills or claims on account of labor performed and any supplies, and materials furnished and used in the performance of the contract, including all demands of subcontractors. . . . The bond is security for all bills, claims, and demands until fully paid, with preference to labor and material supplies as to payment. The bond must run to the governing body, but any person having a lawful claim against the contractor or any subcontractor may sue on the bond.
[¶9] Undisputed evidence established that the County maintains stockpiles of aggregate material for the purpose of repairing and maintaining roads and that the County requested bids for 100,000 tons of Class 13 Modified aggregate material for the County Road Department for two aggregate stockpiles. The County prepared standard specifications to inform potential bidders of the requirements for the project. The stockpile specifications stated, “The Project consists of furnishing all labor, materials, and equipment to perform the hauling and stockpiling of 100,000 total tons of Class 13 Modified that will be divided between two (2) sites.” Edwards Gravel submitted a bid for the project for $1,435,750. The district court concluded it was undisputed the project was to supply aggregate for two aggregate material stockpiles to be used on county road maintenance and repairs.
[¶10] The plain language of
[A]ny improvement undertaken by a governing body for the good of the public and which is paid for with any public funds . . . and is constructed on public land or within an existing or new public building or any other public infrastructure or facility if the result of the improvement will be operated and maintained by the governing body. The term does not include a county road construction and maintenance, state highway, or public service commission project governed by title 11, 24, or 38.
[¶11] The word “improvement” is not specifically defined in
[¶12] We conclude supplying materials to a stockpile for use in future projects does not constitute “the construction of a public improvement” as defined in
[¶13] The South Dakota Supreme Court reached a similar result in Pete Lien & Sons, Inc. v. City of Pierre, 1998 S.D. 38, 577 N.W.2d 330 (per curiam). The City solicited bids for the supply of gravel to a city stockpile used for general road maintenance purposes, and a subcontractor sued the City after the contractor failed to pay for the gravel the subcontractor supplied. Id. at ¶¶ 2-3.
[¶14] Moreover, the definition of “public improvement” under
[¶15] The project was not for the construction of a public improvement as defined by
III
[¶16] We affirm the judgment.
[¶17]
Lisa Fair McEvers
Daniel J. Crothers
Jerod E. Tufte
Gerald W. VandeWalle
Jon J. Jensen, C.J.
