30 Fla. 377 | Fla. | 1892
Thomas Stephenson, the appellee, sued the appellant, James M. Wilcox, in the Circuit Court of Orange .county in assunrpsit for an alleged balance of 82,137.90 due him upon a building contract, whereby the plaintiff agreed to construct a building for the defendant known as the ‘West End Hotel,” furnishing all the materials therefor, and whereby the defendant agreed to pa.y to the plaintiff the aggregate sum of 814,650. The trial resulted in- a verdict and judgment for the plaintiff in the sum of 81,516. Motion for new trial being refused, the defendant brings the case here upon appeal.
The first assignmenkof error is the overruling by the court below of the defendant’s demurrer to the plaintiff’s fourth amended declaration.
The amended declaration questioned by this demurrer contained a special count upon the written contract entered into by the parties, setting forth the contract and a supplemental contract in extenso as part thereof, and contained also a general count in qioantum meruit and quantum valebant for work
The second assignment of error is abandoned.
At the trial after proving- and putting in evidence the original and supplemental contracts and specifications, the plaintiff testified as follows: ‘ ‘I performed the work according tó the plans and specifications with certain exceptions made by the architect. A supplemental contract was made, the dining room was enlarged and porch was lengthened out. The changes were provided for in the supplemental contract. I did also extra work amounting to $80.55. I furnished throughout all timber in every respect according to the specifications. The architect was there all the time except a month. Work was accepted by him. Architect at no time refused to accept work. If he suggested alterations, I altered the work accordingly. The building was not completed within the time specified because a chimney settled. There was a wash-out on the E. R. & N. road, which detained the painter’s materials. There was a very serious settlement under a chimney in another part of the building, owing to a gopher hole, which detained me from some three, four or five weeks, and that was the real cause of delay.
There was no error in this ruling. Motions to strike out evidence that has been introduced in a. cause, as we understand the practice, must be predicated upon some feature of irrelevancy, incompetency, ■ legal inadmissibility, or impertinency in the evidence itself that is struck at. None of these are urged against this evidence by this motion, and could not have been, because it is open to none of these objections, being entirely relevant to the issue, and competent in every respect as far as it went' towards sustaining the plaintiff’s claim ; but the motion was predicated solely upon the ground that, though entirely proper, relevant and pertinent so far as it went, yet it did not go far enough to warrant a recovery; that another fact should have been proven in addition thereto, ws : that the work was performed to the satisfaction of the architect, and that the architect had certified that the amount claimed was due. When the plaintiff; rested his case upon testimony relevant, pertinent and proper so far as it went, but which, in the conception of the defendant,
When the architect, Charles K. Needham, was on the stand as the defendant’s witness, an ex parte written report made ,by him after the plaintiff had been ejected from the work by the defendant, and addressed to the defendant, was offered in evidence ; in which report divers defects were enumerated at great length and detail, both in the character and quality of the workmanship, and in the materials used in and about the buildings. On the plaintiff’s objection the court refused to permit this report to be introduced in evidence, and this ruling is assigned as the fourth error. There was no error in this ruling. The report offered was a written assertion of facts made ex parte to the defendant by the party then on the stand as a witness for the defendant, and if the facts set forth therein were true, pertinent and properly admissible, they could and should have been introduced in the form of sworn oral testimony from the lips of the witness, or in the form of depositions in anwer to interrogatories, put under the authority of a commission, after opportunity to cross them had been afforded.
