MEMORANDUM OPINION AND ORDER
Pеnding is Defendants’ Motion for Summary Judgment. The parties have submitted memoranda in support of their respective positions and the matter is mature for the Court’s consideration. Based on the absence of a genuine issue of material fact and the law, the Court GRANTS the motion.
I.
THE STANDARD
Under Rule 56(c) of the Federal Rules of Civil Procedure, summary judgment is proper only:
“If the pleadings, depositions, answers to interrogatories and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to summary judgment as a matter of law.”
Fed.R.Civ.P. 56(c). A principal purpose of summary judgment is to isolate and dispose of meritless litigation.
Celotex Corp. v. Catrett,
“Unsupported speculation is not sufficient to defeat a summary judgment motion.”
Felty v. Graves-Humphreys Co.,
II.
THE UNDISPUTED FACTS
Wood County Airport Authority (“the Airport Authority”) operates the Wood County Airport (“the airport”) near Williamstown, West Virginia. From the early 1980’s to the early 1990’s, Crown Airways, Incorporated (“Crown”) was a commercial air carrier providing commercial air service to and from the airport. For over a decade, Crown lеased and occupied Hangar 5 at the airport. During that period, the Airport Authority and Crown enjoyed a productive working relationship.
In the late 1980’s, around the time Crown and the Airport Authority were negotiating the renewal of Crown’s existing lease, Crown sought expansion of its operations. Crown informed the Airport Authority it would be acquiring two new 360 Shorts aircraft. These larger airplanes required more space than was available in the existing hangars at the airport. In 1989 and 1990, the parties began discussing the possibilities of either enlarging Hangar 5 or constructing a larger hangar to be known as Hangar 6.
In the spring of 1990, a local engineering firm advised the parties modifying Hangar 5 was not feasible. The parties elected to proceed with the construction of a new hangar. The Airport Authority began pursuing funding for the project and, by the summer of 1991, obtained commitments for much of the financial resources necessary for construction. 2
The parties executed a Lease Agreement (“Lease”) for Hangar 6 on December 14, 1992. The term of the Lease commences on the date of occupancy and extends for a period of fifteen (15) years thereafter. The Lease was drafted by Robert Tebay, house counsel to the Airport Authority and ex offi-cio member of its board. This document is the primary focus of the controversy.
Carolyn Strock, Manager of the Airport Authority, and Mr. Tebay testified Crown’s obligations under the Lease were limited to the payment of rent and utilities and other incidental obligations. Ms. Strock and Mr. Tebay further admitted the Lease does not obligate Crown to retain a maintenance facility at the airport or to retain any particular number of maintenance employees in connection with Hangar 6. The Airport Authority also admitted “[tjhere is no written contract between [the Airport Authority] and either of the defendants relative to a maintenance facility.” (Pl.’s Ans. tо Defs. First Set of Requests for Admissions (“Pl.’s Admissions”), No. 1). Mr. Tebay testified “in hindsight” he should have included a provision in the Lease obligating Crown to retain the maintenance facility.
*964 The following spring, the Airport Authority retained local engineering firms to design Hangar 6. In July 1993, difficulties were encountered when the West Virginia Fire Marshal would not approve a proposed fire suppression system for the hangar. The increased cost of a more elaborate fire suppression system prompted the Airport Authority to request the Economic Development Administration (“EDA”) to allocate funds to assist in the construction. 3
On December 15, 1993, Crown and Mesa Airlines, Incorporated (“Mesa”) executed an Agreement of Purchase and Sale of Assets wherein Mesa agreed to purchase certain assets and to assume certain liabilities of Crown. Prior to this agreement, but subsequent to the execution of the Lease, Mesa conducted a due diligence investigation of thе assets and liabilities of Crown in conjunction with its possible purchase of Crown. During that time, Mesa also examined the Lease.
At least as early as January 11, 1994, 4 the Airport Authority was aware Mesa soon might be acquiring certain assets of Crown. By letter dated February 2, 1994, Mesa informed the Airport Authority that Mesa did “not wish [the Airport Authority] to proceed with the construction of a hangar facility for maintenance purposes.” 5 After receiving this letter, the Airport Authority continued to seek Mesa’s performancе.
On February 11,1994, Crown assigned the Lease to Mesa. 6
Over one year later, on June 14, 1995, the Airport Authority cancelled the Hangar 6 project 7 and initiated this action in the Circuit Court of Wood County. Defendants timely removed the action to this Court. Plaintiff amended its Complaint on August 28,1995.
