75 W. Va. 143 | W. Va. | 1914
In this action of assumpsit for money alleged to be due upon a building contract, the defendant set up a number of counter
The plaintiff in error complains of three items found against him, one of $266.75, the cost of a plate glass front with the expense of drayage and crating, another of $58.81 for steel beams alleged to have been put into the building as extras, and another for $60.45, the value of 465 cement or terra cotta blocks, which the plaintiff claims to have furnished for a part thereof not included in his contract. He also complains of the disallowance of two of his counter-claims, one of $45.00 for one-half of the premiums paid on policies of insurance on the building, while in course of construction, another of $127.50 for loss of rent, alleged to have been occasioned by the refusal of the plaintiff to deliver the keys to the building, after completion, in consequence of which the prospective tenant of a portion thereof could not.be admitted.
Cross-assignments of error by the plaintiff are founded upon the disallowance of two items for commissions, amounting respectively to $88.08, $77.38 and claim of $240.00 for part- of the compensation o'f a time-keeper. He further complains of two findings in favor of the defendant, one as to an item of $118.56 for deficiency in materials used in the roof, and the other of $24.50 for failure to bridge the roof joists.
The glass for which the disputed claim is made was delivered upon the premises of the defendant, but rejected by him because, in his opinion, it was not of the quality or kind called for by the plans and specifications, although the plaintiff claims he ordered it in accordance therewith. It was prepared for union at the corners by what are called “Col-som Bars.” The defendant wanted beveled glass united at the corners by cleats or clasps. The plaintiff says the defendant did not object to the glass, until he understood how it was;
Though the bill for extras charges extra steel beams, there is no pretense that any were used. The evidence adduced in support of this charge proves the extension downward, by wood frame work, of certain steel cross beams in the seiling, so as to render them co-extensive with the beams running lengthwise through the building and thus make the partitions between the panels uniform and facilitate the putting on of the metal ceiling. As to whether or not this was extra work, there is nothing decisive in the evidence. The plaintiff claims it was and the defendant says it was not. Manifestly the contractor carries the burden of proof on an issue of this kind, for his general contract presumptively covers all the work, wherefore he must show, as to any particular item, that it is not within the general contract. But he swears this was extra work, the owner denies it, the court has decided in the affirmative and no controlling fact or circumstance showing error in the finding is perceived. If the architect had been employed to superintend the work, the failure of the contractor to obtain his decision upon the question in dispute would likely conclude him, but he was not in charge of the work. The owner himself, an interested party, undertook the work of superintendence.
The charge for cement or terra cotta blocks was improperly allowed. It was made on the contractor’s books from the report of a time-keeper who admits it was not reported, upon his personal knowledge, but only upon information from some unnamed workman on the building. Less than half the number charged for were used and they were put in the basement, a part of the structure not included in Williamson’s contract. The owner proves his purchase of such blocks from strangers in quantity sufficient for the requirements of the building. These corroborating circumstances clearly overcome the slight and uncertain evidence adduced in support of the charge.
There was no right of detention of the keys of the building by the contractor, as a means of compelling a settlement,
One-half of the cost of insurance should have 'been allowed to the owner. The contract and specifications required him to keep the property insured for the benefit of both parties, and the specifications made a part of the contract expressly provided that the cost of the insurance should be borne by them equally.
The counter-claims for defective material were properly allowed to the owner. Smaller joists than the specifications prescribed were used and fewer of them and the bridging required was omitted.
Nothing in the evidence warrants disturbance of the findings by the commissioner and the court against the contract- or’s claims for commissions and compensation .paid to his time-keeper. These items relate to the third story built under a verbal contract. The contractor says he was to have a commission on the materials for it as well as on the labor, while the owner says he was to pay a commission on the labor only. Bills for materials without any addition for commission were paid while the work was in progress and at least one bill for commission on labor only was paid. These circumstances corroborate the defendant. The time-keeper’s services were general, applying to other work as well as that done for the defendant, and the charge is for one-half of it: and besides the charge of $10.00 or $15.00 seems to be exorbitant, since
Correction of the errors noted here reduces the plaintiff’s right of recovery to $381.72, wherefore the judgment complained of will be reversed and judgment rendered here for said sum with interest thereon from the 6th day of June 1912, the date of -the judgment below, with the costs in the trial court but.costs in this court will be adjudged to the plaintiff in error, who substantially prevails.
Reversed and Rendered.