History
  • No items yet
midpage
Widmer v. Stamps
663 S.W.2d 875
Tex. App.
1984
Check Treatment

*3 JUNELL, Before ROBERTSON and CANNON, JJ.

OPINION ROBERTSON, Justice. appeal

This is from a entered judgment appellee a concerning favor of in suit of a construction home. While issues complex, themselves are not especially large case has made complex been number of the extent of pleadings, testimo- (in ny pages), excess the number of (38) issues appeal. Basically, appellants’ conten- (1) tions concern the amount entitled to as an offset the contract evidence; price; (2) (3) the state issues; (4) failure to submit conflicts answers; (5) error in awarding rent- al damages; value of home as an element of home 9)failed to find pre- fees and (6) the award work- interest, (7) failure to not judgment manner; manlike We reform the damages. award treble judgment to delete the award of reasonable failed to com- 10) failed to home, rental but otherwise value within reasonable plete the home affirm. time; money not lose 11) appellants did found pertinent on Octo- facts indicate that home; other did on the sale of their parties contract signed ber 1976 the addi- funds for spend additional a home providing would build money loan did lose tional paid for which he would home on value of rental representing or plus his costs lesser of 15% actual built; being of construction The estimated cost time for and the estimated prac- 12) specific five of six acts *4 was months.

completing about, construction six to have occurred inquired tices The interim loan was closed on false, construction to mislead- but none have been com- November 1976. Construction deceptive; or ing July month of following menced the and 13) misrepresent did appellee found moved into the house. appellants services; or materials work They complained appellee about of acts and 14) any find that failed to ap- were yet completed. Appellants an practices constituted unconsciona- closing proved permanent for a loan and a action; of ble action course 1977, then initially August was set for of for 15) fees found reasonable following for the This rescheduled month. attorney; appellants’ did not litigation parties ensued and the of rental value 16) the reasonable found agreement December come a final until time appellants the house from closing permanent 1977 when on $4,200; closing was moved until commitment finally loan held. substantially per- 17) appellee found address properly order contract; formed error, jury: points of we note that taking July home in 18) found that 1) cost to construct the found actual work contract accepted to contract and according house performed appellee; would have agreement parties of and between kitchen 19) found bar $70,000; been good a was not constructed in den 2) profit in con- found the reasonable manner; workmanlike $7,500; struction of house would be utility oven and 20) to find the failed 3) appellee express made an war- found not constructed room wall were all ranty for work under the contract manner; good workmanlike year; for one containing 21) the kitchen cabinets found 4) had a defect in work- found house in a were not constructed stove manship; manner; workmanlike 5) found failed correct appellee given was not 22) appellee failed to defect; cure de- a opportunity reasonable 6) proximate found failure construction; fects appellants; damages cause of written had no 23) appellee failed to find 7) failure to correct to find such mislocation complaint notice area; appel- adversely

the defect affected oven room wall and utility lants; written notice 24) had no appellee found cabinets kitchen repair complaint about 8) cost to found the reasonable stove; $2,500; containing correct defect would 25) argument found had no written notice further this issue As on an complaint about bar contend entitled to between den; price offset the full contract from

kitchen and they performed including value of work 26) money have owed to complete cost and cost supervision, appellee since closing; date of request No issues were correct. 27) found reasonable attorney’s fees for offsets; therefore, appellants ed for these appellee. time complain ap cannot for first peal. through Points of error one five are In points of error through one overruled. five, grouped discussion, for the issue presented is the amount to which appellants next group are entitled as an offset the con complain of the state the evidence. price.

tract Appellants argue the trial numbers six and seven appellants complain court erred in failing to enter a sufficiency take noth evidence to support ing judgment compensate answer of appellee because “he profit. failed to for his The contract ex furnish evidence properly meas pressly provided profit of the lesser of ure the deductions and omissions to be sub 15%or This contract price was evi tracted from the contract price.” This issue dence probative value supporting the is not properly preserved for our considera jury finding. Montclair N. Corp. Earl tion because presented it was never to the Co., Lightfoot Paving Inc., 417 S.W.2d 820 *5 trial court. If it us, were properly before 1967, (Tex.Civ.App.—Houston writ ref’d n.r. we note that while it is true that where the e.). There was additional from testimony performance issue is substantial by the con for both to support jury witnesses sides the tractor, the contractor has the burden “to finding. Even appellants’ expert own wit the furnish evidence to properly measure ness Weeks admitted that the house was the deductions allowable necessary to reme in a good and workmanlike dy defects,” the Bros., Atkinson Jackson except manner for a few which appel items 270 (Tex.Comm’n 848 S.W. App.1931, hold lants installed. We find the evidence suffi ing approved), we do not see how this fact cient and overrule sixth and sev can benefit appellants. Appellants present points enth of error. ed extensive testimony concerning the “de point appel In their tenth of error ductions and omissions to be subtracted lants jury’s attack the to special answer price.” from the contract Only one mone issue No. 8 that the “damages for breach tary damage issue was submitted to the $2,500 the express warranty were is so only jury asking for the sum of money that was against great weight overwhelming the and reasonable as a repair “cost to and correct preponderance of the as evidence the defect in workmanship.” There were unjust.” We manifestly fail to understand no objections to the issue and jury the appellants’ argument throughout their brief answered Appellants complaint $2,500 that jury the as found the was for regard this is without merit. “breach the express warranty.” The is sue read: Appellants argue further it was er What money, any, you

