Charles R. WILKIN
v.
DEV CON BUILDERS, INC., et al. Consolidated with
In re PONCHATOULA HOUSING AUTHORITY.
Supreme Court of Louisiana.
*67 Mark C. Landry, Newman, Drolla, Mathis, Brady & Wakefield, Metairie, for applicant.
Robert Tillery, Thomas E. Balhoff, Mathews, Atkinson, Guglielmo, Marks & Day, Baton Rouge, for respondents.
CALOGERO, Chief Justice.[*]
Charles Wilkin filed suit against a contractor, Dev Con Builders, Inc., the contractor's surety, Eastern Indemnity Company, and the contractor's principal, the Ponchatoula Housing Authority. Having paid certain Dev Con suppliers and taken subrogation from them, Wilkin sought to recover the amounts of those claims. The trial court denied his claim finding that he was not in the class of claimants to which the public contract statutes refer.[1] The court of appeal affirmed on other grounds finding that Wilkin loaned money not to Dev Con but to Watkins personally and was therefore not properly subrogated to the suppliers' rights. We granted writs to determine whether there was a proper and legal subrogation, and whether, assuming he is properly a subrogee, Wilkin could assert the suppliers' subrogated rights under La.R.S. 38:2241 et seq. We answer both questions in the affirmative.
In 1983 Charles R. Wilkin became interested in developing a construction business. As a result of Wilkin's inquiries, Charles A. Watkins learned of that interest and called Wilkin. The two men met on or about October 25, 1983, to discuss the possibility of a future partnership in the construction business. When they met Watkins was already president, chief executive officer, and 20% shareholder of Dev Con Builders, Inc. Dev Con was under contract at the time with the Ponchatoula Housing Authority to construct low income housing, and was also involved in a different construction project in Belle Chasse, Louisiana. Watkins and Wilkin met several times to discuss possible business ventures, whereupon Wilkin learned of Dev Con's ongoing projects and of the cash flow problems associated with those projects; because of Dev Con's inability to pay certain suppliers, those suppliers were refusing to continue to supply needed materials.
Wilkin reviewed Dev Con's financial records and decided to extend cash to help Dev Con over its "cash flow hump" and allow it to successfully complete those projects. To protect his cash outlay Wilkin drew up five documents, the legal significance *68 of which are now in question. One was labeled "Promissory Note," dated December 5, 1983, and signed by Charles A. Watkins and two witnesses.[2] The other four documents were labeled "Subrogation of Rights."[3] These latter four documents were dated between December 6 and December 9, 1983, and filled in to reflect amounts owed to different suppliers.[4] As Wilkin paid each supplier directly, that supplier signed the "subrogation of rights, acknowledgment by creditor" and Watkins signed the "acknowledgment by debtor" as the President of Dev Con.
Despite Wilkin's cash infusion, Dev Con defaulted on the Ponchatoula project on December 23, 1983, when the December draw was withheld and Dev Con found itself without funds to proceed. Thereafter, on January 27, 1984, Wilkin filed in the Tangipahoa Parish mortgage records an "Affidavit of Lien," which was a sworn statement of amounts due him as a result of money he paid to suppliers of materials for the Ponchatoula building project.[5] On January 4, 1985, Wilkin filed suit against Dev Con, Eastern Indemnity Company of Maryland which issued the payment and performance bond on the project, and the Ponchatoula Housing Authority, to enforce his claim. When the State of Maryland issued orders of liquidation and insolvency against Eastern Indemnity Company, Wilkin amended his petition to add the Louisiana Insurance Guaranty Association as defendant.[6]
The district court ruled in favor of defendants, finding that the suppliers could not *69 validly subrogate their rights to one not expressly designated as a claimant under La.R.S. 38:2241 et seq., and Wilkin appealed. The court of appeal affirmed, but for different reasons. The court of appeal determined that Wilkin was never properly subrogated to the rights of the suppliers. Wilkin v. Dev Con Builders, Inc.,
The court of appeal concluded that subrogation did not take effect because the promissory note signed before the subrogations were executed indicated that Wilkin had loaned money to Watkins, which money was then used to pay suppliers, so that Wilkin had not paid suppliers with his own money but rather with Watkins' money, and for Watkins. Furthermore, according to the court of appeal, the note evidencing the loan showed that the money was loaned to Watkins personally since the note did not contain express language binding Dev Con for the debt. Therefore the court of appeal concluded that Wilkin was not properly subrogated. We find otherwise.
