History
  • No items yet
midpage
Williams v. Thrall
101 Wis. 337
Wis.
1898
Check Treatment

The following opinion was filed October 11, 1898:

Cassoday, C. J.

The verified complaint is an ordinary complaint to enforce a mechanic’s lien, and alleges, in effect, that the plaintiffs, as principal contractors, sold, furnished, and put into the house of the defendant Thrall the combination hot-air and hot-water heating apparatus, for the agreed price of $460, and extras to the amount of $5.25, making $465.25; that no part thereof had been paid except $300; that there was still due and unpaid $165.25,— and prayed for the customary judgment.

*339The defendants Thrall and wife answered, to tbe effect that tbe beater was put in tbe defendants’ bouse, by tbe plaintiffs, under a written contract wherein they proposed, in effect, to furnish and place in tbe defendants’ residence-a combination bot-water and warm-air beating apparatus, and No. 63 Prince Eoyal combination furnace, and would furnish and connect tbe same with tbe registers in tbe several rooms designated, tbe work to be completed October 1, 1895, unless delayed by tbe defendant or from some cause for which be was responsible; that tbe apparatus when completed was thereby guaranteed to beat tbe entire bouse to '80°, and the bath rooms to 85°, in the coldest weather, with reasonable consumption of fuel; that the furnace, with all material furnished by tbe plaintiffs, should remain tbe property of tbe plaintiffs until the contract price should be fully paid, and tbe defendants should be liable for any damage to tbe apparatus after completion until that amount should be paid in full; that the price for the work should be $460, payable, $300 upon completion of the job, and $160 January 1, 1896; that it was therein further agreed that, should tbe furnace fail to meet the requirements as specified, the plaintiffs thereby agreed to replace the same with a beating apparatus that would fulfill tbe requirements, without extra cost to tbe defendants, and that the plaintiffs would pay for all damages caused on account of any deficiency in said furnace; that all work was to be done in a thorough, workmanlike manner; that on the same day the defendant, by bis written indorsement on tbe back of such proposition, accepted tbe same, with all its conditions; that tbe plaintiffs failed and neglected to construct and erect such beating plant according to the terms and conditions of the contract; that, instead thereof, tbe one placed therein was not according to the contract, nor constructed in a good, workmanlike, and proper manner, and was entirely inadequate to beat tbe entire bouse to 80°, and tbe bath rooms to 85°, in tbe coldest weather, *340with reasonable consumption of fuel, and was not completed until December 26, 1895.

In addition to tbe denials and such defense, tbe defendants alleged sucb failure to perform tbe contract, and tbe damages thereby sustained, as a counterclaim, and, among other things, that they bad been damaged on account thereof, and on account of what it would cost them to construct and erect such heating apparatus according to the terms and conditions of the contract, and of the capacity and ability provided for in the contract, in the sum of $100. The plaintiffs replied to the counterclaim.

The cause was thereupon tried by the court without a jury. At the close of the trial, the court found, as matters of fact, in effect, that the written agreement was made as stated in the answer; that the work was done by the plaintiffs on the heater in a thorough; workmanlike manner so far as the workmanship was concerned; that the same was not completed until December 26, 1895; that the defendant Thrall has used the apparatus for two seasons, and was still using it, and had not removed the same, nor demanded or requested the plaintiffs to remove the same or replace it with another apparatus; that in January, 1896, and frequently thereafter, the defendant notified the plaintiffs that the apparatus did not fulfill the guaranty in the contract contained; that the apparatus when completed would not heat the house to 80°, and the bathrooms to 85°, in the coldest weather, without continuous and careful firing and unreasonable consumption of fuel; that with soft coal and continuous and careful firing it could be done, but that then some of the rooms would be heated to 90° and upward; that in January, 1896, and after the completion of the apparatus, the defendant agreed with the plaintiffs to accept the apparatus if it would heat the house to 15°; that the apparatus would not heat the house to 15° in the coldest weather without frequent and careful firing, and without an unrea*341sonable consumption of fuel; that, except in the coldest weather, the apparatus served its purpose fairly well; that the consumption of fuel by the apparatus was reasonable in ordinary weather; that the price of the apparatus, as stated in the contract, was $460, and that, -if it had complied with the requirements of the contract, its value would have been that sum; that the value of the apparatus as constructed was only $360, and the damage to the defendants for the breach of warranty was $100; that $300 had been paid; that the balance of $160, by the terms of the contract, fell due January 1, 1896; that the plaintiffs furnished to the defendants extras of the value and at the agreed price of $5.25, which fell due January 1, 1897; that the facts found were sufficient to authorize a lien; that the claim for a lien had been duly filed; and that the plaintiffs were entitled to a lien for $65.25 and interest and costs,— and ordered judgment accordingly.

From the judgment so entered, the defendants Thrall bring this appeal.

There can be no question but that the agreement was an entire contract. By its terms, the plaintiffs were to receive nothing until they completed the job. The trial court found that they never did complete the job.' Their right to recover anything upon the contract necessarily depended upon its full performance according to its terms. Cook v. McGabe, 53 Wis. 254, 255, and cases there cited; Moritz v. Larsen, 70 Wis. 569; McDonald v. Bryant, 73 Wis. 26; Fuller-Warren Co. v. Shurts, 95 Wis. 606; Pormann v. Walsh, 97 Wis. 356.

Counsel contends that, when the defendant ascertained that the furnace failed to perform as' stipulated, he should have rescinded the„contract, or requested the plaintiffs to remove the furnace or replace it by another, or removed it himself and replaced it by another. But there is nothing in the contract requiring the defendant to do any of those *342things, nor to do anything else, except to pay as agreed, upon complete performance. It does not appear that the defendant ever waived his right to such full performance. True, the trial court finds that he agreed to accept the apparatus if it would heat the house to a certain less temperature than stipulated, but that it would not do so. Upon the facts found, we must hold that the plaintiffs can recover nothing.

The question recurs, What is the measure of the defendant’s damages ? The contract provides that, in case the furnace failed to perform as agreed, the plaintiffs would replace it with one that would fulfill such requirements, without extra cost, and would pay all damages caused on account of such deficiency. We agree with counsel for defendant that his damages are what it will cost the defendant to put in a heater of the required capacity. It appears from the evidence that it will cost the defendants to put in a heater to heat the house to 80° in the coldest weather, with reasonable consumption of fuel, $415, in addition to the furnace now in use, and upon which the defendant has paid $300, mating the total cost $115. In other words, it will cost the defendant $255 more than he had agreed to pay. From this shoifid be taken the $5.25 for extras mentioned, leaving a balance for $249.15, which amount, with interest from the time of the commencement of this action, the defendants are entitled to recover from the plaintiffs.

By the QouH.-— The judgment of the circuit court is reversed, and the cause remanded with direction to enter judgment in accordance with this opinion.

A motion for a rehearing was denied December 16, 1898.

Case Details

Case Name: Williams v. Thrall
Court Name: Wisconsin Supreme Court
Date Published: Dec 16, 1898
Citation: 101 Wis. 337
Court Abbreviation: Wis.
AI-generated responses must be verified and are not legal advice.
Your Notebook is empty. To add cases, bookmark them from your search, or select Add Cases to extract citations from a PDF or a block of text.