Wiggin v. Marsh Lumber Co.

79 W. Va. 651 | W. Va. | 1917

POEEENBARGER, JUDGE:

The elaborate recital of facts of this case found in the opinion setting forth the grounds of the disposition of a for*652mer writ of error in it, 77 W. Va. 7, renders a restatement thereof unnecessary. The evidence adduced on the new trial awarded may differ in some respects, from that upon which the former verdict rested, but the matter in controversy is the same. Some grounds of recoupment previously relied upon were not asserted in the second trial, but some additional items of set-off, wrongful deductions of freight, were claimed. As on the former trial, full defense was made under the general issue, and the jury found for the defendants.

As it sometimes happens, the terms of the contract were more closely observed and adhered to on the second trial than on the first, and two provisions thereof not specifically and clearly invoked on the former trial became the basis of the court’s instructions, on the second. These were right.of election as to the place of loading the lumber, reserved to the plaintiff, and the inhibition of the defendants from delivery otherwise than as ordered by the plaintiff. The first was that delivery should be made “f. o. b. ears at Surveyor, W. Va. on the C. & O. Railway or The Virginian Railway at the election of the said Wiggin” and the other, that “the remainder of said lumber,” (all but the 50,000 feet to be furnished in October, 1908,), should be “delivered when ordered and directed by the said Wiggin and not otherwise.” On the former trial, the defendants sought only one very short instruction telling the jury to find for the defendants, if they believed all the lumber ordered to be placed on the cars, by the plaintiff, had been “delivered F. O. B. ears Surveyor.” The court gave it. In it, there is no express reference to these controlling provisions. For the plaintiff, the court gave six instructions on that trial and refused two others requested. Two of those given related to claims of recoupment, not now involved. One of them absolved the plaintiff from duty to prove actual damages. Two of them left it to the jury to say whether the defendants had failed to deliver lumber as ordered by the plaintiff, but did not define an order for lumber as contemplated by the contract. Another told them they might consider "the correspondence upon the inquiries submitted to them. One of the two refused would have placed upon the defendants the duty of furnishing the cars for car*653riage and'the other would have denied the defendants right to set up a breach of the contract by the plaintiff, if they had treated it as continuing.

On the second trial, the defendants sought- and obtained four instructions; the first of which told the jury the plaintiff could not recover liquidated damages, because of non-delivery of the 50,000 feet of lumber in October, 1908, as provided in the contract, if they believed from the evidence he had agreed to modify its terms as to that lumber; the second, that, if they believed the .defendants hauled 150,000 feet of poplar lumber to Surveyor, in the summer of 1909, and permitted the plaintiff’s inspector to inspect it and take from it such lumber as he desired, they should find he had waived their failure to haul it to the railroad in January, 1909, in compliance with his request; the third, that the statement in the letter of January 4, 1909, that the defendants might haui the oak lumber if they wanted to, although the plaintiff did not care particularly about it, was a mere permission to haul the oak, but not such an order as was‘contemplated by the contract of July 11, 1908, as to that lumber; and the fourth, that, although they might believe the plaintiff gave the defendants any orders permissible under the contract of July 11, 1908, before the institution of the action, with which they failed to com;,,„. >ei if they believed from the evidence, that it was agreed between -'.ho parties, after the institution of the action, that proceedings should be stayed and the contract completed, it then became the duty of each party to go on according to the terms of the agreement of July 11, 1908, and of the plaintiff to give orders as provided therein; and if they should believe there was no proof that the plaintiff gave such orders, and the defendants did not have them and could not complete the contract for want thereof, they should find for the defendants, or rather that 'the plaintiff was not entitled to liquidated damages. The court refused to honor the request of the plaintiff for three instructions, two of which, Nos. 1 and 6, treated the contract as imposing absolute duty upon the defendants to deliver the lumber within one year and the extensions of time assented to by the plaintiff, and the other, No. 3, ignored the defendants’ evidence *654tending to prove the delivery of 150,000 feet of poplar lumber at the railway siding and at the end of the tramway, and also treated the contract as absolute and unconditional. It also refused to give plaintiff’s instructions Nos. 2, 4 and 5, as drawn, but modified them and gave them as modified. One of these, No. 4, as requested and as-given, directed attention to the provisions of the contract, respecting the character of the orders to be given, and one of them, No. 2, advised the jury that the Marsh Lumber Company had no right to demand of Wiggin that he receive at one time the 150,000 feet of lumber, the defendants claimed to have hauled to the siding and the end of the tramway. All of them, as requested, absolved the plaintiff from estoppel ■ or denial of right, by his waiver of conditions. In this respect, the court amended them. At his instance, the court gave three other instructions, without amendment, Nos. 7, 8 and 9. The first of these advised the jury that the defendants, after breach of the contract by the plaintiff, could not set up such breach, if they had waived it; and second, that the plaintiff was not required to ship lumber furnished him at Surveyor, as soon as it was delivered there, but that he had a reasonable time after delivery in which to procure cars to load it; and the third, that the contract sued on was a continuing one until July 16, 1910, and that the plaintiff’s right to recover could not be defeated upon the ground of his failure to perform the contract, prior to that date, if the defendants did not furnish him any lumber under the contract, after that date.