The Amended Complaint asserts claims of intentional interference with contractual relations by Mesa, breach of contract by Crown and Mesa 8 , breach of the duty of good faith and fair dealing by Crown and Mesa 9 , and promissory estoppel.
*965 III.
THE LAW
A. PAROL EVIDENCE 10
It is well-settled parol evidence of prior or contemporaneous oral negotiations or stipulations is inadmissible to vary, contradict, add to, or explain the terms of a complete, unambiguous, written instrument in the absence of fraud, accident or mistake
11
in its procurement.
Haymaker v. General Tire, Inc.,
“The parol evidence rule, designed to promote the certainty and stability of contractual obligations, ‘is founded upon the principle that when parties have discussed and agreed upon their obligations to each other and reduced those terms to writing, the writing, if clear and unambiguous, furnishes better and more definite evidence of what was undertaken by each party than the memory of man.’ ”
Doganieri v. United States,
“Contract language usually is considered ambiguous where an agreement’s terms are inconsistent on their face or where the phraseology can support reasonable differences of opinion as to the meaning of words employed and obligations undertaken.”
Fraternal Order of Police Lоdge Number 69 v. City of Fairmont,
— W.Va. -, - -,
Where a writing appears to be a complete contract, embracing all the particulars necеssary to make a perfect agreement and designed to express the whole arrangement between the parties, it is conclusively presumed to embrace the entire contract and all the terms and provisions of the agreement.
Kelley, Gidley, Blair & Wolfe, Inc. v. City of Parkersburg,
“A written contract merges all negotiations and representations which occurred before its execution, and in the absence of fraud, mistake, or material misrepresentations extrinsic evidence cannot be used to alter or interpret language in a written contract which is otherwise plain and unambiguous on its face.”
Iafolla v. Douglas Pocahontas Coal Corp.,
“In order to exclude evidence of oral agreement on the ground the parties later entered into a written contract, the oral agreement must relate to the same agreement embodied in the written contract.”
Clator v. Otto,
Furthermore, application of the par-ol evidence rule may not be circumvented by asserting promissory estoppel.
See Wojciechowski v. Amoco Oil Co.,
Here, the Airport Authority admitted the alleged “oral maintenance retention agreement ... invaluably led to the execution of the lease.” (PL’s Supp. Opp. to Mot. to Dis. at 8). The Airport Authority also admitted “[t]hese [oral] representations merely reinforce the purpose of entering into the lease agreement in the first place.” (Pl.’s Response to Mot. for S.J. at 17). In addition, Ms. Strock and Mr. Tebay testified the alleged oral promisеs regarding a maintenance facility were made in conjunction with the written Lease. See Strock Dep. at 49; Te-bay Dep. at 52. Thus, the alleged oral promises relate to the same agreement embodied in the Lease and were made contemporaneously with or prior to the execution of the Lease.
The Lease explicitly and unambiguously sets forth the obligations of the parties with respect to Hangar 6. The Lease’s terms are consistent on their fаce and support only one meaning of the words and obligations undertaken therein. No mention is made in the Lease of any obligation on the part of Crown or its assignee to retain a maintenance facility at Hangar 6. In fact, Ms. Strock and Mr. Tebay admitted the Lease does not obligate Crown or Mesa either to retain a maintenance facility at the airport or to retain a certain number of maintenance employees. See Strock Dep. at 46-47; Tebay Dep. at 25-26. Ms. Strock and Mr. Tebay further testified Crown’s obligations under the Lease were limited to the payment of rent, utilities, and incidental obligations.
The testimony of Ms. Strock and Mr. Te-bay similarly bolsters the conclusion the Lease is a fully integrated declaration of the agreement between the parties. Ms. Strock 12 and Mr. Tebay 13 testified the Lease *967 was intended to set forth all of the parties’ respective contractual obligations in connection with Hangar 6. The Airport Authority also admitted “there is no writtеn contract between [the Airport Authority] and either of the Defendants relative to a maintenance facility.” (Pl.’s Admissions, No. 1).
In opposing Defendants’ motion, Plaintiff contends the alleged oral representations “do not vary or contradict the terms of the lease; therefore, the parol evidence rule is not at issue.” (PL’s Response to Mot. for S.J. at 17-18). Plaintiffs argument is without merit. Plaintiffs assertion that Crown committed itself to retain Hangar 6 as a maintenance facility clеarly varies, contradicts, and adds significant and substantial obligation to the Lease agreement. As noted, Mr. Tebay conceded “in hindsight” the Lease should have included this obligation.