Because Wilkin's agreements were made before the 1984 Civil Code revisions, we look to the articles on subrogation in the Civil Code of 1870, in force in 1983, to determine the legal effect of these agreements. The Code defines subrogation as "the right of a creditor in favor of a third person who pays him." La.C.C. art. 2159 (1870). It delineates two types of conventional subrogation:
1. When the creditor, receiving his payment from a third person, subrogates him in his rights, actions, privileges, and mortgages against the debtor; this subrogation must be expressed and made at the same time as the payment.
When the debtor borrows a sum for the purpose of paying his debts, and intending to subrogate the lender in the rights of the creditor. To make this subrogation valid, it is necessary that the act of borrowing and the receipt be executed in presence of a notary and two witnesses....
La.C.C. art. 2160 (1870).
It is clear that had Wilkin only utilized the four "subrogation" documents when paying the suppliers, subrogation would have taken place according to article 2160(1) because the creditors (suppliers) received payment from a third person (Wilkin) and expressly subrogated him to their rights at the same time that payment was made. Only the presence of the prior executed "promissory note" creates some doubt. If, in fact, Wilkin had loaned funds to Watkins, or to Dev Con, Wilkin could not be validly subrogated to Dev Con's claim against the Housing Authority according to article 2160(2) because the act was not executed in the presence of a notary (although it was before two witnesses). Furthermore, the "promissory note" raises questions as to the intent of the parties and the nature of their overall transaction. Was money loaned to Dev Con, or to Watkins personally, to help complete the construction project? Or was money paid by Wilkin to suppliers with the knowledge and consent of Dev Con, the debtor, with the intention, or anticipation, of Wilkin's stepping into the suppliers' shoes?
When the language of a contract is unclear, it must be interpreted so as to ascertain the common intent of the parties rather than to adhere to the literal sense of the terms, and it should be interpreted in the way most congruous to the object of the contract. La.C.C. arts. 1950, 1952 (1870); Emile M. Babst Co., Inc. v. United States Fidelity & Guaranty Co.,
When applying these principles to the "promissory note," we are convinced that the object of the agreement, as with the "subrogations," was for Wilkin to pay off Dev Con's creditors/suppliers and become subrogated to their rights. Language in the "promissory note" refers directly to the acts of subrogation, to funds paid directly to suppliers, and to articles 2160, 2161, and 2162 of the Louisiana Civil Code.[7] Furthermore, money was paid by Wilkin directly to the suppliers rather than to Watkins or some other representative of Dev Con. Finally, both Wilkin and Watkins testified that Dev Con, rather than Watkins personally, was to be the debtor, and that Wilkin's purpose was to infuse needed funds without his own "risk of capital." Therefore, we find that the intent of the parties was to subrogate Wilkin to the rights of the creditors/suppliers and that the documents which they executed were sufficient in form to achieve this purpose.
Next we must determine the effect of the subrogation agreement and of Wilkin's attendant claim filed in the mortgage records. The trial court determined that public contract law did not recognize liens (or claims) filed by parties not specifically defined in the statute as claimants. Upon applying the principles of subrogation and the statutes pertaining to public contract law, we conclude that the claim filed by Wilkin as subrogee of the suppliers has binding legal effect under La.R.S. 38:2241 et seq.
Louisiana has long evidenced an intent to protect those who perform work and supply materials for the construction and repair of buildings and other works. The earliest Louisiana Civil Code granted a privilege on immovables to workmen employed in constructing and repairing buildings or works. La.C.C. art. 75 (1808). Later Codes included suppliers of materials for buildings or improvements in the class of those who were entitled to the rights, and granted them a lien and a privilege on the building or improvement as well as on the lot of ground on which the building or improvement stood. See La.C.C. art. 3216 (1825); La.C.C. art. 3249 (1870); La.C.C. art. 3249 (1984); Daggett, Louisiana Privileges & Chattel Mortgage 218-19 (1942).
