The plaintiffs, Stephen and Nancy Wood, appeal an order of the Superior Court {Fauver, J.) granting summary judgment to the defendant, William Greaves d/b/a Agricultural Land Management. The court ruled that the plaintiffs’ claims were barred by the statute of limitations. We affirm.
The trial court found the following facts to be undisputed. The plaintiffs hired the defendant to build a horse facility on land they own in North Hampton. As a result of the defendant’s work, the plaintiffs were notified by the New Hampshire Department of Environmental Services (DES) of a potential wetlands violation on their property. The notification, dated July 30, 1999, informed the plaintiffs that DES could institute enforcement action against them, and stated that the plaintiffs could either submit an application “after the fact” for the work already done, or provide a restoration plan.
The plaintiffs submitted an application after the fact in November 1999, which DES denied by letter dated November 14, 2001. The plaintiffs then submitted a restoration plan, which DES approved by letter dated April 16,2003.
The plaintiffs commenced this action on July 7, 2003, alleging that the defendant committed a wetlands violation, without their authorization or consent, on their property, causing damages including the incurring of engineering and legal fees and remediation costs. The plaintiffs’ writ alleged causes of action in implied indemnification and imputed indemnification.
Our standard of review is well established:
We will affirm a trial court’s grant of summary judgment if, considering the evidence and all inferences properly drawn therefrom in the light most favorable to the non-movant, our review of that evidence discloses no genuine issue of material fact, and the moving party is entitled to judgment as a matter of law. We review the trial court’s application of the law to the facts de novo.
Coyle v. Battles,
The plaintiffs do not dispute that the applicable statute of limitations is set forth in RSA 508:4,1 (1997):
Except as otherwise provided by law, all personal actions, except actions for slander or libel, may be brought only within 3 years of the act or omission complained of, except that when the injury and its causal relationship to the act or omission were not discovered and could not reasonably have been discovered at the time of the act or omission, the action shall be commenced within 3 years of the time the plaintiff discovers, or in the exercise of reasonable diligence should have discovered, the injury and its causal relationship to the act or omission complained of.
Rather, the plaintiffs contend that “[t]he sole issue here is whether the superior court erred in deciding when the statute of limitations began to run.”
The plaintiffs argue that the statute of limitations on a claim for indemnification does not begin to run “until the party seeking indemnification suffers a loss.” Jaswell Drill Corp. v. General Motors Corp.,
In a situation where the indemnitee becomes liable to a third party, no “loss” is suffered until the indemnitee pays a judgment entered against it in favor of the third party, or until the indemnitee satisfies the third party’s claim by a settlement payment. The reason for this rule is rooted in common sense: until the indemnitee has satisfied his liability, no loss has been suffered, and no wrong has been done to the indemnitee.
Ameron, Inc.,
We agree with the defendant that the cases upon which the plaintiffs rely are factually distinguishable. In the instant case, there is no underlying action brought by an injured third party. The indemnitee and the party initially injured by the defendant’s conduct are the same: the plaintiffs. Thus, the rationale behind the rule the plaintiffs seek to apply is inapposite.
To determine the nature of a cause of action for statute of limitations purposes, we look not to “the form of the action but .. .[rather] its substance.” Gould v. Concord Hospital,
We consider this case to be functionally equivalent to one in which a builder hired under contract to build a house constructs it negligently and in violation of local building or zoning ordinances. There, the plaintiff’s action would be one for breach of contract. Cf. Roberts v. Richard & Sons, Inc.,
We held in Black Bear Lodge v. Trillium Corporation,
The plaintiffs nevertheless argue that until they “knew whether their Restoration Plan was accepted as proposed, or accepted with additional conditions, they had no way of knowing the extent of their damages.” We acknowledge that a similar argument has been used to support the rule that the statute of limitations on indemnification claims for liability to a third party does not begin to run until a judgment or settlement is paid to the third party. See Ameron,
Affirmed.
