194 F. 838 | 3rd Cir. | 1912
Wilson, the plaintiff in error, an architect by profession, entered into a written contract with one Brown, the owner of a iot of land in the city of Philadelphia, by which it was agreed that lie should build for the said Brown upon said lot 26 houses. The contract was a complete and entire building contract, the houses to be delivered when finished, according to the specifications drawn up by Wilson and accompanying the contract. Eor performance on his pari Wilson was to receive a lump sum, payable in certain instal-ments as the work progressed. By a special stipulation, the owner was relieved from any responsibility for loss or damage which might happen during the course of the work of construction, or for any material or other things furnished or supplied by the contractor. There was also the usual stipulation in which the contractor covenanted to save Erom and keep harmless the owner from the filing of mechanics’ liens lw himself or any sub-contractors. It was further agreed that the said contractor, Wilson, should not “sublet any part of the general contract to construct said operation.” Under this contract, the defendant entered into possession of the premises, for the purpose
During the progress of the work thus provided for, a brick wall on a stone foundation had been built, with a certain pier therein, by the sub-contracting mason. Afterwards the plumbing contractor, in making excavation for the reception of soil pipes, dug a trench under the said brick pier and allowed the same to remain open and to fill with water from the rains that were then prevalent. While the pier was in this undermined condition, Hibberd, the plaintiff below, while working in the second story and pounding on the jamb of a door against the said pier, was suddenly precipitated from the place where he was working to the ground below, by reason of the falling of said pier, and suffered the injuries complained of. The suit in the court below was in consequence brought against the defendant, Wilson, the general contractor, to recover damages suffered by plaintiff by reason of the falling of said pier.
The statement of claim alleges that plaintiff was, at the time of the accident, employed by the sub-contracting carpenter and that the defendant was the builder of the property in question; that while so employed, defendant neglected to properly construct and maintain certain walls and foundations and to provide proper methods for “providing against the elements,” and neglected to require the filling in of various excavations and permitted the plumbing contractor or others to excavate at or about the foundations of the wall in a careless, negligent and dangerous manner, and allowed them to permit such excavations to remain in such condition as to become dangerous.
It appears from the evidence (and there is no dispute about the material facts in the case) that the plumber, under his sub-contract, was required to do his own excavating; that the trench dug for the soil pipe was improperly made to extend under the brick pier in question, and the expert testimony clearly show’s that it would have been convenient, as well as proper, to have placed the pipe in another trench already open which did not so undermine the pier. It also appears that the undermining trench, in which the soil pipe was laid, was not covered over, but was allowed to remain open, and that the rains filled it with water. It is also in evidence that the brick pier itself, after it had fallen, appeared to be a mass of soft material, indicating that the mortar had not entirely hardened when the trench was dug.