274 S.W. 935 | Mo. Ct. App. | 1925
At the last term we handed down an opinion in this cause, but granted a rehearing. The first count is based on an alleged failure to furnish cars for interstate shipments and the second count is based on an alleged failure to furnish cars for intrastate shipments. On oral argument at the last submission counsel for defendant conceded that there is no error of sufficient consequence to justify a disturbance of the judgment on the second count, hence this opinion concerns the first count only.
After some preliminary allegations plaintiff alleges: "That on or about the 20th day of October, 1922, the plaintiff notified the defendant at the said station of Winona that on the 21st day of October, 1922, he would have at said station of Winona four carloads of cattle to be carried by the defendant from said station of Winona, Missouri, to St. Louis, Missouri and to the National Stock Yards, Illinois, and to be then and there placed on the market for sale; that the defendant promised and agreed with the plaintiff that on said 21st day of October, 1922, the defendant would have and provide at said station of Winona, four cattle cars for the transportation of said cattle to St. Louis, Missouri, and thence to the National Stock Yards, Illinois, on its local freight train scheduled to leave said station of Winona, Missouri, at — hour, or about said hour. That in pursuance of said agreement and understanding he drove his said one hundred *669 and fifty-five head in number and sufficient to fill four cars near to the said station of Winona, and had them ready and in time on said date to be loaded for shipment on said date and train, but that the defendant failed to provide the said cars for the transportation of said cattle on said date, and although requested by the plaintiff to provide the said cars on the 20th day of October, 1922, and on every other day from and after the 20th day of October, 1922, until the 20th day of November, 1922, the defendant utterly failed and refused to provide the said cars for the transportation of said cattle on said day and on every other day between said date and November 20, 1922. That if the said cars had been provided and the said cattle shipped on said day as agreed upon, the said cattle would have reached St. Louis and National Stock Yards, Illinois, in due course of transportation, in time to have been placed on the market at National Stock Yards, Illinois, on the 22d day of October, 1922, but on account of the defendant's failure to furnish and provide the cars as aforesaid, the plaintiff's said cattle did not reach the National Stock Yards, Illinois, until November 20, 1922, and that then the plaintiff was compelled to drive his said cattle to Ellington, Missouri, a station of the Missouri Pacific Railway Company, and located at a great distance from plaintiff's place of business, and shipped over said Missouri Pacific Railway Company to said Market, and that by reason of defendant's failure to furnish said cars, as aforesaid, that the market price of said cattle had declined on the market at the National Stock Yards, Illinois, an average price of $1.25 per hundred pounds between the 22d of October, 1922, and the 20th day of November, 1922, and on account of said decline in the market, the plaintiff had to sell the said cattle, and did sell them for $750 less than they would have brought if they had been placed on the market on October 22, 1922. That the plaintiff was also compelled to expend the sum of $300 in feeding, pasturing, *670 watering and caring for said cattle during the time he was delayed in shipping the same.
Wherefore, the plaintiff says that he has been damaged by the acts of the defendant aforesaid in the sum of $1,050, for which and for his costs he prays judgment."
The answer is a general denial, and the shopmen's strike, but defendant stood on its demurrer at the close of plaintiff's case, and no evidence concerning the strike was offered. In the first count plaintiff alleges that on October 20th he notified the defendant at Winona, Mo., that on October 21st he would have at Winona, four car loads of cattle to be shipped from Winona to National Stock Yards, Illinois, and that defendant promised and agreed with plaintiff that on October 21st it would furnish plaintiff the four cars in which to ship said cattle to National Stock Yards, Illinois; that defendant failed to furnish said cars, etc. It will be observed that plaintiff's petition is founded upon an alleged breach of an agreement to furnish cars.
Under the law pertaining to car service for interstate shipments defendant could not make a valid agreement to furnish cars. The whole subject of car service for interstate shipment is controlled by the interstate Commerce Commission acting under the provisions of the Interstate Commerce Act as amended February 28, 1920. [United States Comp. Stat., 1923 Supplement, sec. 8563 et seq.] Paragraph 13 of said section 8563 authorizes the Commission to require all carriers by railroad subject to the act to file with it their rules and regulations with respect to car service. The tariff provision of defendant respecting orders for cars for live stock shipments in interstate commerce filed with and approved by the Commission is as follows: "Orders for cars must be placed with carrier's agent in writing, a reasonable time in advance, stating the number, size and kind of cars, destination and date wanted. For convenience, cars may be ordered by telephone, in which case *671 confirmation must be given in writing." Rule No. 2798, Circular 17-E of Western Trunk Lines.