In the contract it is further provided that “when the hotel building shall have been so far completed as in the customary progress of building to have received the first coat of plastering, six'weeks shall be allowed it in which to settle, etc., and when the first coat of plastering has been properly put on as aforesaid, and other requisites of the specifications in regard to this stage of the operations have been fully complied with, the party of the second part contracts to pay, or cause to be paid to the party of the first part the sum of ten thousand three hundred' dollars including previous payments; and thereafter correct estimates shall be made by the architect as before, the final payment being reserved until to the satisfaction of the architect such payment can be made leaving the premises liable to no lien.” The architect, as defendant’s witness, testified “that estimates were made according to the contract, and paid up to and including the ninth estimate; and that the seventh estimate was the estimate made when the building was standing to settle after the coat of rough plaster, at the time when the plaintiff was to receive a gross sum under the contract of $10,300. The idea was that this
The seventh assignment of error is the refusal of the court to permit ,the architect witness, Charles K. Needham, to reply to the following question: 1 ‘What would it cost to make the building conform to the contracts, plans and specifications ? ” This question, we think, would have been proper had it been so framed as to limit and confine the reply of the witness to the work and materials coming subsequent to the seventh estimate and certificate made by him as the defendant’s architect. Eor all work and materials preceding such estimate and certificate, and included therein, we have seen that under the contract, the doors were closed to any inquiry or objection. The objection to the question is that it was too broad, covering the entire building, and including within its scope work and material that had already been passed upon and accepted by the terms of the contract as being in satisfactory compliance therewith.
The eigth assignment of error has been abandoned.
The ninth assignment of error is the giving of the following charge to the jury: “If the jury believe
Orlando, Fla., Nov. 27th, 1885, 9 A. M.
To Thomas Stephenson, Builder:
Hear Sir : Notwithstanding your many statements that the West End Hotel would be completed
Yours truly,
James M. Wilcox,
Per James M. Wilcox, Jr., Agent.
The ground upon which the defendant, through his* agent, seems to have rested his right thus to eject the' plaintiff from 'the work, was that the plaintiff was not making satisfactory progress with the work, and because he had not completed it at the date fixed for its completion, while the contract between the parties, according to our interpretation of it, gave to the defendant this right of eviction only in case of the plaintiff’s: refusal or disability, from sickness or otherwise, to carry it out. • We therefore think that the eviction of the plaintiff from the work for the causes assigned therefor, was not authorized by the contract and was. wrongful. Another part of the contract made provision of a different remedy for delays in the completion of the work over the date fixed, viz: That the plaintiff should forfeit, $10 per day for every day that the* building remained uncompleted after the date specified. But, whether this eviction by the defendant-
For like reasons we think there was no error.in the following paragraxoh of the court’s charge, that is assigned as the tenth error : “The x>erformance by the plaintiff of his agreement according to xdans and specifications is a necessary condition for his recovery, unless the jury believe from the evidence that the plans or methods of xierformance have been waived by the defendant or his agent, or he was prevented by the act of Providence.” From the undisputed evidence it appears that the defendant by his agent did waive the full completion of the work by taking it away from the xfiaintiff, and comxfieting it himself.
We do not discover any error either in the following paragrax>h of the court’s charge, assigned as the eleventh error : “If the jury believe from the evidence that the xfiaintiff failed to perform his contract in such respect as not waived by the defendant or his agent, or that the xfiaintiff has been fully x^aid for his work, you will find a verdict for the defendant.” Ibis instruc
The refusal of the court to give the four following instructions requested by the defendant are assigned as the twelfth, thirteenth, fourteenth and fifteenth ■errors : 1st, “If the jury believe from the evidence that the architect has not certified the sum sued for in this action is due and payable, then the plaintiff can not recover.” 2nd. “ If the jury believe from the testimony that the plaintiff did not perform his agreement with the defendant to the satisfaction of the architect, then the plaintiff can not recover.” 3rd. “The performance by the plaintiff of his contract with the defendant is a condition precedent to his recovery in this case.” 4th. “If the jury find from the testimony that the plaintiff did not in good faith fulfill his contract with the defendant, the plaintiff can not recover.” After what has been said in reference to the prevention by the defendant, of the entire completion of the works by the plaintiff it becomes apparent that there was no error in the refusal to give these instructions.
The sixteenth and last error assigned is the entry of judgment for the plaintiff, instead of for the defendant. Prom what has been said this assignment can not be sustained. The entire contract price that the plaintiff was to have received for this work was $14,730.55, including some small charges for extras not contemplated by the contract. The payments made by the defendant that seem to be undisputed aggregate $12,-¿592.65, which, deducted from the agreed price, left a
The judgment below is affirmed.