94 Cal. 229 | Cal. | 1892
Action for the foreclosure of several mechanics’ liens.
The Los Angeles College Company entered into an agreement with W. E. Lane, bearing date September 8, 1887, for the erection of a college building for the sum of twenty-three thousand dollars, but the agreement -was not executed until October 6th, on which latter day it was filed in the office of the county recorder for Los Angeles County. The document then filed made reference to certain drawings and specifications as “hereunto annexed,” but they were not filed in the recorder’s office. Lane entered upon the performance of the contract, but .abandoned it March 6, 1888, and thereupon the college company took possession of the premises, occupied and used the same continuously thereafter, and caused the building to be completed on the 21st of April. At various dates, the earliest being March 19th, and the latest May 8tb, claims for mechanics’ liens were filed by the respective respondents herein, and afterwards eight sep
1. The practice adopted by the court below in making separate findings and judgments is not only inconsistent with its order consolidating the actions, but is itself attended with great inconvenience and the possibility of serious complication. The provision of section 1195 of the Code of Civil Procedure, authorizing such consolidation, is placed in the same category with that permitting the several claimants to join as plaintiffs in one action; and after the order of consolidation had been made, the court should thereafter have treated the actions as a single action by the respective plaintiffs against the defendants, and embodied its decision in a single set of findings, upon which a single judgment should have been entered. By this course the court would have very greatly abridged the record and facilitated its examination here, and would also have avoided certain inconsistencies in the findings of fact which it has made upon the same evidence. In five of the cases the court has found that the building was occupied by the owner on the 7th of March, but in one it finds such occupancy to have been on the 6th of March, and in twm it makes no finding whatever upon the subject. Inasmuch, however, as, under the view we take of the case, the time when such occupancy began is immaterial, these inconsistent findings do not constitute a reversible error. A more serious objection, however, is presented by the fact that separate judgments were entered in favor of the respective claimants at different
2. The contract between Lane and the college company is in the form of an ordinary building contract, and provides that the contractor will do the work contracted for “ conformable to the drawings and specifications made by E. B. Young, architect, and signed by the parties, and hereto annexed.” The insertion of this clause in the contract made the drawings and specifications an essential part thereof, as material as was the price of the work or the terms of payment; and until they were “ annexed” to the contract so that its entire terms could be ascertained by mere inspection, and without oral testimony, the contract was only inchoate, and not complete, and could not form the basis of a recovery. (Worden v. Hammond, 37 Cal. 63.) Being by virtue of its terms a part of the contract itself, it was necessary for the parties thereto, or one of them, if it was desired that the contract should be the basis of his liability, or the measure of his right of recovery, to cause the same to be filed in the recorder’s office, and a failure to do so destroyed the validity of the contract. (Holland v. Wilson, 76 Cal. 434.) It is quite as important for the owner as for the contractor to see that the contract is so filed, since without it his liability has no contractual limit. It does not appear from the record
In 1887 the legislature amended section 1183 of the Code of Civil Procedure by providing that instead of filing the entire contract in the recorder’s office, as had been previously required, there might be filed a memorandum thereof, “ setting forth the names of all the parties to the contract, a description of the property to be affected thereby, together with a statement of the general character of the work to be done, the total amount to be paid thereunder, and the amounts of all partial payments, together with the times when such payments shall be due and payable.” After this amendment was made, the owner or the contractor could satisfy the statute by filing either the contract or such memorandum; but if he filed the contract, he must still file the whole of it, including the drawings and specifications, if they were made a part thereof; while if he preferred to file the memorandum, such memorandum must contain all the matters which are prescribed in the statute as the equivalent of the contract.
Section 1184 of the Code of Civil Procedure declares: “The contract price shall, by the terms of the contract, be made payable in installments, at specified times, after the commencement of the work, or on the completion of specified portions of the work, or on the completion of the whole work; provided, that at least twenty-five per cent of the whole contract price shall be made payable at least thirty-five days after the ’final completion of the contract.....In case such contracts and alterations do not conform substantially to the provisions of this section, the labor done and materials furnished by all persons except the contractor shall be deemed to have been done and furnished at the personal instance and request of the person who contracted with the contractor, and they shall have a lien for the value thereof.”
