50 Ct. Cl. 179 | Ct. Cl. | 1915
reviewing the facts found to be established, delivered the opinion of the court:
This case is again before the court on motion for new trial by both claimants and defendants.
The claimant company, on October 1, 1898, entered into a contract with the defendant to construct the battleship Maine. The claimant was to furnish all the necessary material entering into the vessel except the armor and armament and to complete the same within 32 months from the date of the contract, viz, June 1, 1901. The defendants agreed to furnish the armor specified in clause 3 of the contract “ within the times and in the order required to carry on the work properly.” The claimant subsequent to the execution
The case is not susceptible of differentiation in any of its aspects from a similar case of Wm. Cramp & Sons v. United States, 6216 U. S., 494, except as to proof and measurement of damages claimed. In the former^ase, which involved the construction of the U. S. S. Alabama, the Supreme Court passed directly upon all the contentions put in defense here respecting the liability of the defendants, the rights of the claimant to avail itself of the privileges set forth in clause 3 of the contract, and the legal effects of the inserted proviso to the final release. The above case, taken in connection with an earlier suit between the same parties involving the construction of the U. S. S. Indiana, 206 U. S., 118, precludes a repeated discussion of these issues, despite the vigor and ability with which the same are urged.
The vital distinction between this and former cases of similar import revolves exclusively about the quantum of damages. There is absolutely no room for dispute as to important facts. Dates speak for themselves. The Secretary of the Navy conceded defendants’ default, extended the contract period, and remitted all claims for liquidated damages. It was physically and legally impossible for the defendants to comply with their obligations under the contract; they made no pretense of doing so. It would be idle and meaning
The claimant’s progress toward complying mwith the time limit fixed by the defendants in the contract was dependable entirely upon defendants’ obligation to perform a condition precedent. The defendants defaulted and imposed upon the company an extended delay of 18 months and 27 days. The courts have frequently adjudicated cases involving similar conditions; the liability has been determined. Alabama case, supra; Weeks v. Little, 89 N. Y., 566; District of Columbia v. Camden Iron Works, 181 U. S., 453; United States v. Behan, 110 U. S., 338.
In the cases involving the Alabama and Indiana claimant company presented a specific bill of damages, involving a direct pecuniary loss. In this case it is impossible to do likewise. A short time after commencing the construction of the vessel it became notoriously apparent that the defendants would not be in a position to furnish the armor in the order and at the times needed to complete the work. The Secretary of the Navy was powerless so to do because of legislative inhibitions as to price and the unwillingness of armor makers to accede to the same. The claimant under these conditions retarded work on the vessel, employing the bulk of its force on other work in its yard, important and pressing. Up to the time the contract for armor was let by the Secretary, on November 28, 1900,. work on the Maine had been abnormally slow; subsequent to that time, however, work was greatly accelerated and rapid progress made. The shipbuilders were ready for the armor when furnished. The
In this connection it is proper to observe that in ascertaining the intrinsic value- of the slip, wharfage value must be included in making up the total value of the entire plant. Wharfage is an indispensable adjunct to the slip; without wharves the slips would be useless. The two are inseparable, and to ascertain the proportionate value of one the proportion must include the value of the other. Hence, as shown in Finding XI, wharfage is included. This identical method has been heretofore employed by the United States in similar cases and payments made thereunder.
Defendants assail this contention, attacking it because of uncertainty and remoteness, and charging the claimant with dereliction in not prosecuting its work to all possible limits, irrespective of defendants’ default» The findings establish indisputably that the claimant company could have prosecuted work on the vessel to the point of launching, for up to the normal period fixed for said event the defendants’ defaults caused no delay, and the court has computed the delay period from this date. To have launched her, however, would have concededly augmented their final loss, for both parties are in accord in fixing the use value of wharfage as greater than the use value of the building slip. Claimant was obligated under the law to mitigate, so far as possible,
Conceding for the moment the logic of defendants’ contention that the claimant company should have proceeded under the contract to all possible extent despite defendants’ defaults, which under the findings means the completion of the vessel to the point of launching, i. e., April 1, 1900, under these conditions claimant company might have availed itself of two contingencies: It could have launched the vessel and thereafter maintained her at the wharf, or it could have continued to maintain her on the building slip; nothing else could have been done. To have put her in the water would have materially increased the expense incident to her upkeep and necessarily increased the expense to the Government. On this point the record is unanimous. A vessel afloat at the wharf requires the constant attention of numerous employees daily and nightly engaged in vigilant watch over its complicated and costly machinery; it involves the maintenance of steam to keep the machinery in motion, the employment of a tug when necessary to turn her, and the induction and almost constant working of pumping machinery to keep her dry; in fact the innumerable items of expense indispensable in the maintenance of a large battleship, on which at least half, and frequently more than half, of the total consideration for its construction has been incurred, so materially increase the expense of maintenance over and above what it would cost to maintain her on the slip under similar conditions that it can not be and is not controverted.