In Cornwell v. Davis, Agent, 213 Pac. (Mont.) 218, plaintiff alleged that on September 23, 1918, he was the owner of two hundred and thirteen head of cattle which be desired to ship to market; that the cattle were then upon the public range, some thirty-five miles from Glasgow, Montana; that on September 23rd he ordered from the local agent nine suitable cattle cars to be at Glasgow on October 2nd for the transportation of his cattle to the Union Stock Yards at Chicago; that the local agent then and there agreed with and promised plaintiff that the cars would be furnished at the time and place designated; that the time intervening between the dates mentioned was reasonable; that in reliance upon the promise plaintiff caused his cattle to be driven to a point near Glasgow where they arrived October 1st; that he immediately caused notice to be given to defendant that he would be ready to load on October 2nd; that defendant failed, neglected and refused to furnish the cars on October 2nd, and did not furnish them until October 16th; that plaintiff was compelled to return his cattle to the range for feed, and because of extra handling the cattle were greatly reduced in weight, and because of the delay he was forced to sell upon a lower market. The Supreme Court of Montana affirmed a judgment for the plaintiff predicated upon the facts as stated. The cause reached the Supreme Court of the United States by writ of certiorari, which court held that under the provisions of the Interstate Commerce Act tariff provisions must be strictly observed, and that a contract by a railroad company to provide a shipper with cars for interstate shipment on a day certain was void. [Davis v. Cornwell,
In Missouri Pac. R. Co. v. Henderson, 247 S.W. (Ark.) 1070, it appears that the plaintiff Henderson on October 13, 1919, called the agent at Conway, Ark., and notified him to have a cattle car ready on the 16th for shipment to National Stock Yards, Illinois; that the agent accepted the oral notice; that pursuant to the notice plaintiff drove his cattle a distance of twenty miles to Conway where he was compelled to wait a week before he got a car. Plaintiff sold on a lower market and on the above facts recovered judgment for damages. The Supreme Court of Arkansas recognized that an oral agreement to furnish cars for interstate shipment was void, but construed the cause to be one for the failure to furnish cars "within a reasonable time after notice to do so." The Henderson case also went to the Supreme Court of the United States by writ of certiorari. [See Davis v. Henderson, 69 L.Ed. ______ Adv. Ops. Page 22.] The judgment in the Henderson case was reversed. The court said: "There is no claim that the rule requiring written notice was void. The contention is that the rule was waived. It could not be. The transportation service to be performed was that of common carrier under published tariffs. The rule was a part of the tariff." As supporting the conclusion reached the court cited Georgia, F. A.R. Co. v. Blish Mill Co.,
In Underwood v. Hines, 222 S.W. (Mo. App.) 1037, it appears that the agent on March 30th agreed orally with the shipper to have three cattle cars ready on April 2d at Tibbets, Mo., for shipment to National Stock Yards, Illinois. Plaintiff relying upon the contract delivered his cattle at the station, but did not get the cars until a week later. He sued and recovered in the trial court for *673 extra feed and labor, there being no question of a lower market. The Kansas City Court of Appeals in an opinion by Judge TRIMBLE held that plaintiff could not recover.
A cause of action cannot under the law arise from a breach of contract oral or written to furnish cars for shipment of live stock in interstate commerce, because such a contract under the law is void. The tariffs filed with and approved by the interstate Commerce Commission prescribe the manner in which cars for live stock shipment in interstate commerce shall be ordered. And when the tariff rule is complied with, and the carrier fails to furnish cars as ordered within a reasonable time it is liable to the shipper for a breach of duty created by law, and not for breach of contract.