However, workmen and suppliers engaged by agencies of the state for construction and improvement of public property were not entitled to take advantage of these provisions, or of provisions of later enacted private building contract statutes[8] because liens were not enforceable against public property. Porter v. Town of Ville Platte,
*71 Public contract law provides that when the representative of a governing authority enters into a contract for construction of a public work, a bond must be provided.[10] The law further establishes the means for asserting a claim:
Any person to whom money is due for doing work, performing labor, or furnishing materials or supplies for the construction... of any public works ... may after the maturity of his claim and within forty-five days ... of notice of default of the contractor ..., file a sworn statement of the amount due him with the governing authority having the work done and record it in the office of the recorder of mortgages for the parish in which the work is done.
La.R.S. 38:2242 (1979). The effect of these provisions is to give certain certain classes of persons not enjoying privity of contract with the general contractor or with the governing authority a claim nevertheless against the general contractor and his surety and in some instances a claim against the governing authority itself.[11] The provisions also protect the public authority complying with the requirements of the statutes from expenses caused by failure of the contractor to faithfully perform the contract. Town of Winnsboro v. Barnard & Burk, Inc.,
These provisions have been interpreted by this court to limit claims to those who have a contractual relationship with either the contractor or subcontractor. T.M. Thurman v. Star Electric Supply, Inc.,
Defendants argue, as did the trial court, that Wilkin was not entitled to file a claim on this public works project because Wilkin is not included in the category of claimants entitled to do so by law. Defendants note that public contract laws are to be strictly construed such that the privileges granted are not extended beyond the statutes. Rester v. Moody & Stewart,
Similar arguments have been made in cases decided under the Miller Act[12] and its predecessor, the Heard Act, federal equivalents to our own public contract law. In Clifford F. MacEvoy Co. v. United States,
So too in this case, we find that Wilkin, by means of the subrogation agreements, stands in the shoes of Dev Con's suppliers and is entitled to enforce the suppliers' subrogated rights.[14] When a third party pays the debt of another and becomes subrogated to the creditor's rights, that debt is extinguished as to the original creditor but not extinguished as to the debtor; instead the debt continues to subsist in favor of the third party. Great Southwest Fire Ins. Co. v. CNA Ins. Co.,
In State v. Miller,
In the instant case, we agree with the trial court that statutes which create privileges are not to be extended by implication. Subdivision Planning Engineers v. Manor Development Corp.,
Inasmuch as neither the district court nor the court of appeal found need to examine Wilkin's evidence regarding proof in support of his claims, and considering that the case was fully tried on the merits, this case will be remanded to the court of appeal for further proceedings addressing Wilkin's entitlement to a judgment and the amount thereof.
DECREE
For the foregoing reasons the decisions of the trial court and court of appeal are reversed. The case is remanded to the court of appeal for further proceedings in accordance with this opinion.
REVERSED, REMANDED TO COURT OF APPEAL
MARCUS, J., concurs in part and dissents in part for reasons assigned by COLE, J.
COLE, J., concurs in part and dissents in part for reasons assigned.
COLE, Justice (concurring in part, dissenting in part).
The first issue addressed by the majority is whether the Civil Code requirements for a valid subrogation were met by virtue of the agreements executed between Wilkin, Watkins, and four of Dev Con's suppliers. The second issue is whether the Public Works Act[1] may be interpreted to allow subrogation of suppliers' rights to a third party not involved in the project. I concur in the majority's finding that the Civil Code requirements for a valid subrogation were met. However, I respectfully dissent from this court's holding that the privilege afforded to claimants under the Public Works Act is transferable to third parties not involved in the project.
A. Subrogation
Subrogation can result from the performance of the obligation of another (Dev Con) by a third party (Wilkin), or from a loan by the third party (Wilkin) in order for the original obligor (Dev Con) to perform the obligation himself. LSA-C.C. arts. 1826, 1827 and 1828, formerly C.C. arts. 2159-2162, C.C. art. 2160(1) and C.C. art. 2160(2) (1870), respectively. In the case of a loan from a third party to the obligor, the subrogation must be express and in writing. At the time the subrogation agreements in this case were confected, an authentic act *74 was required for subrogation to result from a loan. LSA-C.C. art. 2160(2) (1870).
