258 F. 591 | 6th Cir. | 1919
Plaintiff in error, also plaintiff below, brought this action to recover damages for the wrongful death of one G. A. Williams. A trial to a jury was had, and after all the testimony for both sides had been introduced the District ■ Court, on motion, directed a verdict for the defendant. This action of the court below is the only error assigned.
The decedent was an employé on a lake steamer named Junior. This steamer on the night of May 9, 1915, between 11 and 12 o’clock, as it was entering Cleveland harbor, struck against the inside corner of the east end of the breakwater. As a result the boat sank and the decedent was drowned. This collision of the steamer with the breakwater, it is contended, was due to the absence of any light on or near its east end, and on this hearing counsel for both parties make the answer to the question involved to turn on whether or not the duty rested on the defendant to maintain such a light.
. The defendant on July 2, 1914, had made a contract with the proper engineering officer of the United States government to complete the construction of 6,601 feet of the east breakwater extension of the Cleveland harbor, including the east end against which this steamer collided. This work was divided into seven sections, numbered from west to east and from 1 to 7, inclusive; the first six sections being each 1,000 feet in length, and the seventh 601 feet in.length. These sections were to be constructed in the order given, from west to east, and work was prohibited on more than two sections in advance of the completed superstructure, except by special permission of the engineer in charge. This engineer, however, directed that the work first to be done should be the completion of the east end in the inverse order stated. By December 1, 1914, not less than 1,800 feet at that end was completely finished, and in such a manner that no further work or labor was required thereon by the defendant under its contract. The contract also provided that acceptance would be made by the engineer on the written request of the contractor, when a continuous length of 100 feet had been completed, as was required, and to his entire satisfaction. A request was made of the engineer in charge
The contract also required defendant to maintain at its own expense lights and signals required by the engineer or by the regulations of the United States lighthouse Board. The regulations of the United States Lighthouse Board were not introduced in evidence, and the record does not indicate clearly what specific requirements, if any, the engineer in charge made as to lights during the period of construction. A gas buoy light was, however, maintained by the defendant at the east end of the breakwater from the time it began work until about December 1, 1914, when all construction work on the breakwater was, owing to weather conditions, suspended for the season. The defendant then removed its gas buoy light and stored it on the United States government pier in the Cleveland harbor. Maj. P. S. Bond, the government engineer in charge of this work, established, upon the removal of the.gas buoy, a light on the east end of the breakwater. An upright pole with a cross-arm was erected, with devices to raise and lower the light. Thereafter, and until the lake was frozen over, and again as soon as the ice disappeared in the spring, the engineer, and subordinate employes under his direction and control, maintained and took care of this light.
The evidence tends-to show that on the afternoon of May, 9, 1915, at about 3 o’clock, these employes filled the lamp, lighted it, and placed it in position; but, in our opinion, there was sufficient evidence to go to a jury tending to show that during the night, and preceding the time of the accident, it was not lighted or burning.
An acceptance by him of a part of the work, when completed according to the requirements of the contract and to his satisfaction, is also expressly authorized and is not outside of his authority. Each completed length of 100 feet may be accepted. The severance of such
The duty imposed by this contract to maintain a warning light is no greater than the common-law duty. It becomes unnecessary, therefore, to consider whether or not provisions in a construction contract for the safety of third persons are available to them as supporting an action based on negligence. For discussion of this proposition see the following: Consolidated Coal Co. v. Knickerbocker Co. (D. C.) 200 Fed. 840; Harrison v. Hughes (D. C.) 110 Fed. 545, affirmed 125 Fed. 860; Styles v. F. R. Long Co., 67 N. J. Law, 413, 51 Atl. 710, on second appeal 70 N. J. Law, 301, 57 Atl. 448; Williams v. Stillwell, 88 Ala. 333, 6 South. 914; Earl v. Lubbock [1905] 1 K. B. 253. The final solution of the question involved turns, in our opinion, on whether or not the contractor had fully performed his contract as to the east 1,800 feet, and whether or not it had been turned over to and accepted by the owner and possession and control thereof taken by the owner. All this had been done, and, in our opinion, with proper authority and without violating any provision to the contrary.
When defendant resumed construction work on the other sections
The judgment of the lower court is affirmed.
17. Payments.' Payments will be made monthly on estimates of such stone as has been placed in the work in accordance with the specifications and not included in any prior estimate, except that ten (10) per cent, of the amount of ■each estimate will be retained until the contract work is fifty (50) per cent, completed, after which the amount of reserve will remain unchanged until the full completion of the contract.
22. Changes. No changes in the character of the material, or workmanship herein described will be permitted, unless specially authorized by the engineer. • Should it be found desirable to materially modify or change the plans or designs of the work, such modification or changes must be embodied in a supplementary contract with the consent of bondsmen, and must receive the approval of the Secretary of War, before becoming effective.
29. Order of Worlc. The work will be divided into sections 1,000 feet in length. These sections will be constructed in order from west to east, as far as the funds provided will fully complete. Work will not be permitted in more than two sections in advance of the completed superstructure, except by special permission of the engineer. ,
30. Acceptance and Responsibility. The contractor will be held responsible for and required to maintain and repair the work until it has been accepted by the engineer in writing. Such acceptance will be made by the engineer on the written request of the contractor, as follows: Each length of 100 feet
The contractor will be required to maintain at his own expense, the lights and signals required by the regulations of the United States Lighthouse Board, or by the engineer.
35. Minor Modifications. The right is reserved to make such minor changes in the execution of the work to be done under these specifications as, in the judgment of the contracting officer, may be necessary or expedient to carry out the intent of the contract: Provided, that the unit cost to the contractor of doing the work shall not be increased thereby, and no increase in unit price over the contract rate shall be paid to the contractor on account of such changes. No change which will materially affect the cost of doing the work will he made and no greater or lesser unit price than the contract rate will be paid, except upon formal written agreement between the parties, approved by the Chief of Engineers and the Secretary of War, as provided in the form of contract to be entered into.
7. If at any time during the prosecution of the work, it be found advantageous or necessary to make any change or modification in the project, and this change or modification shall involve such change in the specifications as to character and quantity, whether of labor or material, as would either increase or diminish the cost of the work, then such change or modification must be agreed upon in writing by the contracting parties, the agreement setting forth fully the reasons for such change, and giving clearly the quantities and prices of both material and labor thus substituted for those named in the original contract, and before taking effect must be approved by the Secretary of War: Provided, that no payments shall be made unless such supplemental or modified agreement was signed and approved before the obligation arising from such modification was incurred.
30. Until final inspection and acceptance of, and payment for, all of the material and work herein provided for, no prior inspection, payment, or act is to be construed as a waiver of the right of the contracting officer to reject any defective work or material or to require the fulfillment of any of the terms of the contract.