A most convincing and logical argument predicated upon a comparison of damages allowed on the first trial of this case with ¿he amount allowed in the case of the Alabama exhibits what upon first impression might seem a strong contention hostile to the principle of mitigation of damages. The argument may be sound, but the computation as made by the defendants must be similar. The defendants, as a basis for their figures, take the total judgment awarded the claimant herein and divide the same by the total length of delay, reaching a result which gives a monthly rental value to the slip much in excess of the rental allowed for wharfage in the Alabama case. In the case of the Alabama, however, wharfage value was segregated and allowed as a separate item, quite distinct from the various other items of damage proven in the case. To make the comparison accurate the same method as to each vessel should be adopted, and the total judgment in each case divided by the length of delay. Because in one case the proof enabled the court to fix specifically all the items of damage affords no logical reason for taking the specific item and comparing it with the sum total in another case. In other words, the judgment awarded the claimant in this case covers as a whole all the specific items allowed in the case of the Alabama, and to make the comparison effective the same mode of computation must be adopted. The demonstration of the correct method is found in Finding XI. The total rental value of the slip for the whole period of delay is fixed at $52,885.10, which sum, divided by the whole period of delay, gives a monthly rental for the slip of $2,798.15, exclusive of insurance. With insurance added, the amount is increased to $3,255.54. Pursuing the same method in the case of the Alabama, the rental value of wharfage would amount monthly to the sum of $3,860. These computations, with the differences deducted, clearly
Defendants again insist that no reason prevails against the ascertainment of damages in this case different from any other; that proof could and should be adduced fixing in a positive way the rental value of the slip. It is suggested that witnesses can be called competent in every way to supply this testimony. The court has given the contention most serious consideration. The circumstances of the case are such that the adoption of the defendants’ contention would materially confuse rather than simplify the record. No possible means are at hand other than the one approved to ascertain a reasonable rental value of the slip except resort to expert testimony. A reconciliation of numerous conflicting statements based upon varied and confusing hypotheses, developed according to the viewpoint of the particular witness, is an arduous and difficult task even when unavoidable. It affords in the end no better proof that an estimate and reaches no nearer to certainty, if as close, than the method adopted herein. In any event it would be far from conclusive if it failed to adopt the identical basis adopted by the court, a basis which includes within its conception the material value of every part and adjunct of the claimant’s whole property.
Too much importance is placed upon the appearance of the Johnson board in the findings by the defendants. Claimant company furnished in the record the indisputable proof of each item upon which we founded our computation. The Johnson board, it is true, first adopted the method insisted upon by claimant company, but this fact alone did not move' the court in the premises. Eliminating the report entirely would not have affected the case. The judgment is rested upon an analysis of the method and the record proof in the case, with no thought of alone predicating the same upon the fact that a naval board had done likewise. The board’s findings were persuasive but not conclusive.
Taken as a. whole, we think the proof sufficiently certain to warrant a judgment; it is in any view the best proof of which the case is susceptible. It comes within the rule so admirably stated by the late Judge Davis in Meyerle v. United States, 33 C. Cls., 1. The default of the defendants imposed an additional burden on the claimant; it was powerless in the premises to do more than mitigate the damages. The vessel must be cared for either on the slip or at the wharf. Each facility possessed intrinsic worth of proportionate value to all the others indispensable in the conduct of its business enterprise. To go back over a period of years and definitely ascertain the original cost of the slip and sum up the multitudinous improvements and expenditures thereon, and then proportion to it the items of the general upkeep of the entire shipyard, would furnish no more than a very vague and indefinite estimate, even if we exclude the possibility of enhancement in value of both real estate and general equipment. Too many “intervening incidents” inter
In arriving at this value, however, we can not go beyond the lvalue of the claimant company’s plant as shown in detail upon its books during the period of time covered by the period of delay, i. e., from April 1, 1900, to July 27, 1901, during which time the vessel occupied the slip. The subsequent valuation made by experts in anticipation of financial relief, while doubtless accurate in every particular, can not be given retroactive effect so as to disturb the former valuation with which the company was entirely content, and upon which it must have estimated in anticipating profits for this particular contract. The valuation given the slip by the company during the course of construction of the vessel is the only safe and direct guide in this instance. The subsequent one made in 1902 and 1903, even if entered upon the books of the company prior to the completion of the vessel, had no existence during the period of delay complained of, and could not have formed any part in the company’s past undertakings respecting the cost of building a battleship. The proximate effect of the delay herein is limited to the value of the property used at the time it was used; this is clearly proven and upon it we predicate a judgment.
The second item of the claim respecting proof of loss is unusual. Claimant brings forward proof of the actual cost
Claimant company had refinanced its enterprise, employed new and labor-saving devices, and had in addition the fruitful benefit of past experiences to apply in its management and execution of the South Carolina contract. Something exceedingly potent, aside from the delay of the Government in the Maine, must have transpired to enable the claimant to complete with profit a work of greater magnitude at a less unit cost for labor in the face of an admitted assertion that the same had advanced 10 per centum during the interim. It may be conceded that concentrated and steady work upon a given undertaking may be prosecuted with less expense than intermittent and interrupted service, but from November 28, 1900, until the Maine was complete, as stated in the findings, the work upon her, i. e., labor, was wholly if not much in excess of normal. There is nothing in the record indicating that the delay occasioned by failure to deliver her armor in any way enhanced her labor cost. The
• The loss to be recoverable must be the direct and proximate effect of the breach, capable of being traced to the injury with reasonable certainty. A substantial hiatus affording sufficient time wherein innumerable incidents disconnected with the transaction may occur, affords a fruitful field for conjecture and precludes such a continuity of proof of damages as the law requires.
The remaining item of loss set forth in Finding XIII is proven specifically and directly, and will be included in the judgment.
The claimant’s motion to amend findings is overruled; the defendant’s motion for a new trial and to amend findings is allowed, and judgment will now be entered for the claimant company in the sum of $61,529;69.
It is so ordered.