21 Haw. 87 | Haw. | 1912
Lead Opinion
OPINION OP THE COURT BY
This is an-appeal from a decree of a circuit judge, sitting iu equity, whereby the respondeuts were perpetually enjoined from performing, or partaking in the performance of, a certain contract for the construction of a public road in the City and County of Honolulu. The contract was awarded to the respondent, Lord-Young Engineering Oo.,‘ Limited, by the respondents Campbell, Eern, Adams, Petrie and Dwight, acting as a commission appointed pursuant to section 5, Act 166 of the Laws of 1911. The complainant, who was an unsuccessful bidder for the contract, brought this suit as a taxpayer alleging that he and not the Lord-Young Engineering Co. was the lowest responsible bidder. The statute (Act 62 of the Laws of 1909, as amended by Act 41 of the Laws of 1911,) provides that, with certain exceptions, no expenditure of public money where the sum to be expended shall be one thousand dollars or more shah be made except under contract let after public advertisement
Additional facts are to be found stated in the opinion of Mr. Justice Perry wherein also are contained our reasons for holding that the specifications upon which the bidders based their tenders were so indefinite and uncertain in respect to the time within which the contract was to be performed as to prevent real competition between the bidders, and that a valid contract could not be founded on them. That ground alone is enough to require the affirmance of the decree, but in view of the importance of the case because of the fact that public contracts are constantly being let by officers acting under the statute here involved we deem it our duty to express our views with reference to the procedure followed by the commission in considering the bids and awarding the contract in question.
The trial judge found as a fact that the complainant was the lowest responsible bidder and the finding was fully supported by the evidence. That alone would not, howfever, be conclusive of the complainant’s right to the relief sought because if upon a fair and impartial public hearing the commission had found up
“The Loan Fund Commission,
City and County oe Honolulu.
Gentlemen :
At a meeting of'this Commission held on September 29th, 1911, I was authorized and directed to investigate the responsibility as contractors of Mr. Theo. Bauman, the Lord-Young Engineering Company, Limited, and Mr. John H. Wilson.
I beg to malee the following report:
*91 I have found no record of irresponsibility on the part of Theo. Bauman as a contractor. I am informed by credible business men that his record is good.
So far as I can learn the Lord-Young Engineering Company,Limited, also has a good record for responsibility as contractors, as an instance of which it is stated that although they are reported to be losing on one of their operations by contract, namely the Hilo Breakwater, now under way, they are continuing to perform their obligations in good faith. Our engineer, Mr. Gere, has a criticism of Mr. Young’s attitude toward the Queen Street paving proposition for the City and County Government, but I did not understand Mir. Gere to question the responsibility of the firm as contractors.
I am informed that Mr. J. H. Wilson has failed to complete two contracts which he has undertaken, one for the County of Kauai, and one for the Territory. I have sent a wireless message to the Vice-Chairman of the Kauai Board of Supervisors, asking for information bearing on the Kauai contract. I am informed that the County of Kauai was not put to additional expense by the failure of Mr. Wilson to complete his contract. I understand Mr. Wilson claimed that certain machinery used by him was not delivering the guaranteed amount of material and that, therefore, he could not perform the work as rapidly as he had expected to be able to do. I understand also that the County Government of Kauai caused an engineer to be sent to them from Honolulu and that after certain repairs were made to- the machinery it was found to- have the capacity of delivering a greater' amount of material than was required. • T understand further that the Kauai authorities claimed the machinery had not been properly operated by the contractor. T would state that I am informed that the machinery used by Mr. Wilson on the Kauai contract under question is a duplicate of the plant which the Supervisors of the City and County of Honolulu will lend to this Commission for use on Section No. 1 of the Oahu Belt Road, the-bids for the construction of which are now being considered by this commission.
■ I quote the following from a published report of the Superintendent of Public Works, now incorporated in the public records, under the title
*92 'Loan Appropriations.
Completion and Extension of Sewerage, Honolulu.
A contract was made July 5th, 1899, with J. H. Wilson under the firm name of Wilson & Whitehouse, for the construction of the Outfall Sewer, the same to be completed July 1st, 1900, but his progress'was so slow that at the expiration of the time specified little had been accomplished beyond laying that part of the Outfall which consists of vitrified pipe, a length of 1500 feet in shallow water, and his methods were so manifestly inadequate for the carrying out of the work, that on September 10th, the contract was taken awiay and the work continued by the Government. The completion of his contract would have entitled him to receive a total amount of something in excess of $28,000. The actual payment made to him under the contract amounted to $6,656.60.’
I am informed that since the last above mentioned contract Mr. Wilson has performed satisfactory work by contract on Maui, and also that under the last Board of Supervisors he completed the Kahana beach contract on this island to the satisfaction of the Supervisors.
Nespectfullv submitted,
Andrew Adams.
Honolulu, October 3rd, 1911.”
In addition to what is contained in the written report it appears that the chairman stated that he had been told by W. E. Nowell, who was superintendent of public works at the time of the letting of the outfall sewer contract, that Wilson’s bid for the work was ridiculously low and his methods were all wrong, but that he did not blame Wilson as he thought no man could have done the work for the amount of the bid. The chairman also stated that he was informed that Wilson’s bondsmen on that contract had lost about twTenty-one hundred dollars which Wilson had never made good; that in connection with the road contract on the island of Kauai the Hawaiian Sugar Oompany had lost four hundred dollars; and that the manager of the company’s plantation had stated that he did not care to have any further business connection with Wilson. It was not explained
The testimony given by the chairman of the commission before the circuit judge shows that in making the investigation he did not have in mind Wilson’s financial responsibility nor his ability and skill to do the work. He seems to have regarded those qualifications as being conceded. He testified that his inquiries were directed solely to the question whether Wilson was “the type of man who stood from under when he got into a hole,” or Would “live up to his contracts whether pinched or not.”
