146 Pa. 427 | Pennsylvania Court of Common Pleas, Alleghany County | 1892
The only question here, is whether a material-man who furnished lumber for the defendant’s building is prevented from filing a lien therefor by the fact that the contractor, subsequent to his contract but before the plaintiff furnished the lumber, had released his right to file a lien. In Schroeder v. Galland, 134 Pa. 277, the contractor was prevented by his contract with
The judgment is affirmed.