Wind River Mining Corporation v. United States of America Manuel Lujan, Jr. Delos Jacobson, Director of the Bureau of Land ManagementWind River Mining Corporation v. United States of America Manuel Lujan, Jr. Delos Jacobson, Director of the Bureau of Land Management
Lead Opinion
We must determine the applicable statute of limitations, if any, for challenges to federal land classification decisions.
I
On March 30, 1979, the Bureau of Land Management (“BLM”) published in the Federal Register its decision establishing 138 Wilderness Study Areas (“WSAs”) on federal land located in California. These classifications were mandated by the Federal Land Policy and Management Act of 1976 (“FLPMA”). WSAs are “roadless areas of five thousand acres or more and roadless islands of the public lands” having certain wilderness characteristics.
Wind River Mining Corporation staked certain mining claims within one of those regions, “WSA 243,” over a several-month period stretching from 1982 to September 6, 1983. After Wind River failed to file a 1983 notice of intention to hold the claims, as required by
Because Wind River’s claims are located within a WSA, Wind River is barred from pursuing ore-extraction activities on the land. See
On September 22, 1989, Wind River filed a complaint for review in federal district court from the IBLA’s 1987 refusal to declare invalid the BLM’s creation of WSA 243. Wind River sought a decree declaring WSA 243 null and void ab initio and ordering the agency to restore the property to its former multiple-purpose use. Wind River urgеd that the agency’s 1979 administrative decision was ultra vires and an unconstitutional taking.
On March 21, 1990, the district court filed an order and opinion granting the government’s motion to dismiss. The court concluded that Wind River’s action was barred by its failure to exhaust administrative remedies and by the six-year statute of limitations on civil actions against the United States set forth in
On May 10, 1990, the court issued an order denying Wind River’s motion to vacate the prior order and to reconsider its decision. The court did correct the factual error in the new order, however. In so doing, the court apparently abandoned the exhaustion rationale for denying relief, instead reiterating its ruling on the statute of limitations.
Wind River appeals both orders. Whether Wind River’s challenge is barred by a . statute of limitations is a question of law, subject to plenary review. See Sierra Club v. Penfold,
II
Although FLPMA authorizes judicial review of land-management decisions, see
We have previously held that an action commenced by filing a complaint for review of agency action is a “civil action” within the meaning of
Previously, we have suggested, without holding, that§ 2401(a) applies to the APA. Lee v. United States, 809 F.2d*713 1406, 1409 n. 2 (9th Cir.1987), cert. denied,484 U.S. 1041 ,108 S.Ct. 772 ,98 L.Ed.2d 859 (1988). We believe this suggestion to be correct.... By its terms,section 2401(a) applies to “every civil action commenced against the United States.” As a general statute of limitation, it should apply to actions brought under the APA which challenge a regulation on the basis of procedural irregularity.
Nonetheless, Wind River cites two earlier decisions of this court that arguably are inconsistent with the Penfold-Shiny Rock rule. In Coleman v. United States,
Somewhat more troubling is United States v. Webb,
There is no statute of limitations for judicial review of an administrative decision by the BLA. Thus, a BLA decision is ordinarily reviewable in a subsequent action for ejectment regardless of how much time has elapsed. See Coleman v. United States,363 F.2d 190 (9th Cir.1966), rev’d on other grounds,390 U.S. 599 ,88 S.Ct. 1327 ,20 L.Ed.2d 170 (1968). The broad rule that judicial review of BLA decisions is available without regard to passage of time is subject, however, to the rules of pleading which the Federal Rules of Civil Procedure impose upon all parties, and to the general principles of estoppel.
Id. at 979. While this case is more helpful to Wind River than Coleman, because it involves a claim which seemingly would be barred by
Penfold and Shiny Rock mandate our conclusion that
Ill
Concluding that the general statute of limitations for actions against the government applies to APA actions does not end our inquiry. The statute requires that the judicial complaint be filed “within
Several possible events could be used for measuring the date on which Wind River’s right of action first accrued. If the announcement of the BLM’s decision in the Federal Register in 1979 is chosen, then Wind River’s 1989 filing of the complaint was too late. Similarly, if the dates on which Wind River located its claims (ranging from 1982 to September 6, 1983) are used, then Wind River’s September 22, 1989 filing was still untimely. If, however, Wind River’s cause of аction did not arise until Wind River relocated its claims in 1985, or when the IBLA affirmed the BLM’s denial of Wind River’s challenges to the designation of WSA 243 in 1987, then the statutory limit had not expired by the time Wind River filed this action.
In Shiny Rock, a public land order promulgated in 1964 (and amended a year later) withdrew certain lands from appropriation under mining laws. In 1979, Shiny Rock Mining Corporation located a mining claim within the designated region and shortly thereаfter applied to the BLM for a mineral patent. In 1983, the BLM denied the application on strength of the 1964 and 1965 orders, and Shiny Rock filed a complaint for declaratory judgment in federal court.