The requirements of LSA-C.C. art. 2160(1) (1870) were met when the four subrogation agreements were executed. These agreements, as well as the promissory note, indicate the suppliers (creditors) received payment from Wilkin, a third party, as required by article 2160(1) (1870). As evidenced by the note's recitation, "In each case the funds have been paid directly to suppliers ..." Similarly, the subrogation agreements provide: "I acknowledge receipt from Charles R. Wilkin, of.... and any other legal rights to enforce collection are subrogated to Charles R. Wilkin, from whom payment is received." (emphasis added).
Furthermore, the subrogation was expressed and made at the same time as the payment, as required by article 2160(1) (1870). Whether the note was executed before or after the subrogation agreements or before or after the receipt of payment by the suppliers is irrelevant, and does not affect the subrogation which resulted under LSA-C.C. art. 2160(1) (1870) from the subrogation agreements. The promissory note executed between Wilkin (subrogee) and Watkins (debtor) in addition to and prior to the subrogation agreements does not render the subrogation invalid under article 2160(1) (1870).
Although subrogation under article 2160(1) (1870) could have been accomplished without the consent of the debtor, it was a prudent and reasonable measure to obtain the debtor's consent. Implicit in the debtor's consent is a promise to repay the subrogee or new creditor the amount of funds paid to the old creditors. That Watkins' promise was made expressly, and in writing, does not affect the validity of the subrogation which resulted from the third party's (Wilkin's) payment to the creditors (suppliers) and their express, contemporaneous agreement to subrogate him to their rights. The note is merely an acknowledgement of the debt owed to Wilkin by virtue of his performance of the obligation.
The transactions evidenced by the subrogation agreements and the promissory note could be construed as a loan by Wilkin to Watkins as found by the court of appeal. Since the note agreement is not an authentic act, however, subrogation could not have resulted from the loan. LSA-C.C. art. 2160(2) (1870). Nonetheless, the failure of the note agreement to satisfy the authentication requirements of article 2160(2) does not preclude a finding that a subrogation was effected under article 2160(1).
I therefore concur in the majority's finding that a subrogation was properly and validly effected. I dissent, however, from the holding that a supplier's privilege under the Public Works Act is transferable to third parties not involved in the project.
B. The Public Works Act
The Public Works Act provides protection to "claimants" who have been hired by a general contractor for the construction, alteration, or repair of public works. Those persons who qualify as "claimants" are specifically defined in LSA-R.S. 38:2242(A), which, at the time Wilkin filed the lien, provided:
"Claimant", as used in this Chapter, means any person to whom money is due pursuant to a contract with a contractor or subcontractor for doing work, performing labor, or furnishing materials or supplies for the construction, alteration, or repair of any public works, or for transporting and delivering such materials or supplies to the site of the job by a for-hire carrier, or for furnishing oil, gas, electricity, or other materials or supplies for use in machines used in the construction, alteration, or repair of any public works, including persons to whom money is due for the lease or rental of movable property, used at the site of the immovable and leased to the owner by written contract, and including any architect or consulting engineer engaged by the contractor or subcontractor in connection with the building of any public work. (emphasis added).
Under the Act, the general contractor must obtain a bond which secures its obligation *75 to pay "claimants." Within forty-five days after the recordation of acceptance of the work by the governing authority or of notice of default of the contractor or subcontractor, a claimant may file a sworn statement with the governing authority of any amount due him by the general contractor, and record it in the mortgage records for the parish in which the work was done. LSA-R.S. 38:2242(B). The filing of this claim preserves the claimant's statutory privilege whereby he is entitled to payment from the governing authority in preference to any payment due by the authority to the general contractor. A governing authority's failure to pay claimants with outstanding claims in preference to the general contractor, renders the governing authority liable for the amount of the outstanding claims. LSA-R.S. 38:2242(D).
The Public Works Act, as a whole, evidences an intent to protect those who directly aid in the construction of a public project.[2] Generally, materialmen and laborers have contractual privity with the general contractor, but not with the governing authority. The Public Works Act provides a method for claimants to obtain payment from the primary source of funds for the project (i.e., the governing authority), rather than from the secondary source of funds (i.e., the general contractor who receives from the governing authority funds which are to be used to pay the materialmen and laborers). This privilege provides a measure of protection to those who have no contractual relationship with the governing authority, and no control over the funds advanced by the authority to the general contractor during construction of the project. In the event the general contractor does not use the funds advanced by the authority to pay the laborers and materialmen, as contemplated by the authority, but uses them instead for his own personal benefit, or to pay a debt he owes to another, the claimants are protected.