Differences of opinion between the trial court and the attorneys for the plaintiff, as to the effect .of the decision of this court upon the former writ of error, were the inducing, causes of_ the adverse rulings complained of. Although the former verdict was set aside, careful examination and analysis of the opinion fail to disclose any purpose on the part of the court, to say the obligation of the contract on the part of the defendants was unconditional and absolute. On the contrary,, it distinctly asserts the burden of conditions precedent resting upon the plaintiff. It says the duty' of selecting the carrier and-giving shipping directions falls on the plaintiff, and that, without performance of these duties, the defendants *655•could not be required to load the lumber. Nor does it overlook or ignore the right of the defendants to have orders from the plaintiff, as conditions precedent. In support of the former verdict, failure of the plaintiff to furnish cars and designate the carrier was relied upon extensively in the argument, but it was held that failure to make one or more of the recmi-site selections named, did not exonerate the defendants from compliance with express requirements as to delivery at the time and place specified by the contract, when so ordered, and that cars could be secured, the carrier elected and destination given, after the assembling of the lumber. But the duty of the plaintiff to designate with each order, the place of loading, the Chesapeake and Ohio siding or the Virginian siding, a right which he had reserved, and the inhibition of deliveries without orders, were not distinctly relied upon in the argument, nor observed at all in the requests for instructions. These vital and controlling provisions of the contract were practically ignored, both in the trial court and in this court. But, when the case went back for a new trial, they were invoked. By their request for instruction No. 3, the defendants asked the court to tell the jury that their general order to haul lumber contracted for, or a mere permission to do so, without designation of the point to which it was to be hauled, was not such an order as was contemplated by the contract. Though their instruction No. 4, did not define the order contemplated by the contract, it did submit to the jury'an inquiry as to whether orders were given as provided for by it. One of the instructions given for the plaintiff on the former trial told the jury lumber was to be furnished as ordered by the plaintiff, not as ordered by him in compliance with the terms of the contract defining the character of the order. Another told them it was the duty of the defendants to haul and place the lumber at a convenient place at Surveyor, if so directed by the plaintiff. These instructions declaring the plaintiff’s right to order as he pleased, were followed by another asserting liability on the part of the defendants, for failure to furnish the plaintiff 500,000 feet of lumber, on his orders to do so provided for by the agreement. The first two allowed the plaintiff to order as he *656pleased, and tbe third did not suggest any different theory to the jury, by its reference to the agreement. The first two construed the agreement as one allowing the plaintiff to order as he pleased, and the third did alter that interpretation. On the second trial, the court refused to tell the jury the defendants were bound to place the lumber at a convenient place at Surveyor, when directed by the plaintiff, and told them it was the duty of the defendants to furnish the lumber, as ordered and directed by the plaintiff, or his agent, as provided by the contract. Two others given; at the instance of the plaintiff, did not so define or limit the order, but the definition was an explicit requirement of plaintiff’s instruction No. 4, and of defendants’ instructions Nos. 3 and 4. Their combined effect was to bring the conditions precedent into full and conspicuous view.

