Plaintiff Guy F. Wing, d/b/a Franklin Homes Construction, appeals from the trial court’s order granting summary judgment to defendant Town of Landis on plaintiff’s quantum meruit claim for reimbursement of the cost of engineering plans for a water line extension. Because there was no showing that the plans were prepared in expectation of payment by the Town or that the Town received any benefit from the plans, plaintiff has failed to produce a forecast of evidence sufficient to establish each of the elements of his claim. The trial court, therefore, properly granted defendant’s motion for summary judgment.
Facts
Early in 2001, plaintiff, a developer, sought to have municipal water service extended to serve an expansion of his Highland Woods development in the town of Landis. The Town informed plaintiff that the State’s approval of any extension of service was contingent upon the Town’s obtaining an additional water source from the City of Salisbury. The Town, however, agreed to apply to the N.C. Department of Environmental and Natural Resources (“DENR”) for approval of an extension of its water service to Highland Woods. Plaintiff hired an engineer, at a cost of $22,469.00, to draft plans for the extension of service and to prepare an application for approval of the plans to be submitted to DENR. On 14 May 2001, the engineer submitted to DENR the completed application, signed by the Town’s Mayor as required by DENR.
On 21 June 2001, DENR responded to the application by letter, requesting additional information prior to processing the application. The evidence is conflicting as to whether the Town’s engineer or plaintiff’s engineer was supposed to respond to DENR’s request for additional information. In any event, neither responded.
Nevertheless, on 3 January 2002, DENR notified the Town that DENR would be able to approve expansion of the Town’s water system since an “authorization to construct” letter had been issued to the City of Salisbury permitting it to supply additional water to the Town. When the Town’s administrator called plaintiffs agent with the news, however, plaintiffs agent informed him that plaintiff no longer needed the water line extension. Plaintiff planned instead to construct community wells to serve the new homes. As a result, the water line extension has never been built.
On 5 August 2002, plaintiff filed a complaint alleging that by failing to respond to the State’s requests for information, the Town breached its agreement to apply for approval of the application and, therefore, owed plaintiff $22,469.00 in reimbursement of plaintiff’s cost in obtaining engineering plans for the water line extension. On 22 January 2003, the Town filed a motion for summary judgment, which the trial court granted in an order entered 20 May 2003. Plaintiff filed notice of appeal to this Court on 18 June 2003.
Summary judgment shall be granted “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that any party is entitled to a judgment as a matter of law.” N.C.R. Civ. P. 56(c). The party moving for summary judgment has the burden of establishing the lack of a triable issue.
Collingwood v. Gen. Elec. Real Estate Equities, Inc.,
On appeal, this Court’s task is to determine whether, on the basis of the materials presented to the trial court, there is a genuine issue as to any material fact and whether the moving party is entitled to judgment as a matter of law.
Oliver v. Roberts,
Discussion
Plaintiff concedes that his agreement with the Town regarding the DENR application is unenforceable under N.C. Gen. Stat. § 160A-16 (2003), which provides that a contract made by or on behalf of a city is void and unenforceable unless it is in writing.
See also Concrete Machinery Co. v. City of Hickory,
To recover in
quantum meruit,
a plaintiff must show that (1) services were rendered to the defendant; (2) the services were knowingly and voluntarily accepted; and (3) the services were not given gratuitously.
Scott v. United Carolina Bank,
In this case, plaintiff failed to present any evidence that the engineering plans were prepared with an expectation of payment by the Town.
See also Twiford v. Waterfield,
In addition,
"[q]uantum meruit
does not apply where no benefit accrues to the party from whom compensation is sought.”
Scott,
Here, although plaintiff had engineering plans prepared for a water line extension, the Town never received any benefit from those plans because the water lines were never built. Thus, as this Court observed in
Greeson v. Byrd,
Plaintiff nonetheless argues that the Town may still be able to use the engineering plans in the future. As the Town points out, however, it has no use for plans extending water service to Highland Woods because plaintiff now has constructed wells to serve the new phase of his development. Indeed, the planned extension was stricken from the Town’s water system expansion plans when plaintiff informed the Town that he no longer needed the water. Plaintiff offered no contrary evidence and has provided no explanation of how the Town could use the plans in the future.
Viewing the evidence in the light most favorable to plaintiff, there was no showing that the engineering plans were prepared with an expectation of payment by the Town or that the Town received a benefit from completion of the plans for the water line extension. Therefore, the court properly granted summary judgment to the Town.
Affirmed.
Notes
. The Town has not asserted sovereign immunity and, therefore, we do not address that affirmative defense.