The Court concludes the Lease is a fully integrated document that unambiguously and explicitly sets forth all of the parties’ respective obligations regarding Hangar 6. As a matter of law, the Airport Authority is precluded from relying upon alleged prior or contemporaneous oral negotiatiоns or statements to alter or add to the terms of the Lease. Construing the unambiguous language of the Lease according to its plain and natural meaning, the Court finds and concludes neither Crown nor Mesa had any obligation under the Lease to retain a maintenance facility at Hangar 6.
B. CONTRACT MODIFICATION
The Airport Authority further alleges Crown made representations regarding a maintenance facility
after
the Lease was executed. To demonstrate the parties committed themsеlves to a separate oral agreement, entered subsequent to the Lease, which would modify the terms of the Lease, Plaintiff must show the parties expressly agreed to any such modification, and any such modification had all of the requisites of a valid and enforceable contract, including mutual assent and separate identifiable consideration.
See Wheeling Downs Racing Ass’n v. West Virginia Sportservice, Inc.,
C. BREACH OF CONTRACT
Fundamentally, for an action on the contract to succeed, the party accused of repudiation must have been a party to thе contract at the time of the alleged breach.
See Microsoft Corp. v. BEC Computer Co.,
An anticipatory breach occurs when a party to a contract asserts he will not perform a future obligation required by the contract. Anticipatory breach requires an unequivocal renunciation of the contract by an obligee.
Mollohan v. Black Rock Contracting, Inc.,
A party’s failure to perform its own obligations precludes recovery against another party for breаch of contract. Where one has “failed to perform an act which is a condition precedent to the assertion of a right to which he may have been entitled had he performed such act, he is not entitled to the benefit of the promise for which the omitted act was of the essence of the consideration for such promise.”
Shank v. Jefferson Standard Life Ins. Co.,
Plaintiff admitted it is relying solely upon the February 2,1994 letter as the basis for its breach of contract claim. Mesa was not a рarty to the contract until February 11, 1994 when it accepted assignment of the Lease. Mesa did not breach the contract as a matter of fact and law.
Furthermore, the February 2, 1994 letter does not constitute an anticipatory breach. The statements in the letter do not conflict with any obligation set forth in the Lease. 14 Nor can the language in the letter be construed as “definite and unequivocal.” Mesa never stated it would not perform under the Lease. In faсt, nine days after sending the February 2,1994 letter, Mesa accepted assignment of the Lease, and to date, stands ready and willing to perform its obligations under the Lease once Hangar 6 is constructed. See Defs. Mem. S.J. at 17 & 19; Pretrial Order at 8-9.
Construction of Hangar 6, however, has not commenced. When the Airport Authority cancelled the Hangar 6 project, it was not in a position to complete the project because it had not received the necessary funding nor the Fire Marshal’s approval of the hangar’s fire suppression system. The Airport Authority thus has not performed its own eon-traetual obligations to lease a completed Hangar 6 to Mesa. The Court finds and concludes neither Crown nor Mesa breached the Lease.
D. INTENTIONAL INTERFERENCE WITH CONTRACTUAL RELATIONS
West Virginia recognizes a cause of action based on tortious interference with contractual relations.
Torbett v. Wheeling Dollar Sav.
&
Trust Co.,
In order to succeed with this claim, Plaintiff must prove:
“(1) existence of a contractual or business relationship or expectancy; (2) an intentional act of interference by a party outside that relationship or expectancy; (3) prоof that the interference caused the harm sustained; and (4) damages.”
Id.
at 167, Syl. Pt. 2;
accord C.W. Development, Inc. v. Structures, Inc. of West Virginia,
A party cannot be liable for interference with a contract if that party has a financial interest in the contract.
Torbett,
*969 Here, a contract existed between the Airport Authority and Crown in the form of the Lease. Contrary to Plaintiff’s assertions, 15 however, the Lease does not obligate Crown to retain its maintenance operatiоns at the airport in exchange for the Airport Authority constructing a maintenance hangar. Plaintiff does not dispute Crown had a contractual right to assign the Lease to Mesa. At the time Plaintiff alleges the tor-tious interference occurred, Mesa, as the as-signee of Crown’s interests under the Lease, had a financial interest in the business of Crown. Indeed, nine days after sending the February 2, 1994 letter, Mesa assumed the same contract with which it was alleged to have interfered. Undеr these circumstances, Mesa cannot be said to have interfered with Plaintiff’s contractual relations with Crown.
