Thе sole issue in this appeal is the sufficiency of damages awarded to the plaintiff by the Superior Court for the defendant’s repudiation of a contract for regrading and the sale of fill and other eаrth materials. The facts of this case as found by the trial court are as follows: On July 29, 1968, the plaintiff, an excavating and road building contractor, and the defendant, a real estate developer, enterеd into a written agreement whereby the plaintiff was given permission to enter a tract of land, which the defendant purportedly owned, located in Wallingford, Connecticut, and to remove 132,000 cubic yards of surрlus earth mate *624 rial or fill. The plaintiff agreed to pay fifteen cents a cubic yard to the defendant for the material, and he also agreed to regrade 34,000 cubic yards of earth for which the defendant agreed to pay forty-five cents per cubic yard for the regrading. In addition the plaintiff agreed to pay a $2000 commission of the agent who acted as intermediary for the parties.
On August 6, 1968, the plaintiff began work at the project site with a power shovel, a bulldozer, four trucks, and a crew of six workmen. Soon after work was begun, the plaintiff and his crew were stopped by the town building inspector because no permit for the work had been issued. The plaintiff immediately contacted the defendant, who assured him that the inspector was mistaken and that a permit had been obtained. The plaintiff recommencеd work one week later and was again stopped by the inspector. The parties corresponded during the month of August, as the defendant was considering changing the plan and accelerating the wоrk schedule and had asked the plaintiff for a new estimate based upon these changes. The plaintiff submitted the estimate, but specified that the new figures were not intended as a modification of the terms of the agreement of July 29. While the plaintiff was waiting to be advised when he could begin work at the site, another contractor began work there. The plaintiff complained to the defendant. In a letter reсeived by the plaintiff on September 14, the defendant repudiated the agreement. The plaintiff immediately removed his equipment from the site. Subsequently, the plaintiff discovered that the defendant did not own or hаve a leasehold interest in the site, nor did he have permission to authorize work on the site.
*625 The plaintiff brought this action to recover damages resulting from the defendant’s breach of the written agreement. The defendant filed four special defenses claiming that the agreement was not a valid and binding contract, and filed a counterclaim for damages against the plaintiff in the event that the agreement was found to be a valid and binding contract. The trial court held that the agreement was a valid and enforceable contract and that it had been wrongfully repudiated by the defendant. Judgment was rendered for the plaintiff on the complaint and the counterclaim, and the court awarded damages to him totaling $22,513, plus interest. That total included sums for loss of the profits the plaintiff would have earned on the grading jоb, for the cost of moving the power shovel and bulldozer to the site, for loss of the use of the shovel and bulldozer during the thirty-five days they remained at the site while the plaintiff waited for the defendant to obtain a wоrk permit, and for loss of the use of the four trucks during the two days in August of 1968 when the plaintiff actually attempted to work at the site. The plaintiff has appealed to this court, claiming that the damages awarded by thе trial court were insufficient in amount.
The plaintiff has made numerous assignments of error. In many of them, the plaintiff claims that the court erred in failing to include in its finding certain paragraphs of the draft finding which contain mаterial facts which are admitted or undisputed. To secure additions by this court on that ground, however, “it is necessary for an appellant to point to some part of the appendix, the pleadings, оr an exhibit properly before us, which discloses that the appellee admitted that the fact in
*626
question was true or that its truth was conceded to be undisputed.
Martin
v.
Kavanewsky,
We first consider whether the trial court erred in awarding damages for loss of the use of the plaintiff’s four trucks for a time of only two days, although the plaintiff had claimed damages for loss of their use for a period of thirty-five days. In its memorandum of decision, to which we can turn to ascertain the ground on which the court acted; see
Ruggles
v.
Town Plan & Zoning Commission,
*627
We next consider the plaintiff’s claim that the trial court erred in failing to award damages he claimed under General Statutes § 42a-2-713, entitled “Buyer’s damages for . . . repudiation,” which provides: “(1) Subject to the provisions of section 42a-2-723 with respect to proof of market price, thе measure of damages for . . . repudiation by the seller is the difference between the market price at the time when the buyer learned of the breach and the contract price together with аny incidental and consequential damages provided in section 42a-2-715 .... (2) Market price is to be deter *628 mined as of the place for tender or, in cases of rejection after arrival or revocation of acceptance, as of the place of arrival.”
It was incumbent upon the plaintiff to offer evidence sufficient to prove the damages claimed. See
Jones Destruction, Inc.
v.
Upjohn,
The plaintiff also made two claims for consequential damages, the first of which is for loss of profits he would have earned on the resale of the earth materials. The plaintiff testified that he had five oral contracts with third parties for the resale of the materials, but nonе of those third parties were called as witnesses on his behalf. As his testimony on this point involved questions of credibility for the trial court to determine; see
Slavitt
v.
Ives,
As to his second claim for consequential damages, the plaintiff аlleged that he planned to use some of the earth materials purchased from the defendant on other property which the plaintiff had an option to purchase, and he claimed damages caused by the defendant’s failure to supply that material. The court disallowed this claim, concluding that the plaintiff had not proved those damages. That conclusion will not be disturbed as it is based upon a determination of credibility; French v. Ober-reuter, supra; and as it is supported by the facts as found by the court.
*630 Therefore, we hold that the trial eonrt did not err in conelnding that the plaintiff had failed to prove the damages which he claimed under § 42a-2-713 and in awarding damages in the amount of $22,513, plus interest in the amount of $7,766.98.
There is no error.
In this opinion the other judges concurred.
