73 P. 238 | Cal. | 1903
The above-entitled action and certain four others were brought in the superior court of the city and county of San Francisco for the foreclosure of mechanics' and materialmen's liens on the land described in the complaint. The causes were consolidated and tried together. The pleadings in all of the cases are substantially alike, mutatis mutandis, and only the pleadings in the case above entitled are given in full. The late Adolph Sutro was the owner of the land, and on April 9, 1896, leased the premises to defendant John M. Weir, for the purpose of erecting thereon a scenic railway, and Weir agreed to complete it within fifty days or pay a forfeit for each working-day thereafter that the work remained uncompleted. The Magic Transit Company was made a defendant, but its interest in the premises does not appear. Defendant Sutro answered, and as a separate defense alleged that "within three days after he had obtained knowledge of the construction of the certain structure mentioned in plaintiff's bill of complaint, on certain lands belonging to him, the said Adolph Sutro did duly and regularly give notice that he would not be responsible for the same by posting notice in writing to that effect in a conspicuous place on said lands." The court found that Sutro "had actual knowledge of the intended construction of said structure from the said ninth day of April, 1896; that the actual construction of said structure was commenced on the thirteenth day of April, 1896; that on the fourteenth day of April, 1896, and not prior thereto, the said defendant, Adolph Sutro, caused to be placed in a conspicuous place on the said structure a notice to the effect *498 that he would not be responsible," etc., as alleged in the answer.
The court in its conclusions of law found that plaintiffs are entitled to judgment against the Magic Transit Company in some of the cases, and the Magic Transit Company and Weir in others, but that the judgments do not constitute a lien on the land, and that, as to defendants, the executors of Sutro, deceased, plaintiffs take nothing by the actions. Plaintiffs appeal from the judgment.
The sole question relates to the construction to be given to section 1192 of the Code of Civil Procedure, which reads as follows: "Every building or other improvement mentioned in section one thousand one hundred and eighty-three of this code, constructed upon any lands with the knowledge of the owner, . . . shall be held to have been constructed at the instance of such owner, . . . and the interest owned or claimed shall be subject to any lien filed in accordance with the provisions of this chapter, unless such owner . . . shall, within three days after he shall have obtained knowledge of the construction, . . . or the intended construction, . . . give notice that he will not be responsible for the same, by posting a notice in writing to the effect, in some conspicuous place upon said land. . . ." Appellants' position is, that the land shall be subject to the liens unless the owner shall post a notice within three days after he shall have obtained knowledge of either one or the other of two things — (1) the construction, or (2) the intended construction, of the building, etc. Respondents' position is, that the legislature intended to give the owner an option of posting notices either within three days after he obtained knowledge of the construction or within three days after he obtained knowledge of the intended construction of the building. In the present case the notice was given five days after the owner had knowledge, through the lease, of the intended construction of the structure, and within one day after the actual construction was commenced.
The general purpose of the Mechanics' Lien Law is to give to contractors, laborers, and materialmen a lien on the land improved as security for their labor and material. But the law also gives to the owner certain rights and privileges by which he may protect himself against the operation of *499 such a lien. The law does not, and in fairness should not, make the land subject to the lien in any and every case of a building or other structure erected upon it. The statute in question is not absolutely free from uncertainty or ambiguity, although both parties claim that it is, each claiming that it plainly supports their contention. The statute has existed since 1868 (Stats. 1867-1868, p. 589), but never before, so far as we can find, has the present question arisen under it. Whoever drafted the section may have concluded when he had framed the expression "knowledge of the construction," etc., that it might be understood to mean the completion of the work, and so added the expression "or the intended construction," etc., for the purpose of greater clearness, thinking that the actual commencement of the improvement would thus be more clearly indicated. The phrase "intended construction" is susceptible of a different meaning than if it read "or the intention to construct," etc. However this may be, we think the statute should be given an interpretation that would best answer its purposes, and this can be ascertained by keeping in mind the various conditions to which the law must be applied. Contracts for the sale as well as leasing of land conditional on its improvement by the purchaser or lessee at some future time are quite common. This contemplated improvement may be for a short period (as in the case here), or it may be for one or more years, the work not to be begun for many months, or even years, in the indefinite future, and the contract or its terms may be unknown to the laborer or materialman who in this distant future is to furnish labor or material for the improvement. The owner would be charged with knowledge of the intended work as soon as he signs the contract, and under the construction contended for by the appellants he must within three days post his notice or lose his protection against the lien. On the other hand, if he post such notice, it is not at all likely that it would remain posted and be conspicuous when in the future the laborers and materialmen would be called upon to furnish labor and material, and yet the owner would be protected. If, however, the owner posted his notice within three days after the actual construction began, the persons interested could not fail to observe it, and would govern themselves accordingly. It would, it seems to us, be a much better protection *500 to the laborers and materialmen, and equally subserve the protection of the owner, to hold the notice posted by the owner "within three days after he shall have obtained knowledge of the construction" (i.e. the actual beginning of the work) to be in time; and that such is the notice referred to in the statute. Whether a notice posted within three days after knowledge of the intended construction would in all cases be sufficient to protect the owner is a question not before us. We think, however, a failure to give such a notice by the owner who does in fact give the notice within three days after he shall have obtained knowledge of the actual commencement of the work does not deprive him of the protection given him by the statute.
In Evans v. Judson,
In Fuquay v. Stickney,
To hold that the statute compels the owner to give the notice within three days after he has knowledge of the intended construction would in most cases give no effect to the provision as to notice where he had knowledge of the actual construction. But we cannot say that the legislature had no object in making this provision. It would be more reasonable to suppose that it was intended to provide that the owner might give the notice within three days after the actual construction was commenced. *501
We advise that the judgment be affirmed, with directions to enter judgment in accordance with this opinion in all of the consolidated cases.
Haynes, C., and Gray, C., concurred.
For the reasons given in the foregoing opinion the judgment appealed from is affirmed, with directions to enter judgment in accordance with the above opinion in all the consolidated cases. Van Dyke, J., Shaw, J., Angellotti, J.