73 So. 394 | Ala. | 1916
(1) Whether or not defendants’ covenant to pay rent was dependent upon plaintiff’s covenant to make improvements and have the premises ready by October 1st was, under the evidence, a question of fact for the jury.—Drake v. Goree, 22 Ala. 409, 414.
(2) If the jury found that these covenants were dependent, then plaintiff’s breach of the covenant to repair fully justified defendants in declining to occupy the premises at the time stipulated, and released them from the obligation to pay rent.—Lunn. v. Gage, 37 Ill. 19, 87 Am. Dec. 233, and note, 237; 9 Cyc. 643, and cases cited.
(4) But plaintiff insists that, inasmuch as defendants themselves first breached the rental contract by their notice to her that they would not take the premises or be bound by their obligation, they cannot now complain of her subsequent failure to make the improvements, nor avail themselves of her default therein. If, when defendants notified plaintiff of their abandonment of the contract, she had elected, as she clearly could have done, to submit to a rescission, and rely upon her action for the breach, she would certainly not have been bound to go on and make the improvements, though relief from that burden would naturally have reduced to that extent the amount of her recovery. But, when she elected, as she rightfully could, to keep the rental contract alive, and held defendants to their obligations thereunder, she necessarily kept the contract alive for all purposes, and her own obligations remained in full force and effect. The law on the subject was clearly and accurately stated by Lord Cockburn, C. J., in Frost v. Knight, L. R. 7 Ex. 111, as follows:
“The promisee, if he pleases, may treat the notice of intention tto abandon the contract] as inoperative, and await the time when the contract is to be executed, and then hold the other party responsible for all the consequences of non-performance; but in that case he keeps the contract alive for the benefit of the -other party as well as his own; he remains subject to all his own obligations and liabilities under it, and enables the other party, not only to complete the contract, if so advised, notwithstanding his previous repudiation of it, but also to take advantage of any supervening circumstance which would justify him in declining to complete it. On the other hand, the promisee may, if he thinks proper, treat the repudiation of the other party as a wrongful putting an end to the contract, and may at once bring his action -as on a breach of it; and in such action he will be entitled to ■such damages as would have arisen, from the nonperformance tof the contract at the appointed time, subject,, however, to abate
This statement is quoted with approval in Roehm v. Horst, 178 U. S. 1, 11, 20 Sup. Ct. 780, 44 L. Ed. 953, where many other authorities are cited and discussed. See, also, O’Neill v. Supreme Council, 70 N. J. Law, 410, 57 Atl. 463, 1 Ann. Cas. 422, and note, 427.
If, therefore, the jury should find that plaintiff covenanted to make the improvements described, and that defendant’s covenant to pay rent was dependent thereon, then plaintiff’s failure to make the improvements in season would discharge defendants” obligation to occupy the premises and pay the rent.
It follows from the foregoing principles that the trial judge erred in giving the general affirmative charge for the plaintiff, and the judgment must be reversed, and the cause remanded for another trial.
Reversed and remanded.