Shiny Rock contended that its right of action, for purposes of
Shiny Rock dealt with a procedural challenge to the agency’s action. See id. at 1364; see also Shiny Rock Mining Corp. v. United States,
Other circuits have concluded that an agency regulation or other action of continuing application may be challenged after a limitations period has expired if the ground for challenge is that the issuing agency acted in excess of its statutory authority. See Public Citizen v. Nuclear Regulatory Comm’n,
In Oppenheim v. Coleman,
The District of Columbia Circuit’s approach, in our view, strikes the correct balance between the government’s interest in finality and a challenger’s interest in contesting an agency’s alleged overreaching. If a person wishes to challenge a mere procedural violation in the adoption of a regulation or other agency action, the challenge must be brought within six years of the decision. Similarly, if the person wishes to bring a policy-based fаcial challenge to the government’s decision, that too must be brought within six years of the decision. This result, even if not dictated by Penfold and Shiny Rock, would make the most sense. The grounds for such challenges will usually be apparent to any interested citizen within a six-year period following promulgation of the decision; one does not need to have a preexisting mining claim in an affected territory in order to assess the wisdom of a governmental policy decision or to discover procedural errors in the adoption of a policy. The government’s interest in finality outweighs a late-comer’s desire to protest the agency’s action as a matter of policy or procedure.
If, however, a challenger contests the substance of an agency decision as exceeding constitutiоnal or statutory authority, the challenger may do so later than six years following the decision by filing a complaint for review of the adverse application of the decision to the particular challenger. Such challenges, by their nature, will often require a more “interested” person than generally will be found in the public at large. For example, assuming that Wind River’s challenge to the designаtion of WSA 243 is merited, no one was likely to have discovered that the BLM’s 1979 designation of this particular WSA was beyond the agency’s authority until someone actually took an interest in that particular piece of property, which only happened when Wind River staked its mining claims. The government should not be permitted to avoid all challenges to its actions, even if ultra vires, simply because the agency took the action long before anyone discovered the true state of affairs.
We hold that a substantive challenge to an agency decision alleging lack of agency authority may be brought within six years of the agency’s application of that decisiоn to the specific challenger. In Wind River’s case, its September 1989 filing of a complaint for review was easily within the six-year period. The right to bring a civil suit challenging an agency action accrues “upon the completion of the administrative proceedings.” Crown Coat Front Co. v. United States,
IV
The dual orders of the district court dismissing Wind River’s complaint as barred by the applicable statute of limitations are reversed. The case is remanded to the district court for further proceedings.
REVERSED and REMANDED.
Notes
. See Order Denying Plaintiffs Motion for Reconsideration at 2-3, Wind River Mining Corp. v. United States, No. CV-89-5639-JMI (Gx) (May 10, 1990) (Ideman, J.) (¶ 6) (after noting correction, continuing: "In the instant action, however, Plaintiffs action is still barred by the six year statute of limitations.”). Wind River has satisfied the exhaustion requiremеnts of
. Under a more lenient view of what constitutes an "interested” or "affected” person, the Shiny Rock Court might not have found an accrued right of action until 1979, when Shiny Rock actually obtained an interest in the land. However, in this context we took a very broad view of "interested" party, declaring: “The only injury required for the statutory period to commence was that incurred by all persons when, in 1964 and 1965, the amount of land available for mining claims was decreased.” Id. at 1365-66 (citation omitted). Frankly, our strict view may not be in step with that of other circuits. See, e.g., Illinois Cent. Gulf R.R. Co. v. ICC,
. We recognize that in Shiny Rock as well the objection to the agency’s 1964 land withdrawal decision did not turn up until after Shiny Rock stаked a claim more than fifteen years later. The significant difference, however, is that Shiny Rock’s objection was to the agency’s noncompliance with procedural requirements for the adoption. Since the agency action was not ultra vires, the strong interest in finality justified our reading of
Dissenting Opinion
dissenting:
I agree with the majority that the six-year federal statute of limitations applies to suits challenging agency action. I further agree that the Penfold-Shiny Rock rule shоuld not apply to claims for which an agency was wholly without statutory authority to promulgate a regulation. Because I do not think Wind River’s claim can be so characterized, I dissent.
The Bureau of Land Management (BLM) created the wilderness areas in question pursuant to the Federal Land Policy and Management Act of 1976,
Wind River contests this determination, claiming that it is inconsistent with the BLM Manual. Even if this claim is accepted at face value, it does not demonstrate an absence of statutory authority vested in BLM. Instead, it merely shows that BLM’s exercise of its authority was ill-considered or, at worst, arbitrary and capricious.
The fact that Wind River chose to describe BLM’s actions as “ultra vires” in its complaint does not change this analysis. While it is true that courts must take plaintiffs allegations as true in resolving motions to dismiss, that rule apрlies only to factual allegations. See Usher v. Los Angeles,
I do not think we can allow a plaintiffs unsupported legal characterization to preclude disposal of cases on a motion to dismiss. See Western Mining Council v. Watt,
In Sisseton-Wahpeton Sioux Tribe v. United States,
. The interpretation of the agency charged with administering a statute is given great deference. See Brock v. Bechtel Power Corp.,
. A good example of this difference can be found within
Here, however, BLM merely exercised its authority to define and interpret the word "road-less." It concluded that the “Kelso Road” was in fact a deteriorated way, rather than a road. Wind River may claim that that determination was wrong, but not that BLM had no authority to make that determination.