The provisions of the Public Works Act must be strictly construed. American Creosote Works, Inc. v. City of Natchitoches,
Plaintiff argued, and the majority apparently agreed, that our decision in Subdivision Planning Engineers v. Manor, etc., supra, supports his contention that the privilege afforded claimants under the Public Works Act may be transferred by subrogation. See note 15 of majority opinion. In Manor, two partners performed work on a project which was governed by the Private Works Act, LSA-R.S. 9:4801 et seq. *76 They subsequently incorporated their business and the corporation performed the remainder of the work. The partners assigned their claim to the corporation, which filed the lien. This court found the rights resulting from the work done by the incorporators prior to incorporation were assigned by them to the corporation, and the transfer of the right included the transfer of the accessory lien. While recognizing "statutes creating civil penalties and privileges are not to be extended by implication," this court found there was no extension of the Private Works Act in its holding because part of the work was done by the corporation. We also noted the corporation's contract was directly with the owner. Thus, the defendant owner's obligation to the plaintiff corporation would exist without the lien statute. We note there is no contractual privity between Wilkin and the Ponchatoula Housing Authority. Manor is therefore inapposite.
While State v. Miller,
Finally, I am not persuaded by the treatment afforded the federal equivalent to our own public contract law, which the majority uses by analogy to bolster its result. The source provision varies from our own statute and we should adhere to our oft repeated admonition that our Public Works Act must be strictly construed.
NOTES
Notes
[*] Retired Chief Justice John A. Dixon, Jr. participated in this case having been Chief Justice of this court when the case was orally argued and taken under advisement.
[1] Louisiana public contract law, La.R.S. 38:2241 et seq, entitled "Claims of Subcontractors, Materialmen, and Laborers on Public Works," and sometimes referred to as the Public Works Act, creates a counterpart to the Private Works Act, La.R.S. 9:4801 et seq. which grants certain laborers and suppliers a lien on the private construction work. Although the rights granted to laborers and suppliers under public contract law are sometimes referred to as "liens," these claimants are not really entitled to a lien on the public works themselves. In lieu of a lien, the public contract law grants certain claimants a privilege against the unexpended funds in the hands of the public authority. A discussion of these provisions appears later in this opinion.
[2] Promissory Note
I, Charles A. Watkins, promise to repay Charles R. Wilkin or order within Sixty (60) days after date at Slidell, Louisiana, the principal amount advanced to me, as his interest may appear, plus interest at the rate of 14.5% simple.
These funds are advanced to complete the Ponchatoula Housing Authority Project LA 48-P075-005. In each case the funds have been paid directly to suppliers, material men, mechanics, or sub-contractors whose services or materials were essential in my judgment to complete the project.
It is the intent, as covered by acknowledgments of subrogation signed by each recipient when funds were paid for the account of Devcon Builders, Inc., that all rights of the parties paid as pertains to means of collection, placing liens, etc., be subrogated to Charles R. Wilkin under Articles 2160, 2161, and 2162 of the Louisiana Civil Code.
I also agree that these funds will be repaid when construction draws are received for these items. Should legal expense become necessary to file liens or to pursue collection through court action, all legal expense plus attorney fees not to exceed 25 percent will be paid by Dev Con Builders, Inc.
Lender reserves the right to waive formalities voluntarily or involuntarily without impairing his rights to collection in full.
__________________ Charles A. Watkins Witnesses: ____________________ ____________________[3] Subrogain of Rights
Acknowledgement by Creditor
I acknowledge receipt from Charles R. Wilkin, of______ in full payment for________ to be performed and/or installed on the Pontchatoula Housing Authority Project, LA48-P075-005 for the General Contractor, DEVCON BUILDERS, INC. of Mandeville, Louisiana, as per plans and specifications.
All my rights as a supplier of material or labor or as a sub-contractor on the above item(s) related to collection of funds due, including the rights to file liens under the laws of the State of Louisiana and any other legal rights to enforce collection are subrogated to Charles R. Wilkin, from whom payment is received.