ror to sum of if do find award price the full contract from preponderance of the evidence only by offset the damages the repair would be the reasonable cost to the jury they for what contend was a breach of workmanship? defect in express warranty. we What have said applies above equally to this contention. There no objections were to this issue nor offered; Evidence was the issue was sub were additional requested instructions on jury; jury mitted the the answered the the amount of damages appellants. Evi- issue, and the judgment. court entered The dence was concerning submitted defects in argument is without merit. workmanship and the cost of remedying good in a was constructed the home jury

those and the found some defects manner,” the against great as good and workmanlike performed the work was not overwhelming preponderance weight place We refuse workmanlike manner. not what the this was Again, evidence. that the upon jury the limitation answer it to find that found; jury duty jury It appellants litigants do. is the in a and work- was not constructed jury pre- to isolate the issues discussion The same manlike manner. appellate serve the so court can record of error. point to this applies made above appellants any If had pass upon issues. and, obviously, conflicting issue, The evidence they should objection special appellee’s much of jury chose believe trial; it have it at cannot make made quality the issue concerning However, evidence appeal. for the first time on say simply cannot We of construction. $2,500 insufficient, attacking the award as favorably their failure evi- they presented maintain thir- Point of error evidence. weight of the $5,890 $6,290 damages, of which dence is teen overruled. we they claim was not rebutted. While that the amount was question the assertion fourteen, fif rebutted, evidence, even if uncon- com teen, and nineteen eighteen troverted, binding jury. was not issues answers plain jury Co., 142 Tex. Coxson v. Atlanta. Life Ins. practices trade concerning deceptive (1944). The S.W.2d overwhelming weight and great testimony ap- was free to disbelieve the We decline evidence. preponderance expert. The award of pellants’ jury’s have as appellants these issues to address weight is so great 418(e) failing violated Tex.R.Civ.P. overwhelming ev- preponderance Appellants’ issues. properly brief these manifestly unjust. Appel- idence to be assertions factual bold continually make tenth of error is overruled. lants’ record. to the citation any without 911 pages is in this case facts Point of error eleven attacks statement of This court are 111 exhibits. jury’s long answer to issue No. 31 “that and there *6 record the to search utility the room wall was constructed in a is not required un position appellants’ and manner.” This is good supporting workmanlike evidence error, and in this found; of points failed to jury jury particular not what the the der These points in we to so search. good find that it was constructed a case refuse not merely This are and workmanlike manner. overruled. to meet their bur appellants