If the rulings of the court on the second trial are correct and the verdict is sustained by the evidence, no injustice will be occasioned by disregard' of so much of the former decision as is not accordant with the law of the case as it is now developed. It did not mislead either the trial court or the jury and application of correct principles of law will not result in a reversal of the judgment or award of a new trial. Under such circumstances, an erroneous decision on a writ of error may be disregarded on a second writ of error in the same case. Pennington v. Gillaspie, 66 W. Va. 643; Cluff v. Day, 141 N. Y. 580; Bomar v. Parker, 68 Tex. 435; Bird v. Sellers, 122 Mo. 23; Bynum v. Apperson, 9 Heisk. (Tenn.) 632; Barton v. Thompson, 56 Ia. 571. If the erroneous parts of the former decision had not been adopted, the costs here would have been adjudged against 'the plaintiff. These he then escaped. They will be no greater now than they would have been then. The costs of the second trial in the court below, which he may be deemed to have incurred as a result of the former decision, is comparatively a small matter, and, besides, he sought the privilege of a new trial and induced the error by which it was accorded him. Hence, it is obvious that no substantial injustice will result. The responsibility for the error must be shared by all members of this court that participated in the decision, the trial court and the *657attorneys. When the ease was previously in this court, it was earnestly considered in two conferences of all the judges as the court was then constituted.

The practical and common sense determination of the rights of the parties, evidenced by the two verdicts of juries, returned in disregard of the nisi prius court’s instructions on the first trial and in accord with a reasonable interpretation of those given on the second, seems to conform to. well settled law. The contract was one of dependent covenants or of covenants on the part of the vendor, dependent, as to obligation, upon the performance of conditions precedent by the vendee. If the vendee in a contract of sale reserves to himself the right to name the place of delivery, the quantities in which deliveries are to be made, the mode of shipment, the instrument of conveyance, or the like, the vendor’s, covenant does not bind him to act, until the vendee has exercised his election. His designation as to the subject matter of his reserved right of election is a condition either concurrent or precedent, performance of which the vendor may await. Benj., Sales, sec. 318. “Where the place is fixed but not the time, neither party, as will be seen, can ordinarily put the other in default until, in some way, the other has had reasonable notice of the time when delivery would be offered or demanded.” Mech., Sales, sec., 1126. “Where expressly or by implication the place of delivery is at the option of either party, that fact throws upon him the burden of taking the initiative, and it is his duty to give notice of the place -at which the goods will be offered or demanded. If the contract fixes, the kind or time of the notice, the contract must prevail; if it does not, reasonable notice would be required. Until such notice is given, the other party, if ready and willing to perform, is not in default.” Mech., Sales, sec. 1127. “If the place is specified but not the time, neither party can ordinarily put the other in default by tendering or demanding delivery at that place, unless reasonable notice of such act has been given the other, or unless the place or,circumstances are such as to fairly make the act appropriate without previous notice-; if the time or place is expressly or impliedly at the option of either party, he cannot tender or demand deliv*658ery until lie has given reasonable notice of- the time or place at which such delivery is to be made.” Mech., Sales, sec. 1130. If, in a sale of tobacco to be delivered f. o. b. cars at a certain place, there is no provision as to naming the carrier or the destination, the vendee must give the shipping directions, before he can demand performance on the part of the vendor, or put him in default. Hughes v. Knott, 138 N. C. 105. If a contract of purchase of railroad spikes provide that shipping directions shall be given by the buyer, his failure to give them exonerates the seller, and, if he gives, and then countermands them, before they are acted upon, the seller is not'in default. Railway Co. v. Hon Co., 126 Ill. 294. From the multitudinous decisions illustrating the operation of. the principle, the following may be regarded as accurate and representative: Dwight v. Echert, 117 Pa. St. 490; Rogers v. VanHoesen, 12 Johns. (N. Y.) 221; Dingley v. Oler, 117 U. S. 490; Harroe Spring Co. v. Harrow Co., 90 Mich. 147; Posey v. Scales, 55 Ind. 282; Weill v. Metal Co., 182 Ill. 128; Hunter v. Wetsell, 84 N. Y. 549; Armitage v. Insole, 14 Ad. & Ell. (68 E. C. L.) 727.