Company ____________________ BY______________________ Title ____________________ACKNOWLEDGEMENT BY DEBTOR
I accept payment on the account of Devcon Builders, Inc. for the specific Item(s) specified above and acknowledge that all rights to collect said funds advanced from Devcon Builders, Inc. or its surety are transferred to Charles R. Wilkin.
____________________ Charles A. Watkins, President DEVCON BUILDERS, INC.[4] Gabriel Building Supply Co., Inc.$4578.53, Campbell Building Material Co., Inc.$4022.19, Kentwood Brick Co.$2675.00, and Louisiana Power and Light$9075.65.
[5] The affidavit included a charge of $58.73 for materials which Wilkin supplied Dev Con for the Ponchatoula project as well as the sums advanced the four suppliers for a total of $29,419.10.
[6] La.R.S. 22:1380-22:1382 establishes the Louisiana Insurance Guaranty Association as a legal entity which is obligated for covered claims of certain insolvent insurers.
[7] Wilkin, though an accountant and not an attorney, owned a copy of the Louisiana Civil Code which he had "picked up in a thrift shop" and used to prepare the documents. Wilkin testified that he "believe[d] in ... God and the Louisiana Civil Code."
[8] Statutes pertaining to private works are now codified in La.R.S. 9:4801 et seq.
[9] See also Decatur Cornice & Roofing Co. v. Caldwell Bros.,
[10] As in existence in 1983, La.R.S. 38:2241(A) provided: He shall require of the contractor a bond, with good, solvent, and sufficient surety... for the faithful performance of the contract with an additional obligation for the payment by the contractor or subcontractor for all work done, labor performed, or material or supplies furnished for the construction ... of any public works. The bond shall be executed by the contractor with surety or sureties approved by the officials representing the state ... and shall be recorded with the contract in the office of the recorder of mortgages in the parish where the work is to be done not later than thirty days after the work has begun.
[11] For example, La.R.S. 38:2244(B) provides in part: Whenever it is found that the surety is not solvent or sufficient to cover the amount of the bond or that the governing authority has failed to exact the bond or record the bond within the time allowed, the governing authority shall be in default and shall be liable to the same extent as the surety would have been.
[12] 40 U.S.C. § 270a et seq.
[13] For examples of cases in which assignees of persons furnishing labor or material to public works projects were allowed to file claims on payment bonds under the Heard or Miller Acts, see U.S. Fidelity & Guaranty Co. v. United States ex rel. Bartlett,
[14] "To subrogate means `to put in place of.'" Planiol, Civil Law Treatise Vol. 2, §§ 475 n. 24; 506.
[15] See also Subdivision Planning Engineers, Inc. v. Manor Development Corp.,
[16] La.R.S. 38:2242 (1950), amended by Acts 1960, No. 59, § 1; Acts 1966, No. 537, § 1; Acts 1977, No. 253, § 1; Acts 1979, No. 406, § 2; Acts 1985, No. 703, § 1; Acts 1985, No. 244, § 1; Acts 1986, No. 158, § 1; Acts 1986, No. 195, § 1; Acts 1989, No. 305, § 1.
[17] We have addressed in this opinion the specific legal questions regarding the adequacy of the subrogation and the availability of statutory claim rights in the subrogee. The question of whether Wilkin's recordation conforms with statutory requirements and whether he proved with adequate evidence his claim, and his consequent entitlement to judgment, and the amount thereof, are matters to be addressed by the court of appeal upon remand.
[1] LSA-R.S. 38:2241, et seq.
[2] In its earliest form, the Public Works Act provided in part:
AN ACT
Relating to contracts for public works; to protect persons doing work, performing labor or furnishing material for the construction, erection, alteration or repair of public buildings, public roads or public works of any character; requiring the State, Parish, city, town, village, public board or body having the work done to exact a bond, with good and solvent surety, for the protection of itself, for the faithful performance of the contract and the payment of all persons doing work, performing labor or furnishing material therefor.... Louisiana Legislative Acts, 1918, No. 224. (emphasis added).
[3] We note the surety [now LIGA] may look to the provision of LSA-R.S. 38:2241 which mandates its performance bond to be "a statutory bond" and the surety "shall be immune from liability for or payment of any claims not required by this Part."