means failed sev and Points of error sixteen However, will of the we proving den fact. other answers to jury’s the enteen attack as a contest construe contention al concerning issues parts special the being to find jury to the failure of the so as Trade Deceptive the leged violations overwhelming great weight the and the had (DTPA). Appellants Practices Act evidence, preponderance proper thus the elements to establish all of proof burden finding Prun ly invoking powers. our fact appel In sixteen their claims. DTPA Bank, (Tex. v. Post ty Oak S.W.2d 645 appel- that answer jury’s the argue lants Civ.App. Dist.], 1973, writ [14th — Houston would house that the “representation lee’s evidence, n.r.e.). Looking ref’d to all the workmanlike good in a and constructed be have say may we cannot that since the wall false, misleading or a manner ... was not at with been constructed in dimensions odds against the practice, is so or deceptive act jury the desires of therefore a overwhelming preponder and great weight was not constructed in finding that the wall manifestly be of the evidence ance was re good a manner and workmanlike fail to understand unjust.” We overruled. This of error is quired. jury found complaint. While the (to in a be built representation attacks the made the of error thirteen Point manner) they failed 9, “that workmanlike good issue No. and jury’s special answer favorably above, and answered issue, jury find mitted to the in as discussed another not have de Alamo, the a the answers would that house was not constructed in recover the sum good right and workmanlike manner. The an- feated Moulton’s swers are consistent and since we overruled in to issue No. jury answer by found the thirteen, point of error error six- point of was correct We believe the trial court 45.” teen is appel- without merit. In seventeen instruc requested denying appellants’ argue jury’s lants appellees answer that relating and issues to failure tions “representations adequate, competent that if the issue of failure consideration. Even qualified and supervision provided would be have been could be said to consideration false, ... was not a misleading deceptive consent, “the substance by tried we believe or practice, act is so against great issues was substan requested each weight and overwhelming preponderance of tially submitted in other issues contained the evidence as unjust.” manifestly Miller, charge.” main Cree v. court’s Again, jury found the representations 255 S.W.2d (T ex.Civ.App.—Eastland made, to have been but find failed to n.r.e.). writ ref’d Points error representations false, misleading, etc. eight and nine are overruled. The evidence conflicting, was and as we Next, discussion, grouped for are read the answers are all consistent. contending of error irreconcilable We say cannot answers are point of jury conflict in answers. In error great weight of the evidence. Points of jury twelve assert conflict in an error sixteen and seventeen are overruled. 9, 30, swers to and 32. special issues Nos. In points eight and jury answer No. 19 nine, discussion, grouped for appellants con that in a house was constructed tend the trial court refusing erred in good Appel and workmanlike manner. submit their jury issues on failure consid a argument finding lants’ that this is that eration. Failure of is an consideration af good the home constructed firmative defense which must be raised workmanlike manner has been re already verified pleading. 93(j), Tex.R.Civ.P. 94. jected. jury issue No. 30 Failure of plead. consideration was not bar between the kitchen den While it might be said the issue was tried work by consent we would not be comfortable in manlike manner and in No. 32 so holding. The evidence adduced at trial kitchen cabinets the stove were containing which could be said relate to the issue of not so constructed. There is no conflict failure of consideration relates much more between answers. These points are directly to issues raised the pleadings overruled. already submitted to the other *7 special issues. Examples include substan In error point twenty appellants of performance tial and most of the issues special contend that the answer to issue No. relating allegations to under the DPTA. In 18 in jury where the to find that cer the leading subject case on this Moulton v. tain acts “false, which occurred were a mis Alamo Inc., Ambulance Service, 414 S.W.2d leading deceptive practice” is in irreconcil (Tex.1967), 444 the Supreme Texas Court able conflict with their answers to issues No. expressed its proce dissatisfaction with the 30 and 32 above. We to fol discussed fail dure of including issues pertaining logic low and cannot discern to an affirmative defense when such issues error twenty conflict. Points of twelve and have already been submitted in another are overruled. form. remarked, As the court the result Next, would be proliferation grouped “a for are issues in discussion an area already mired in a three error prolixity contending it was to complicated $4,200 issues.” Id. at 448. The court award as reasonable rental further commented at 449 “it is obvious the constructed home from date ap that had the requested pellants issues been sub moved in until the date of closing.

