275 F. 660 | 3rd Cir. | 1921
This suit arose out of an alleged breach of a contract for 1,000 tons of pipe. On October 21, 1916, the W. E. Sexton Company, of Mineóla, N. Y., placed an “order for one thousand tons ‘class B’ pipe immediate and winter shipments, price twenty-nine dollars six-inch and larger; four-inch, thirty-two dollars”—-with Walter Wood, trading as R. D. Wood & Co., of Philadelphia. Two days later ibc defendant accepted the order. In January, 1917, the plaintiff ordered approximately 353 tons of the 1,000, which was eventually delivered ; but the rest had not been delivered on March 14, 1917, when a telephone conversation was held between the parties, and Wood asked the Sexton Company to send the specifications for the remaining tonnage. They were sent on that day, but at this time the market price had risen to about £20 a ton above the contract price. Then passed between them a number of letters. In these the plaintiff sought to enforce, and the defendant to avoid, the contract. They were diplomatically maneuvering for the be.st terms of adjustment, and, if that failed, then for an advantageous position for the coming litigation. Finally, on May 30, 1917, the defendant definitely refused to fill the balance of the contract. Thereupon the plaintiff went into the open market and purchased the pipe, and brought suit for $15,527.38, with interest, which was the difference of $24 per ton between the market price at that time and the contract price, on the 646.97 tons still undelivered.
The jury rendered a verdict for the full amount of the demand, and the defendant sued out a writ of error to this court, based upon 12 assignments. The first, second, and twelfth assignments are general and formal, and do not require consideration. The other nine may be reduced to the following propositions:
í. The court erred in sustaining objections to questions designed to establish the market price of pipe in October, 1916, when the contract was made.
II. The court erred in refusing to affirm the defendant’s “points” for charge, which were in substance as follows:
2. -The measure of damages adopted was illegal, because the plaintiff did not avail itself of the lowest price offered, but instead bought in the open market at a higher price.
3. The contract was-breached, if at all, on March 16, 1917, and the market price of pipe must be fixed as of that date, and not at the higher price on May 30,1917.
[ 1 ] These propositions, with the exception of the first, might be disposed of upon technical grounds. At the conclusion of the charge the trial judge said:
“There have been a number of points submitted to me. So far as affirmed in the general charge, they are affirmed; so far as not affirmed in the general charge, they are denied.”
The defendant did not take an exception to the refusal to take up his points seriatim and affirm them, but left the trial judge under the impression that he had satisfactorily covered the points. Where it is obvious from the remarks of the trial judge at the close of his charge that he believes he has substantially covered the requests or “points” to the satisfaction of the litigants, though as a matter of fact he has inadvertently overlooked some of them, and an opportunity is given to bring to his attention the omissions or dissatisfaction, failure to take advantage of this opportunity waives the error. Pennsylvania Railroad Co. v. Minds et al., trading as Bulsh Coal Co., 250 U. S. 368, 373, 39 Sup. Ct. 531, 63 L. Ed. 1039.
The plaintiff, however, bad been dealing with the defendant for several years, and the account between them had never been definitely stated and a balance struck. Defendant made shipments to the plaintiff, on which payments had been made from time to time, which defendant credited to the general account of the plaintiff. Over some of these shipments, however, there were controversies as to the exact amount due. Deductions were demanded by the plaintiff. This was the case on March 14, 1916. The plaintiff had asked a number of times that there disputes be adjusted, and adjustment was finally made on April 17, 1916, and the account was paid in full. The evidence cannot he read without reaching the conclusion that the failure of the defendant to ship the balance of the pipe upon receiving the specifications on or about March 14, 1917, was due to the increase in the price of pipe of about $20 per ton at that time, and that the refusal to ship pipe because payments then due had not been made was an afterthought.
The main defense upon which defendant principally relied is the meaning to be given to the words “winter shipments” in the trade. The defendant contended in his affidavit of defense that “winter shipments” in the trade meant while the ground was 'frozen too deep for digging, and not the calendar ending of winter oh March 21st. He sought to show at the trial, however, that specifications on orders must be given in time for the seller to manufacture and ship the pipe while the ground was frozen; that it would require some four or five weeks to manufacture the balance of this pipe, and, as the specifications were not sent in
The facts of the instant case, however, do not bring it within this rule. If the offer had been made unconditionally, and did not. require, expressly or impliedly, that plaintiff relinquish its rights to damages under the contract in accepting the offer, it would be limited to the difference of $10 per ton between the contract price and the price offered. But the very ground on which this reduction in price was offered involved the surrender by the plaintiff of its rights under the contract. It was not compelled to give up anything it Fad under the contract, and the measure of damages is therefore not limited to the difference between the contract price and the price offered .on March 16. There is no evidence that the price paid by the plaintiff was not then the market price. Therefore, as charged by the court, the measure of damages for which the defendant is liable, if liable for any, was the difference between the market price at the time of the breach and the contract price.
Defendant claims that the contract was breached by him, if at all, on March 16, 1917, when he definitely refused to deliver the balance of the pipe under the contract, and that under any view of the case the measure of damages is the difference between the contract price and the market price of that date, and not the higher market price of May 30, 1917. There was, however, not a definite refusal, as above noted, of the defendant to ship the iron covered by the contract until May
The judgment of the District Court will therefore be affirmed.