Accordingly, the Court GRANTS summary judgment in favor of the Defendants. The Court ORDERS this ease dismissed and stricken from the docket of the Court.
Notes
. In opposing summary judgment, Plaintiff makes several unsupported assertions that would be inadmissible at trial. These statements have not been considered by the Court in ruling upon Defendants’ motion.
. The Airport Authority submitted grant applications to the Appalаchian Regional Commission (ARC) and the Farmers Home Administration (FmHA). The Airport Authority also committed itself to invest up to one hundred twenty-five thousand dollars ($125,000.00) in the project. In addition, the Airport Authority obtained a loan from United National Bank to finance the remainder of the project. The loan closed in February 1993.
. The Airport Authority never received final approval from the EDA for the requested funding.
. The Minutes of the January 11, 1994 Special Meeting of the Airport Authority state, "Mr. Shaver [Vice President of the Airport Authority] asked about Mesa Airlines. Mesa Airlines is buying Crown Airways.” The Airport Authority then had internal discussions regarding the possible effect an assignment would have on the parties’ respective obligations under the Lease.
. The Airport Authority relies on this letter as the sole basis for its breach of contract claim. (Pl.'s Admissions, No. 6).
. The Airport Authority does not dispute Crown’s right to assign the Lease to Mesa under the terms of the Lease. Further, at no time did the Airport Authority communiсate to either Defendant an objection to the assignment of the Lease.
. At the time of cancellation, the Airport Authority had not received the Fire Marshal’s approval of the fire suppression system nor the funding necessary to complete the project. Consequently, actual construction had not begun.
. Plaintiff argues it "is not claiming that Crown promised to retain a maintenance facility for fifteen years ... or that Crown promised to employ a certаin number of employees at Wood County.... Crown needed to only commit itself to the retention and operation of a maintenance facility — nothing more.” (Pl.’s Response to Mot. for S.J. at 7-8).
.Plaintiff did not respond to Defendants’ argument for summary judgment regarding this issue. Most importantly, Plaintiff
did
not reference this claim in its portion of the Pretrial Order. Accordingly, Plaintiff has abandoned this claim.
Turley v. Union Carbide Corp.,
. Defendants argue аny claims of alleged oral agreements are barred by the parol evidence rule and by the Statute of Frauds, West Virginia Code § 55-1-1 (1990). Because the Court concludes the aEeged prior oral negotiations or statements effectively merge into the final contract and because Plaintiff is precluded from relying upon alleged prior or contemporaneous oral negotiations or statements to alter, contradict, or add to the Lease, it is unnecessary to address the applicability of the Statute of Frauds.
. Plaintiff makes no allegation of fraud, mistake, or accident.
. Ms. Strock testified a new contract between Crown and the Airport Authority was needed before proceeding with the construction of the new hangar. In response to the questions, Ms. Strock further admitted the following:
"Q: Were there any other contracts that you [the Airport Authority] had to get?
A: No.
Q: So the Lease agreement is the one that contains аll the terms?
A: Contains all the terms?
Q: The Lease agreement is the only contract you had to obtain?
A: The Lease agreement for the use of Hangar 6, right."
Strock Dep. at 42.
. Likewise, Mr. Tebay testified:
"Q: Did you intend for the lease to set forth all the parties' obligations?
A: In hindsight? I intended the lease to reflect a fair rental agreement for hangar six once it was built and completed.
Q: But is that intended to include all of the parties’ obligations.
A: Once the hangar was completed, yes.
Q: Does it include all the parties' obligations?
A: In retrospect, no. There should have been a statement that it was for a maintenance facility.
Q: So you think you left something out?
*967 A: In hindsight. But once again that lease was intended to reflеct the rental of that building once the building was constructed and occupied."
Tebay Dep. at 22-23.
. The February 2, 1994 letter states Mesa "does not wish [the Airport Authority] to proceed with the construction of a hangar facility for maintenance purposes of [Mesa’s] aircraft.”
. Plaintiff asserts “a contract existed between Wood Co. and Crown, in which Wood Co. agreed to build a maintenance hangar if Crown would retain its maintenance operations at the Wood Co. Airport.” (Pl.’s Response to Mot. for S.J. at 19).