The evidence shows that the principal charges made against Wilson — and the only charges which need be referred to hei’e— were his failure to complete the work under the outfall sewer contract and the Kauai road contract. With reference to those matters neither the commission or its chairman made any attempt to get from Wilson any statement as to why he failed to carry out his contracts. No opportunity was given. Wilson to present his side of the case though he was available and, appar
In considering tenders for public contracts under a statute providing for the letting of contracts to the lowest responsible bidders, the awarding officers have a wide discretion. But that, discretion must be exercised fairly, honestly and judicially. The phrase “responsible bidder’’ means one who is not only financially responsible, but who is possessed of the judgment, skill, ability, capacity and integrity requisite and necessary to perform the contract according to its terms. The duty of such officers in considering and determining those matters is an important and responsible one, and one upon the performance of which the taxpayers have the right to insist. The refusal.to award a contract to the lowest bidder can be justified only when it has been made to appear ujion a proper hearing and investigation that he is not a responsible bidder. 2 Dillon, Mun. Corp. (5th ed.) Sec. 811.
The decree appealed from is affirmed.
Concurrence Opinion
CON CURRIN G OPINION OP
One of the grounds of the petition is that the contract and the award are null and void for the reason that “the said specifications and advertisement for bids were indefinite, uncertain and incomplete in that they did not name any time within which the work thereunder was required to be completed and did not state whether or not the time for completing the work named'by a bidder would be considered by the commissioners in determining the lowest responsible bidder or provide any means of fixing or estimating the value in money of the-difference in time between the several bids so that intelligent and exact bidding and fair and equal competition was impossible, and it was and is impossible for the commissioners to definitely ascertain who among the bidders for said contract was, in fact, the lowest responsible bidder therefor.” The published call for tenders required that all bids for the construction of the road should be filed with the commission on or before September 28, 1911. The Lord-Young Engineering Company offered to do the work specified for the sum of $79,710 and to complete it by September 1, 1912. The complainant presented a bid in the sum of $79,367, performance to- he completed by December 1, 1912. Other bids in due form, with time of completion, were those of T. Bauman, $88,950, September 30, 1912; L. IVf. Whitehouse, $93,518, October 31, 1912; Concrete Construction Company, Limited, $91,462, October 31, 1912,. and the Honolulu Draying & Construction Company, $109,250, January 31, 1913.
The specifications related to the grading, metaling and oiling of 26,358.7 linear feet of highway, the construction of culverts, drains, ditches and walls, the removal and erection of fences
Act 166 of the Laws of 1911, appropriating $200,000 for “belt roads and bridges” in the City and County of Honolulu, provides in section 3 that “the provisions of Act 62 of the laws of 1909, and amendments thereto, shall apply to all said items to the same extent as if they were a part of this Act”, with exceptions not material to' this case. Act 62 of the Laws of 1909, as amended by Act 47 of the Laws of 1911, in turn provides that “no expenditure of public money * * * where the sum to be expended shall be One Thousand Dollars ($1,000.00) or more, shall be made, except under contract let after public advertisement for sealed tenders, in the manner provided by law,” and that “all such contracts * * * shall be made with the lowest responsible bidder and' after publication of a call for
The specifications in idle case at bar fail in at least one respect to comply with these requirements. They are indefinite and misleading with reference to the time within which the contract is to be performed. The natural inference from what is said in the specifications, form of bid and call for tenders is that time will be deemed of importance by the commission and will be considered in making an award, but of how much importance and of what monetary value it would be impossible for intending bidders to ascertain from those instruments. Each bidder was left at liberty to name his own time. AVithin certain limits, at least, a shortening of the period for construction would ordinarily result in greater cost to the contractor and consequently to the taxpayers and a lengthening of it in a decrease of the cost. Each of the bidders made his tender in ignorance of the time to be named by each of the others and was given no opportunity of meeting opposing bids upon the same allowance of time. The commission did not express itself 'in the instruments under consideration as being bound to consider the element of time and it was open to it either to consider or to disregard the differences in the bids in that respect and, if the element was taken into consideration, to give as great or as low a monetary value to the difference as it should see fit. The specifications and advertisement left the commission at liberty to choose either a bidder who had named the lowest price and
To furnish a common standard for the competition either a reasonable time should be named in the specifications for the performance of the contract (or two or more alternative, reasonable periods), or, if the bidders .are left to name the proposed time of completion, the specifications should state the value of the difference in time between bids and thus furnish the means of reducing the bids to a common standard of measurement, or if one or more periods for performance are specified liberty may be given to the bidders to name a different period, the value of the difference in time being in such event also stated, or it should be specified that the award will be to' the bidder (responsible) naming the lowest price irrespective of the time required by him for the performance of the contract.
It is clear, without reference to the other grounds named in the bill of complaint, that the injunction prayed for and granted must stand and the contract in effect be set aside. Upon a new and valid call for tenders it may be that, aside from any question of his responsibility, Wilson will not be the lowest bidder, or it may be that, if he is the lowest bidder, the commissioners will find him to be the lowest responsible bidder and that fur
Under these circumstances I base my concurrence in the affirmance of the decree upon the sole ground that the specifications were fatally defective and the award and the contract for that reason invalid. Consideration of the other grounds is unnecessary to the decision of the case now before the court.