882 31, 8, 1977 to December July house from challenges our consideration of Appellee this contention presented is in 1978. While this contention for failure of appel points, only three we need sustain error particular attention to the direct our point twenty-one. lants’ of error we it sufficiently but believe is upon, relied review. Both designated authorize our attorney’s The next issue concerns fees. the Texas Court parties agree Supreme that point twenty-four, In case, Smith, 624 Baldwin 586 S.W.2d failure to enter complain of the trial court’s on other (Tex.Civ.App. Tyler), rev’d — in favor for the amount judgment their (Tex.1981), is the 611 611 grounds, S.W.2d jury. by such fees as found Appellee on this issue. ar controlling case express an breached had us gues requires uphold that Smith the DTPA. a violation warranty, argue Appellants court’s award. that trial will we assume discussing this result is due to the contrary required $2,500 was at jury’s award of agree We distinguishable facts of Smith. express of an “breach part least warranty.” Appellants Smith, the contract appellants. with acknowledge that $31,300. price was fixed at The house art. applying TEX.REV.CIV.STAT.ANN. be on or before question was to courts (Vernon Supp.1982-1983), 29, 1977, 9, January 1977. On March un fees attorney’s award have refused to purchaser and the complete house was 98% recovery. They has a net party less the in with the builder’s moved his furniture not be rule should however, the same argue, occupan physical March 12 permission. On the DTPA because under applied to claims although began. The that cy jury found provides specifically 17.44 thereof Section substantially performed, builder had the there were defects in need act are to of the purposes the underlying repair false, mislead consumers “protect period amounting During un practices, business ing, deceptive 1978, 28,1977 February until from March the war breaches conscionable actions prohibited by purchaser builder economi efficient and ranty provide except for a going premises from on the Fur action.” procedures cal ther, to secure through from November 8 thirty day period December offset and an permit “to they say, judge when the trial decisions the rationale then follow to vacate enable purchaser ordered corrections to (appellants) deny 2226 and under Article be made. The builder had de would fees attorney’s recovery of fi agreed pay interest on interim cit purposes,” underlying feat the DTPA’s paid but the nancing, purchaser actually Brumlow, 630 S.W.2d 1982, ing Guerra v. $2,900 financing interest. The in interim writ). no Antonio (Tex.App. — San purchaser court allowed the to be supreme Guerra that since (There held the court $2,900 expended plus for the reimbursed trade deceptive of his on one recovered damages, required but was not claims, though he practice even against the reasonable amount be offset neverthe recovery, he was a net awarded This result of the house. is rental value of his portion recover a less entitled to the builder’s given the fact that justified respect due fees.) With all attorney’s interest it financing for interim liability Court, we Antonio opinion San move purchaser would be unfair disagree. respectfully running completion up thus prevent in and the re authorizing price on a fixed contract Article the builder’s cost the “Act fees, provides could be ob permanent financing covery since its to promote complete. liberally until construction was construed shall tained Appellees that out pointed us to hold As purposes.” would have read Smith underlying expressly likewise buyer pay law a must the DTPA a matter of appellants, *8 construction, but Sec if moves in before provides contractor rent he for a liberal the permanent financing ques the time in 17.50(b)(in is We do effect at obtained. tion such recovery In the broadly. tion) authorizing the case so case in not read con $4,029.86 actions, provided “each us, in inter appellants paid before in DTPA fees costs may court prevails of the construction obtain part im interest as sumer who and (There attorney’s is (reasonable) that to fees.” permit We believe cost. wording for the reasonable rental difference meaningful further recover no statute.) Upon allow provision present the house would effect in the value of recovery this two in the strikingly sustained. Thus so similar damages wording statutes, be the same rule should the trial court committed error we believe we hold $4,200 We therefore the rental value of the under both statutes. awarding applied as of action the that in DTPA cause shall recover judgment, party hold original (as consumers) were not entitled shall court but higher the the costs attorney’s they pre- recover fees unless of the court be- pay costs adjudged low ” vailed, be- they prevail and that did not Accordingly, appeal costs of this .... cause were not awarded a net recov- against appellee. are adjudged twenty-fourth is ery. Appellants’ overruled. point is rehearing motion for over- Appellants’ ruled. twenty-five Point of error asserts awarding in the fees to error Appellee was to attor entitled appellee. pursuant to TEX.REV.CIV. fees ney’s 2226, (Vernon arts. 5472d STAT.ANN. twenty- Point of Supp.1982-1983). error is overruled. five PARTIN, ux., Appellants, et C.H. of error twenty-eight ap v. pellants assert error the trial court’s fail ure to award them treble damages. HOLDEN, al., Appellees. et Zula rule is well established that absent a net No. 13811. recovery in favor appellants are not entitled to treble damages. Durham St. Texas, Appeals of Court of John, (Tex.1983). 645 S.W.2d 261 Point Austin. error twenty-eight is overruled. Dec. 1983. Point of error twenty-six twen ty-seven concern the prejudgment award of interest and the denial of same

to appellants. Since have suf fered a net judgment them, trial court was correct in awarding prejudg ment interest to appellee. Black Pipe Lake Line Co., Co. v. Inc., Union Const. S.W.2d 96 (Tex.1976). Appellants’ points of error twenty-six and twenty-seven

are overruled. The judgment is reformed to delete therefrom the award to appellee of value, reformed, rental and as so is affirmed.

OPINION ON APPELLANTS’ MOTION

FOR REHEARING discussing appellants’ eighth and ninth

points of original error our opinion, we stated that failure of consideration was not pled. is While issue not crucial to the these disposition points, what we intend- toed was that failure say of consideration not properly pled pleading since such not verified required by affidavit 93(j). Tex.R.Civ.P. Appellants further contend we were in assessing appeal error in the costs agree. We apply them. We

provisions pro- of Tex.R.Civ.P. 139 which appealed, court judg- a case is if the against vide “When *9 higher ment of the but for less amount than the appellant,

Case Details

Case Name: Widmer v. Stamps
Court Name: Court of Appeals of Texas
Date Published: Jan 12, 1984
Citation: 663 S.W.2d 875
Docket Number: C14-82-429CV
Court Abbreviation: Tex. App.
AI-generated responses must be verified and are not legal advice.