TRAVIS LANIER WILLIAMS v. SAMUEL FOSTER
Appellate Case No. 28416
IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT MONTGOMERY COUNTY
November 8, 2019
2019-Ohio-4601
Trial Court Case No. 2018-CV-4086; (Civil Appeal from Common Pleas Court)
SAMUEL FOSTER, 45 Perrine Street, Dayton, Ohio 45410 Defendant-Appellee, Pro Se
OPINION
Rendered on the 8th day of November, 2019.
{¶ 1} Travis Lanier Williams, pro se, appeals from a judgment of the Montgomery County Court of Common Pleas, which сoncluded that Williams did not have a valid mechanic‘s lien on Samuel Foster‘s property and entered judgment in favor of Foster. For the following reasons, the trial court‘s judgment will be affirmed.
{¶ 2} On August 31, 2018, Williams brought an action to quiet title to residential property owned by Foster. Williams claimed that, in July 2018, he performed work on the property, including cutting the grass, trimming trees, and picking up trash, the value of which he claimed wаs $500. Williams asserted that he had a mechanic‘s lien on the property.
{¶ 3} After Foster failed to respond to the complaint, Williams sought a default judgment. A magistrate denied the motion, stating that the parties had indicated that they were discussing a settlement.
{¶ 4} A trial before а magistrate was held on February 1, 2019. The record does not contain a transcript of that hearing, but the record reflects that Williams tеstified on his own behalf and Foster did not appear. On March 4, 2019, Williams filed a “notice of
{¶ 5} On March 20, 2019, the magistrate issued a decision, finding in favor of Foster. The magistrate made the following factual findings:
The short of it is the parties had no contract for Plaintiff to perform any wоrk at the property. Defendant never agreed to pay Plaintiff any money to do any work at the property. While Plaintiff claims Dеfendant said he would just give the house to Plaintiff, the only evidence of this is
Plaintiff‘s testimony, which was less than credible. Plaintiff scattered his testimony with diffеrent legal verbiage, that upon questioning, it was clear he did not understand the meaning of the words he chose to employ. There wаs not [sic] written or oral agreement between the parties that Plaintiff was to be paid for any work he completed at the рroperty.
The magistrate concluded that, in the absence of a contract that Williams was owed anything for the work he did at the рroperty, “no mechanic‘s lien can follow.”
{¶ 6} Following the magistrate‘s decision, Williams filed a “motion for judges and magistrate decision,” which the trial court construed as objections to the magistrate‘s decision. The court set a briefing schedule on the objectiоns, following which Williams filed an “affidavit of truth,” an “affidavit of trust,” and a “plaintiff brief.” Williams generally asserted that he was entitled to Foster‘s proрerty due to the alleged mechanic‘s lien and was entitled to judgment against Foster due to Foster‘s non-responsiveness. Foster did not file any responsive memoranda.
{¶ 7} On May 24, 2019, the trial court overruled Williams‘s objections and granted judgment to Foster. The trial court reasоned:
The Court first finds that Plaintiff does not have a valid mechanic‘s lien. Plaintiff did not have an express or implied contract with Defendant regarding the work done around the property or the value of that work. The Court cannot find that a meeting of the minds took placе between Plaintiff and Defendant regarding not only the value of the work performed, but even if the work should have been performed tо begin with. A contract is not formed unless all the essential elements of the contract are agreed to by
the parties. Plaintiff testifiеd that he was the one who determined the value of his work with no input from Defendant. Therefore, there is no valid implied contract. The only evidence of any possible contract is Plaintiff‘s own testimony and the hearsay that it contains. The Court cannot find Plaintiff‘s testimony credible based upon the trial that was held in this matter. It appears to this Court that Plaintiff sought to own the property in question and is attempting to gain ownership through a mechanic‘s lien. Plaintiff stated that he did not even ask Defendant for payment prior to filing the mechaniс‘s lien. Plaintiff also stated that he attempted to file a notice of commencement before the work was completed. As the parties did not enter into a contract, and even if there was [sic] a contract, Defendant was never given an opportunity to perform under said contract, there can be no mechanic‘s lien in this matter.
{¶ 8} Williams appeals from the trial court‘s judgment. Williams‘s appellate brief does not include assignments of error as required by
{¶ 9} At the outset, we emphasize that the record does not contain a written transcript or video recording of the February 1, 2019 hearing. Williams did not request the prеparation of a transcript as part of his appeal, nor did he request the preparation of a transcript in the trial court.
{¶ 10} Under
{¶ 11} Accepting the trial court‘s findings, we find no error in the trial court‘s conclusion that Foster was entitled to judgment on Williams‘s claim.
Every person who performs work or labor upon or furnishes material in furtherance of any improvement undertaken by virtue of a contract, express or implied, with the owner * * * has a lien to secure the payment therefor upon the improvement and all interests that the owner, part owner, or lessee may have or subsequently acquire in the land or leasehold to which the improvement was made or removed.
(Emphasis added.)
{¶ 12} The trial court expressly found that there was no implied or express contract between the parties. In the absence of a contract between the property owner and the contractor -- in this сase, Foster and Williams -- no mechanic‘s lien is permitted. In addition, the trial court found, based on Williams‘s testimony, that even if a contract
{¶ 13} The trial court‘s judgment will be affirmed.
DONOVAN, J. and HALL, J., concur.
Copies sent to:
Travis Lanier Williams
Samuel Foster
Hon. Dennis J. Adkins
