68 N.Y.S. 348 | N.Y. Sup. Ct. | 1900
This is an action brought by plaintiff to recover the value of a quantity of sand supplied by her assignor, Frederick Williams, to the defendant Daiker, and used by bim in the construction of three houses at St. Bichólas avenue and One
Prior to the commencement of this action plaintiff filed a lien against the property in question, which lien was discharged by giving an undertaking as provided by law, and the sureties are made parties to the action.
The defendants claim that whatever material was furnished by plaintiff’s assignor was in pursuance of a written contract between plaintiff’s assignor and defendant Daiker. This contract is in evidence. By it, plaintiff’s assignor agreed to furnish sand for all stone work upon the buildings to be erected for one and three-fourths cents for each cubic foot of stone work, $500' for all brick work on comer building, $300 for all plaster work on comer building, $480 for all brick work on adjoining buildings, and $300 for all plastering on adjoining buildings. It appears from the evidence that when the buildings were partially completed, "Williams discontinued the delivery of sand and refused to supply more on the ground, as he claims, that he was misled as to the quantity required through Duiker’s misstatement as to the number ■of bricks to be used in the construction of the buildings. Defendants claim a breach of contract by Williams. Plaintiff meets this -defense and attempts to explain her failure to sue on th¡e contract, by trying to prove a fraudulent misstatement by Daiker of the quantity of stone work and brick work necessary to complete the buildings in question. Williams claims to- have relied on such alleged misstatement in entering into the contract, and contends that thereby the contract was vitiated.
The evidence does not satisfy me that the defendant Daiker was guilty of such misstatement as would amount to fraud and warrant the court in holding the contract was annulled thereby. The evidence of the alleged fraud is furnished by the plaintiff’s assignor, and is as follows: That before the contract was signed he called upon Daiker to get information in order to make an estimate, and that Daiker showed him the plans. He then told Daiker he would furnish sand for stone work at one and three-fourths cents per cubic foot of stone work, but that, he would have to know the
The contract being valid, plaintiff cannot prevail in this action, as the failure by her assignor to continue the delivery of sand in accordance with the terms thereof, constituted the breach.
The plaintiff must fail in this action for a further reason. In the lien filed, claim is made for $4,682.79, composed of the following items:
“ Sand for 101,524 cubic feet of stone work at one and three-fourths cents — $1,776.67; sand for 589 cubic yards of concrete; 15,903 cubic feet at four cents — $636.12; sand for plastering, $600; sand for 3,200,000 bricks at eighty cents per thousand, $2,560; sand for 9,000 cubic feet of concrete for cellar floor at four cents — $360,” making a total of $5,932.79, from which is deducted a cash payment on account of $1,250, leaving a “ balance due, October 9, 1896,” of $4,682.79. The lien filed contains the statement that all work for which the claim is made has been actually performed, and all materials have been furnished, and the amount now due to claimant therefor is as above stated with interest from October 9, 1896. This statement of the account and the accompanying affidavit are grossly exaggerated, extremely inaccurate and clearly false. This is admitted by the plaintiff, both in the complaint and in the proceedings on the trial. The explanation of the false statement which plaintiff makes is that it was a miscalculation due to the papers having been drawn in a hurry. This explanation is not satisfactory. It fails to explain why plaintiff should have claimed more than twice the amount of his present demand. He must have known that he did not supply sand for 3,200,000 bricks for he discontinued the supply of sand when the buildings were half completed, and the total number of bricks for the completed buildings did not exceed 3,200,000; the amount stated in the lien.
Under the authorities the lien as filed cannot be sustained in this action. Goodrich v. Gillies, 66 Hun, 422; Aeschlimann v. Presbyterian Hospital, 29 App. Div. 630; S. C., 53 N. Y. Supp. 998; Foster v. Schneider, 50 Hun, 155.
It follows from the views here expressed that defendant must hjave judgment.
Judgment for defendant. '