In this case, we are presented with the question of whether the Contract Disputes Act of 1978 (“CDA”) gives the Armed Services Board of Contract Appeals (“Board”) jurisdiction over a claim against the government brought by a subcontractor that is a third-party beneficiary of a contract between the government and the prime contractor. For the reasons stated below, we hold that it does not.
I. BACKGROUND
On February 6, 2002, the Navy awarded a contract for the installation of floor coating at warehouse bays on a military base to G.M. & W. Construction Corp. (“GM & W”), a minority-owned business qualifying under section 8(a) of the Small Business Act. The Navy agreed to pay GM & W $42,000 for the completion of the work. FloorPro, Inc., which is not a section 8(a) contractor, entered into a subcontract agreement with GM & W on February 11, 2002. Under the terms of the subcontract, FloorPro agreed to perform the work specified by the Navy’s contract with GM & W for $37,500.
FloorPro completed all of the work under the contract by February 27, 2002, and submitted its invoice to GM & W on March 6, 2002. On March 8, 2002, the government’s contracting officer notified GM & W that the work had been completed satisfactorily. The government received GM & W’s request for payment on April 16, 2002. The next day, FloorPro informed the government that GM & W had not paid its invoice on the subcontract. On April 22, 2002, the government’s contracting officer called GM & W to inquire about GM & W’s failure to pay FloorPro. GM & W informed the contracting officer that there were various pending claims against it and that it did not know whether it would be able to use funds deposited into its account to pay FloorPro. Accordingly, the government and GM & W agreed to modify the original contract, which provided for payment to be made directly to GM & W, to specify that the government would issue a two-party check made payable to both FloorPro and GM & W. This agreement was executed by GM & W and the government as Modification No. P00001 on April 22, 2002.
Notwithstanding the modification, the government paid GM & W directly. On July 18, 2002, the contracting officer notified FloorPro that the payment had not been made by two-party check. Several weeks later, the contracting officer confirmed to FloorPro that GM
&
W had been
On March 27, 2003, FloorPro filed an appeal against the government with the Board. . The underlying claim was hot sponsored by GM & W.
1
The government filed a motion to dismiss in which it alleged that the Board lacked jurisdiction over FloorPro’s appeal. Specifically, the government argued that the CDA only authorizes appeals to the Board taken by “contractors,” and thus claims brought by FloorPro, a subcontractor, are outside the Board’s jurisdiction. The Board denied the government’s motion, concluding that FloorPro was an intended third-party beneficiary of the contract modification and, therefore, could file a claim even in the absence of contractual privity.
In re FloorPro, Inc.,
ASBCA No. 54143,
The government timely appealed. We have jurisdiction' under 28 U.S.C. § 1295(a)(10).
II. DISCUSSION
“The determination of jurisdiction under the CDA is a question of law. It is therefore subject to
de novo
review.”
England v. Swanson Group, Inc.,
The CDA was enacted to “provide! ] a fair, balanced, and comprehensive statutory system of legal and administrative remedies in resolving government contract claims.”
Contract Disputes Act of 1978,
S.Rep. No. 95-1118, at 1 (1978), as
reprinted in
1978 U.S.C.C.A.N 5235, 5235. Under the CDA, a contractor has two possible avenues of appeal after an adverse decision from a contracting officer.
Id.
at 2. First, the contractor may file an appeal with an agency board of contract appeals. 41 U.S.C. § 606. In the alternative, the contractor may file a claim against the government in the United States Court of Federal Claims.
Id.
§ 609(a). Importantly, these provisions apply only to those who are “contractors” within the meaning of the CDA, which defines the term to mean “a party to a Government contract other than the Government.”
Id.
§ 601(4);
see also Admiralty Constr., Inc. v. Dalton,
In this case, the Board determined that FloorPro was not in contractual privity with the government.
FloorPro III,
We begin with the established principle that a “waiver of sovereign immunity must be strictly construed in favor of the sovereign.”
Orff v. United States,
As mentioned above, the provisions of the CDA apply only to “contractors,” i.e., “part[ies] to a Government contract other than the Government,” 41 U.S.C. § 601(4);
see also, e.g., id.
§ 604 (creating liability for “contractors” who bring fraudulent claims against the government);
id.
The recommendations of the procurement commission specifically exclude bringing subcontractors under the provisions of S. 3178.... By administering its procurement through a single point of contact, the government’s job is made both simpler and cheaper. The single point of contact approach also helps suppress frivolous claims.... By forcing the prime contractor to administer its subcontractor network, the government permits prime contractors and subcontractors at all tiers to use to some extent their familiar commercial procedures in contract award and administration.... Finally, by denying the subcontractors direct access to administrative remedies, the government is forcing the prime contractor and the subcontractor to negotiate their disputes.
S.Rep. No. 95-1118, at 16-17.
As the Board correctly noted, subcontractors are generally not in privity of contract with the government.
3
See Johnson Controls,
The Board’s reliance
on. D & H
for the proposition that the CDA permits direct appeals by third-party beneficiary subcontractors was misplaced. In
D & H,
the prime contractor and the government modified their contract to provide that payment should be made jointly to the prime contractor and the subcontractor.
While the facts in
D & H
are similar to those in the present case,
D & H
differs in one critical respect. The subcontractor in
D & H
invoked the Court of Federal Claims’s jurisdiction under subsection (a)(1) of the Tucker Act, 28 U.S.C. § 1491, not under the CDA. Complaint at 1,
D & H Distrib. Co. v. United States,
No. 93-381C (Fed.Cl. Nov. 30, 1995);
see also
Brief for D
&
H Distributing Co. at v,
D & H Distrib. Co. v. United States,
Moreover, the grant of jurisdiction in subsection (a)(1) of the Tucker Act is broader than the Board’s jurisdiction under the CDA.
See
28 U.S.C. § 1491(a)(1) (“The United States Court of Federal Claims shall have jurisdiction to render judgment upon any claim against the United States founded ... upon any express or implied contract with the United States.... ”). Although privity has generally been required for suits brought under the Tucker Act,
see Merritt v. United States,
Consistent with the requirement that waivers of sovereign immunity be construed narrowly, we conclude that Floor-Pro is not a “contractor” within the meaning of the CDA. Accordingly, the Board lacks jurisdiction over FloorPro’s appeal of the contracting officer’s decision.
III. CONCLUSION
For the foregoing reasons, we vacate the Board’s decision and remand with instructions for the Board to dismiss FloorPro’s appeal.
VACATED AND REMANDED
COSTS
Each party shall bear its own costs.
Notes
. Prime contractors are permitted to sponsor claims brought by subcontractors against the government.
See
48 C.F.R. § 44.203(c). Sponsorship allows the subcontractor to proceed against the government "through, and with the consent and cooperation of, the prime, and in the prime’s name."
Erickson Air Crane Co. of Wash., Inc. v. United States,
. FloorPro argues on appeal that it was in fact a party to the contract between GM & W and the government because it "gained contractual rights and privileges through the issuance of Modification P00001.” However, FloorPro does not offer any evidence to refute the Board’s conclusion that “there is no evidence that the Government and [FloorPro] entered into a contractual relationship.”
FloorPro I,
. An exception to this rule may arise when an agency relationship between the government and the prime contractor is established by the terms of the prime contract.
See United States v. Johnson Controls, Inc.,
. The government disputes the Board's conclusion that FloorPro was an intended third-party beneficiary of the contract modification. In the government's view, FloorPro was not such a beneficiary because the modification was made after FloorPro had completed its performance on the subcontract. Because the Board lacks jurisdiction over FloorPro's claim regardless of whether it was a third-party beneficiary, we need not decide this issue.