Stipulations as to quantities in which deliveries are to be made are equally essential and binding. “Not only must the article delivered correspond in kind with what is agreed upon, but it must also correspond in amount. Where a specific quantity or number is agreed upon, to be delivered at one time, that quantity or number must be delivered, and the seller will not 'perform his undertaking, if he delivers either more or less.” Mech. Sales, sec. 1157. “The precise amount to be furnished may also be left to be determined by one of the parties, and his determination, when made and manifested, fixes the quantity to which the contract applies.” Mech. Sales, see. 1170. “The seller is bound to deliver the quantity stipulated, and has no right either to compel the buyer to accept a less quantity or require him to select a part out of a greater quantity: and when the goods are to be shipped in certain proportions monthly, the seller’s failure to ship the required quantity in the first month gives the buyer the same right to rescind the whole contract that he would have had, if it had been agreed that all the goods should *659be delivered at once. ’ ’ Norrington v. Wright, 115 U. S. 188, 203; Mech. Sales, sec. 1216.- The provisions of the contract as to time, place, quantity, price and all other conditions are material and binding upon both parties.

The plaintiff reserved to himself, in express terms, the right to fix the times of delivery and the kinds and quantities of lumber to be shipped, from time to time, within the year. He also held the right of election as to the exact place of each delivery. All were to be made at Surveyor, but each at one of two different points, one-half mile distant from each other, and, in every case, he had power of designation of the point of loading. All deliveries were to be made on board of cars. No other delivery would pass the title, shift the hazard of damages or loss, or entitle the defendants to payment. The prescribed mode and conditions of payment were remittance on receipt, from plaintiff’s inspector, of bill of lading and invoice of lumber shipped.

The contract must be so construed as to make it operate reasonably and fairly. It contains no express provision as to interruption of the process of delivery, for the purpose of inspection. The parties did not likely contemplate the presence of an inspector, on the arrival of each wagon load or tramcar load of lumber; but such assemblage of lumber for inspection of shipments properly ordered, as may have been necessary, did not impose any duty upon the defendants to keep large quantities of lumber stored at or near the places of loading, for which no proper orders had been given, nor confer upon the vendee any right to demand it. However, it is unnecessary to construe the contract as to the rights and duties of the parties, respecting inspection. That part of it is not directly nor materially involved.

Of course, plaintiff’s rights of election could have been waived, in so far as they had been reserved for his exclusive benefit and protection, and no doubt were, in some instances and to some extent; but such waivers were obviously only partial. No letter found in the correspondence set forth in the former opinion,' or in the present record, signified any purpose or intent to take up and pay for lumber not actually loaded on the ears, receipted for by the carrier and invoiced. *660Nor was there any promise to absolve the defendants from duty to remove lumber stored at one loading place to the other, in case shipment from the other should be desired. Nor did the contract impose any obligation upon the defendants to store lumber at Surveyor, for use in performance of the contract. They could keep it where they pleased, until called for by proper orders for deliveries. Until delivered, it was theirs and they bore the hazards of loss and injury by fires, floods, thefts and otherwise. Moreover, the plaintiff was not bound to accept any deliveries made without orders, except in so far as he waived his rights of election. No letter authorized shipment by such roads or cars, or at such times and in such quantities, as the vendors- might elect, or promised inspection and payment, without delivery on board of cars of roads designated by the vendee, and he designated no road in any of the general letters relied upon. He ordered 150,000 feet of poplar lumber hauled at one time, without any indication of the places of loading or his intention as to the times at which, or the quantities in which, he would take it up and pay for it. He gave the defendants their option to haul some oak lumber. That was no order. He took up and paid for 164,919 feet of poplar, chestnut and oak, a quantity far in excess of any specific orders found in the correspondence. <

Such oral testimony as tends to prove proper verbal orders or demands for lumber, made through Callaway, the plaintiff’s inspector, not honored and filled, is flatly and emphatically denied by Poteet, one of the defendants and manager of the defendant corporation, the Marsh Lumber Company. He swears every proper order was filled and that the company always had ample lumber on hands with which to comply with the requirements of the contract and was ready and willing to do so, not always when ordered, but within extensions of time assented to by the plaintiff. Whether the contrary may be inferred from the correspondence and the repeated general demands and inquiries found in the plaintiff’s letters and the replies thereto, as well as whether Callaway testified truthfully, was a question for the jury. There is nothing legally conclusive in them. - Of course, the plaintiff *661could rightfully make inquiries and there was a moral obligation upon the defendants to answer them frankly and truthfully, but they were devoid of the legal virtue and power to force the defendants to move or to put them in legal default.

Seeing no error in the trial court’s rulings upon instructions and evidence, nor any ground upon which it could rightfully have set • aside the verdict, we will affirm the judgment.

Affirmed.

midpage