The contract in the present case fails to conform to
Whether the document which was filed in the recorder’s office is to be regarded as the original contract, or as a memorandum thereof, is immaterial. A memorandum of the contract can have no higher force than the contract itself, and if the contract fails to comply with the requirements of the statute, the memorandum itself must be equally insufficient. As a memorandum merely, the document so filed was insufficient, by reason of its
The finding of the court that there had not been filed in the recorder’s office a contract or memorandum containing the statements required by the statute was therefore correct, and the effect of such finding, under the provision of section 1183 of the Code of Civil Procedure, was to render the contract “wholly void” for all purposes. It cannot be the basis of a recovery by the contractor against the owner, nor can it be looked to for the purpose of determining the amount for which the owner is liable, or when any payment is to be made. In any action against him by a laborer or material-man, their rights are to be determined by other rules, and irrespective of any provision of such contract.
3. It is provided in section 1183 that the laborers and material-men “ shall have a lien upon the property upon which they have bestowed labor or furnished materials, for the value of such labor done and materials furnished, whether at the instance of the owner, or of any other person acting by his authority,” and also that “ every person having charge of ... . the construction of any building .... shall be held to be the agent of the owner for the purposes of this chapter.” The same
Section 1187 declares that “ every person, save the original contractor, claiming the benefit of this chapter, must, within thirty days after the completion of any building,” file his claim of lien with the county recorder. If the contract is “ wholly void,” there is neither a “ contract ” nor an “ original contractor,” and in such case every person claiming a lien must file his claim within thirty days after the completion of the building, as he is required to do whenever he makes a direct contract with the owner in person. (Sparks v. Butte Co. M. G. Co., 55 Cal. 389; Schwartz v. Knight, 74 Cal. 432.) The filing of a claim before the completion of the building is premature, and confers no right. (Roylance v. San Luis Hotel Co., 74 Cal. 273.) In the absence of any statutory qualification or definition of the term “ completion,” there would be no room for its construction by the court, but it would be construed to mean actual completion, and would be a question of fact to be determined in each case. The statute has, however, pro
The statute has, however, in a limited class of cases, made another exception to the rule which requires actual completion of the building before the claim of lien can be filed. In this exception, however, it has placed a limitation to the extent of the exception, making it applicable only in certain designated cases, so that if any one would avail himself of the exception, he must show that he is within the limited class for which the exception was made. It is provided in section 1187 that, “in case of contracts,” the occupation or use of the building by the owner, or his acceptance of the building, shall be deemed conclusive evidence of completion. This exception to the general rule is, by its terms, of limited application, and can be invoked in behalf of the claimant only “in case of contracts”; and the “contract” which is here referred to is the one between the owner and him who is termed the “ original contractor,” under which, and subject to whose terms, the laborer and the material-man must enforce their liens. One object of this provision is apparent: that the owner and the contractor shall not, by a secret agreement between themselves, abandon the original contract before its completion, or dispense with the completion of the building according to its original plan, and thereby, by being able to show
The provision of the statute that this conclusive evidence of completion shall be applicable only “in case of contracts” makes it essential that the claimant who would invoke the provision in support of his claim of lien, filed before the actual completion of the building, shall show that at the time of such occupation or use
The court finds, in the present case, that the college building was not actually completed until the 21st of April, and it finds that the notices of lien, with the exception of those filed on behalf of the plaintiff Willamette Steam Mills Company, the plaintiff Thompson, and the plaintiffs McLeod & O’Leary, were filed prior to that date. It follows, with the exception of the three plaintiffs above named, that judgment should have been rendered in favor of the appellants.
4. The motion on the part of the college company to amend its answer was properly refused, for the reason that the matters sought to be presented in such amendments were immaterial. Inasmuch as by a failure to file the contract in the recorder’s office it became wholly void, it was not available as a defense for any purpose, either to determine the amount of the contract price, or to limit the liability of the appellant, or as the foundation of a right to complete the building according to its terms.
The judgment and order denying a new trial are reversed as to the respondents the Los Angeles Planing Mill Company, the California Door Company, the Harper-Beynolds Company, B. A. Breakey, and Charles B. Tidball et al., and the court is directed to enter judgment upon its findings in favor of the appellant as against the said respondents; and as to the respondents Willamette Steam Mills Lumbering and Manufacturing Company, Robert Thompson, and McLeod & O’Leary, the order denying a new trial is affirmed, and the court
Garoutte, J., McFarland. J., Paterson, J., and Sharpstein, J., concurred.
Rehearing denied.