71 Iowa 367 | Iowa | 1887
The petition in this case is a remarkable document. It is remarkable for its great length, and for the indefiniteness of its averments as to the injury complained of. It appears therefrom that the plaintiff is the owner of a mill upon a creek or stream of water in Mills county, and that in the year 1879 a county ditch was constructed, which had its initial point at said creek. But whether the ditch intersected the stream above or below the mill it is impossible to determine from the petition. In one part of the petition it is averred that “the defendant entered upon plaintiff’s
This suit was commenced more than five years after the ditch was constructed, and one ground of demurrer was that the actibn was barred by the statute of limitations. Accepting the averments of the petition to be true, the act complained of was a willful trespass, without authority of law, and done against the protests of the plaintiff made at the time. For this invasion of his rights he had an immediate cause of action. We do not mean that he had a cause of action against the county. That question we do not determine, because it may admit of doubt whether the county would have been liable. But there then accrued a right of action to the plaintiff for the trespass, against the trespassers, whether they were the men who constructed the ditch, the contractors, or whoever was liable therefor. The present action is founded upon the original trespass. It should have- been brought within five years after the right of action accrued. Code, § 2529.
Affirmed.