William C. Godley sued the United States Postal Service in the United States Court of Federal Claims for breach of contract. The Court of Federal Claims granted Mr. Godley’s motion for summary judgment.
Godley v. United States,
Mr. Godley owned an interest in a tract of land in Mecklenburg County, North Carolina. When the Postal Service advertised its need for a postal facility, Mr. Godley offered to build one on his land. Mr. Godley made this offer to Charles D. Paramore, the Postal Service agent responsible for this project. Mr. Godley offered to build a postal facility and to provide a ten-year lease with an option to buy after the first year: The Postal Service accepted Mr. Godley’s offer in February 1989.
On September 5, 1989, Mr. Paramore was indicted for conspiracy and bribery. The charges stemmed from his involvement with Postal Service projects. On November 22, 1989, Mr. Paramore pled guilty to several counts of conspiracy and bribery.
United States v. Paramore,
In October 1989, the facility was complete and the Postal Service took possession. Mr. Godley and the Postal Service entered a final lease agreement on December 5, 1989. On March 27, 1990, however, the Postal Service informed Mr. Godley that the contract was not valid because it was tainted by Mr. Para-more’s illegal conduct. The Postal Service offered instead to renegotiate. The Postal Service stopped paying the lease amount in the contract.
On May 17, 1990, Mr. Godley filed claims against the Postal Service under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1988). Mr. Godley claimed that the Postal Service breached the contract. As damages, Mr. Godley sought the payments required by the original lease. In addition, Mr. Godley sought compensation for changes in the contract. On June 21,1990, the Postal Service began paying a reduced lease rate. In November 1990, the contracting officer for the Postal Service denied Mr. Godley’s claims.
In the Court of Federal Claims, Mr. God-ley claimed that, the contract was valid and sought to enforce the lease. The Postal Service answered that the contract was void ab initio due to the alleged taint from Mr. Paramore’s illegal actions and alleged fraud on the part of Mr. Godley. The Postal Service also counterclaimed based on alleged fraudulent claims by Mr. Godley. The parties filed cross motions for summary judgment.
On August 14, 1992, the Court of Federal Claims granted summary judgment in favor of Mr. Godley. The trial court stated:
Where the prime contractor is innocent of wrong-doing, the government must exercise the right to avoid the contract within a reasonable time of learning that it is tainted by wrongdoing. The failure to do so results in the loss of the right of avoidance.
Godley,
OPINION
Summary Judgment
In the absence of genuine issues of material fact, a trial court may award summary judgment to a party according to the law. Fed.R.Civ.P. 56(c). In reaching summary judgment, the trial court must construe facts and resolve inferences in the light most favorable to the non-movant.
Adickes v. S.H. Kress & Co.,
Voidable or Void Ab Initio-
In general, a Government contract tainted by fraud or wrong-doing is void
ab initio. J.E.T.S., Inc. v. United States,
It is this inherent difficulty in detecting corruption which requires that contracts made in violation of [a conflict of interest statute] be held unenforceable, even though the party seeking enforcement ostensibly appears entirely innocent.
Id.
In Mississippi Valley, the contract sought construction and operation of a steam power plant near Memphis, Tennessee, to take pressure off the Tennessee Valley Authority. Mr. Adophe H. Wenzell acted as a Government agent to negotiate the contract. Mr. Wenzell was also Vice President and Director of First Boston Corporation, the financial institution eventually, chosen to finance the project. Although First Boston declined to accept a fee for the project, the Court held that Mr. Wenzell’s conflict of interest rendered the contract unenforceable:
[T]he negotiations in which [Wenzell] participated were the very foundation upon which the final contract was based.... If the [Mississippi Valley Generating Company] and the Government had not agreed on the cost of construction and on the cost of money, no contract would have been made.
Id.
at 553,
As the Court explicitly stated, in
Mississippi Valley
the taint' of illegality clearly infected the contract itself. Moreover, the contractor was not innocent of the fraud. The Court noted that the Mississippi Valley Generating Company “recognized Wenzell’s conflict of interest almost from the outset of the negotiations.”
Id.
at 565, n. 19,
Thus,
Mississippi Valley
does not present a situation where a completely innocent contractor entered a contract with the Government which, despite illegal conduct by a Government' agent associated with the contract, was nonetheless wholly untainted by fraud.
1
Rather, in
Mississippi Valley,
the contractor, with knowledge, implicitly condoned the illegal conflict of interest.
2
Moreover the ille
*1476
gality permeated the contract. Without Mr. Wenzell’s illegal participation, the Court noted, “no contract would have been made.”
Mississippi Valley,
Thus, as stated above, the general rule is that a Government contract tainted by fraud or wrongdoing is void
ah initio. J.E.T.S.,
On this record, this court cannot determine whether Mr. Paramore’s illegal conduct tainted the contract. Specifically, this court cannot. on this record determine whether Mr. Paramore’s illegal conduct caused any unfavorable contract terms. Moreover, the existence of genuine and material factual disputes and inferences in favor of the Postal Service precludes summary judgment in favor of Mr. Godley.
The trial court erred in determining on summary judgment that Mr. Godley’s contract was voidable, rather than void ab initio. The trial court incorrectly concluded that the Government’s acceptance of the building and entry of the contract with knowledge of Mr. Paramore’s conduct made the contract voidable. These factors, however, are relevant to whether the Government exercised its option to void a voidable contract if, in fact, the contract was voidable. These factors do not show that Mr. Godley’s contract was voidable, rather than void ab initio. On remand, the trial court will have the opportunity to make findings on whether Mr. Godley’s contract was void ab initio.
In the event it determines that Mr. God-ley’s contract was voidable, the trial court must also determine whether the Government cancelled the contract within a reasonable time after discovery of the illegality.
ACME Process Equip. Co. v. United States,
The Court of Federal Claims also determined that Mr. Godley’s conduct did not violate numerous procurement regulations and that Mr. Godley’s offer was not fraudulent.
Godley,
CONCLUSION
For the reasons stated above, this court remands for a determination whether Mr. Godleyls contract was void ab initio or voidable. Consistent with this opinion, this court vacates the decision of the Court of Federal Claims and remands for determination of material issues of disputed fact.
Costs
Each party to bear its own costs.
VACATE and REMAND.
Notes
. In
K & R Engineering Co. v. United States,
Even in K & R Engineering, however, the Court of Claims recognized that the void ab initio rule only applies to contracts actually tainted by illegality:
What the statute condemns is the inevitable taint of the contract itself when it is the product of a conflict of interest.
. In
John Reiner & Co. v. United States,
[T]he court should ordinarily impose the binding stamp of nullity only when the illegality is plain.
Id.
Again in
Trilon Educational Corp. v. United States,
