96 N.Y.S. 978 | N.Y. App. Div. | 1906
The plaintiffs were jobbers in bicycles, engaged in business, in - Springfield, Mass., under the firm name of P. A. Williams &• Co.
The defendant was engaged in the manufacture of bicycles at Syracuse, H. Y.
The parties entered'into a contract in writing, as follows:.
“ Syracuse, H. Y., Nov. 18th, 1902.
“ H. M. Gbidley, Syracuse, H. Y.:
Dear Madam.—-In addition to our order of Oct. 24th, 1902, you may enter our order for 3,000 (three thousand) of your Olive bicycles model Ho. 53, same to be stripped, or in other words, less tires, pedals, saddles, handle bars, tools and bag, at $8.75 each F. O. B. Syracuse, H. Y. Terms: — Sight draft as fast as goods are ready for shipment, weekly, we to give you shipping directions for same.
“All wheels to be enameled Olive with "red head, with Olive-transfer on all wheels. All to be filled by April 1st, or as soon as possible.
*526 “ All wheels to be vaseli-ned that are'sent to our home office at Springfield, Mass,; you to purchase of us such parts as we may offer you at. the market price to complete the. above Order, same to be paid.by you on receipt of goods, we agreeing as far 'as possible to have, the goods'delivered F. O. B. Syracuse, FT. Y., you to furnish us specifications' of the parts required. Specifications on -above . order to be as follows: Frames to be 22" unless special orders are-received for Other sizes, same to be equipped with Fauber Special Hangers.- -
“Veryrespectfully yours,
' ■ “P. A. WILLIAMS & CO:-
“ Accepted by H. M. Gridley,” .,
' The referee found that under and pursuant to said contract, the defendant, prior to April 1, 1903, furnished and delivered to the plaintiff 469 wheels, and that the santéwere paid for in full, .prior to the commencement of this action, and that there still remained undelivered .on April 1, 1903, 2,531 wheels, and that the defendant • failed to deliver or to offer to deliver said 2,531 wheels to the plaintiffs on- or before April 1, 1903. ■ .
That it'was the understanding, agreement and intention of the .parties, at the time of the execution of said' contract, that- all the wheels contracted for were to be ready "for delivery to the plaintiffs on or before April 1, 1903. . ...
That the market value of the wheels specified in said contract as modified, F. O: B. cars, at Syracuse, FT. Y., on or about April 1,1903, was twelve dollars per wheel.
That t'lie plaintiffs by reason of the failure of the defendant to deliver or to offer to deliver said 2,531 wheels and to have the same ready for delivery as provided in said contract as modified, on or prior to April 1, 1903, have suffered damages, in the amount of $8,225.75,. and interest- thereon from April 1, 1903, and directed judgment'for the plaintiffs therefor.
It appears, that the phrase “ or as soon as possible ” was not in the contract when it was first prepared, but was inserted before execution. The plaintiffs, under objection and exception, were permitted to give parol evidence as to the-purpose'of the parties in introducing into_the-contract the phrase N “ or as'soon as possible,.” The plaintiffs’ witnesses testified that the reason- for the insertion of this .
“ The rule that parol evidence is inadmissible to add to or vary the terms of a written contract, precludes evidence of the negotiation which preceded or conversations which accompanied the making of it in relation' to the subject-matter thereof, unless necessary to explain ambiguous provisions, the meaning of which cannot be ascertained with certainty by an inspection of the written instrument.” (Corse v. Peck, 102 N. Y. 513.)
There is no ambiguity‘in the provision of the contract as it was finally made to read: “All to be filled by April 1st, or as soon as possible.” This phrase has a definite legal meaning. The contract as originally prepared required payment by the plaintiffs, “ as fast as goods are ready for shipment, weekly,” and gave the defendant until April first to fill the order. 'The additional phrase, “ or as soon as possible,” did not make the contract indefinite as to the time of performance. “ As soon as possible ” meant that the defendant was to fill the order within a reasonable time, under- the circumstanced. (Church, Ch. J., Brink v. Hanover Fire Ins. Co., 80 N. Y. 112 ; Attwood v. Emery, 1 Com. B. [N. S.] 110.) Under the contract as it -was completed, there were two periods of time fixed by its terms for filling the order : First, by April first; second, if not then “ as soon as possible.” In construing a written Instrument for the purpose of ascertaining the intention of the parties, resort must be had to the instrument as a whole, and effect must be given to every clause and part thereof when it can be done without violence. (Martin, J., Sattler v. Hallock, 160 N. Y. 298.) If possible, effect must be given to every expression in a contract. (Mason, J., Ward v. Whitney, 8 N. Y. 446.) Thq finding of the referee', that the wheels.contracted for were to be ready for delivery to the plaintiffs on or before April 1, 1903, leaves the phrase “ or as soon as pos
The judgment should be reversed.
All concurred, except Hiscock, J., not voting.
Judgment reversed and new trial ordered, with costs to the appellant to abide event, upon questions of law only, the facts having been, examined and no error found therein.