Plaintiff's petition is bottomed upon a breach of an agreement to furnish cars. His instruction permitted recovery if the jury found "that the plaintiff, on the 20th day of October, 1922,notified (Italics ours) the defendant at the station of Winona, Missouri, that on the 21st day of October, 1922, he would have at said station of Winona, Missouri, four car loads of cattle to be carried by the defendant from the station of Winona, Missouri, to St. Louis, Missouri, and to the National Stock Yards, Illinois, and there placed on the market for sale, and if you further believe and find that the defendant failed to furnish said four cattle cars on the 21st day of October, 1922, at Winona, Missouri, or within a reasonable time of said date for the transportation of said cattle to St. Louis and the National Stock Yards, Illinois; and if you further find that between said 21st day of October, 1922, and the 20th day of November, 1922, plaintiff repeatedly requested defendant to furnish said cattle cars, and that during this time the plaintiff had the cattle ready for shipment; and if you further find that the defendant during all this period of time failed and refused to provide said cars for the transportation of said cattle, and that on November 20th, 1922, plaintiff was compelled to, and did, drive his cattle to Ellington, Missouri, and ship *674 them from said Ellington, Missouri, over the Missouri Pacific Railway Company to St. Louis and National Stock Yards, Illinois; and if you further find that the defendant, St. Louis and San Francisco Railway Company, failed to furnish cars at the time stated therein, or within a reasonable time thereof, and that plaintiff was damaged by reason of the failure of defendant to furnish said cars for the transportation of plaintiff's cattle within a reasonable time after said notice, if they did fail to furnish cars, then you should find the issues for the plaintiff under the first count of his petition and give his whatever damages you believe, from the evidence, that he has sustained, as defined in this and other instructions, but not exceeding the sum of $1,050."
Under the most liberal construction this instruction would permit recovery if the jury found that plaintiff notified orally or in writing defendant that on a certain date he would need four cars, and further found that defendant failed to furnish said cars on said date or within a reasonable time thereafter. Under this instruction the order for the cars was not required to be in writing, and the record does not definitely show that the order for these cars was in writing. Furthermore by way of emphasizing that an oral order was sufficient the instruction directs attention to the evidence tending to show that Plaintiff repeatedly requested defendant to furnish said cars after October 21st. The first count of the petition should be amended and all references to agreements to furnish cars and breach thereof should be eliminated, and plaintiffs cause, if such he has, stated as for a breach of duty to furnish cars for interstate shipment after reasonable notice in writing. And the instruction, if any is given, should conform to the law pertaining to the furnishing of cars for interstate shipment as herein stated.
Defendant challenges the instruction on the measure of damages on the first count and complains of the refusal of its instruction on the same subject. Plaintiff's *675 instruction permitted recovery for the following: (1) The difference between the market price at National Stock Yards when the cattle should have arrived had there been no delay, and when they did arrive after the delay; (2) a reasonable amount for feed, pasture and labor in caring for the cattle during the delay. Defendant's refused instruction limited the damages to the difference between the market value of the cattle at National Stock Yards, Ill., on the day when the cattle would have arrived had there been no delay, and their market value at Winona, Mo., on same date.
At common law it is the duty of railroad companies to furnish cars to shippers upon reasonable notice. [10 C.J., p. 73, sec. 66; Darlington Lumber Co. v. Railroad,
In Morrison v. St. Louis-San Francisco Ry. Co., 264 S.W. 449, we stated the rule for the measure of damages for failure to furnish cars for intrastate shipment. In the absence of a statute we believe that the same rule *676 should prevail as to interstate shipments. In the Morrison case we said: "The measure of damages which result from delay in shipment, and applicable, we think, for damages resulting from unreasonable delay in furnishing stock cars, is the difference in the market price at the place of destination when the shipment should have arrived and when it did arrive, plus the additional expense incurred because of the delay." We would modify this rule by limiting the additional expense incurred to read: "Plus a reasonable expense incurred because of the delay."
On a retrial the instruction on the measure of damages will be so framed as to conform to the rule as herein stated. The judgment as to the second count is affirmed, and as to the first count the judgment is reversed and cause remanded. The whole cause, however, is remanded, and when final disposition on the first count is made, judgment on the whole cause will be entered. It is so ordered. Cox, P.J., and Bailey, J., concur.