83 Mich. 241 | Mich. | 1890
This cause was commenced in justice’s ■court in the city of Detroit, where plaintiff had judgment for $88.82. The plaintiff declared in an action of assumpsit, and filed the following bill of particulars:
Balance due on contract for building house.........$60 00
Extra door............................-............. 8 00
Glass for extra door................................ 3 00
Two drawers, at $2.00 each________________________ 4 00
28 feet sidewalk.................................... 8 00
■6 feet sidewalk to house............................ 2 00
Two extra windows and glass...................... 12 00
Total........................................... $97 00
The defendant pleaded the general issue, gave notice of recoupment, and filed a bill of particulars as follows:
“Please take notice that the following is a bill of particulars of ■our claim for recoupment in this case, and for which we will claim damages on the trial:
For failure to put tar paper on the outside of the house, under the siding, as required by the contract ____________________________________________ $100 00
For failure to properly complete the oil finish on the interior of the house------------------------ 25 00
Total____________________________________— - $125 00”
From this judgment defendant appealed to the circuit court for Wayne county, where the cause was tried before a jury, and verdict and judgment passed for the plaintiff in the sum of $64.59. Defendant brings error.
The assignments of error all relate to the 'refusal of the court to charge as requested by defendant, and the charge of the court as given. The defendant, at the
l£l. If you find from the evidence that, at the time the defendant paid the plaintiff the three hundred and fifty dollars, the plaintiff agreed to come back and put on another coat of oil finish, and then was to be paid the remaining sixty dollars due on the original contract, these facts constitute in law a new contract; and if you also find that the plaintiff did not return and perform said work, then your verdict must be for the defendant.
“2. If you believe from the evidence that the plaintiff did not complete the house according to the contract, then you must deduct from the claim of the plaintiff the amount necessary to put the house in the condition required by the contract.
££ 3. If -you believe from the evidence that it will cost more to put the house in the condition called for by the contract than is due the plaintiff on the original contract, then you should render a verdict for the defendant for the amount necessary over and above the plaintiff’s claim.
££4. The defendant did not waive his right, to insist upon the completion of the house by taking possession of it.
“5. If you believe from the evidence that the defendant did not order the sidewalk built, then the plaintiff cannot recover for it.
££6. If you believe from the evidence that the plaintiff made the drawers charged for in his bill at the request of the defendant’s wife, then the defendant cannot be made to pay for them.
££ 7. If you believe from the evidence that the plans and specifications called for the two windows charged for in plaintiff’s bill of extras, then he cannot claim extra pay for them.
££ 8. If you believe from the evidence that there was a condition in the plans and specifications that the defendant was not to be charged for any extras, then he cannot be" made to pay for any whatever.”
It is claimed by the counsel for the defendant that none of these requests were given by the court, but, on a careful reading of the chaz’ge, it appears that each was
Counsel for defendant cites several cases from this Court which he claims bear him out in this assertion, but in this counsel is in error.
“ If the plaintiff was required to put three coats of oil finish, on the inside of the house, and three coats of oil finish were put on the inside of that house, and the work was done properly, the promise of the plaintiff to put on .another coat would be a mere gratuity, and without consideration, and his" failure, when he discovered that there were already three coats put on, to put on an additional ■coat, would not preclude him from the right to the full amount due under the contract.”
The other questions raised under the charge of the court, as given, are purely questions of fact. The court very fully and fairly submitted the claims of the respective parties. The jury were specifically instructed that, if the plaintiff failed to complete his contract according to the specifications, the defendant would be entitled to recoup his damages.
"We find no error in the record, and the judgment must ■be affirmed, with costs.
Ortman v. Green, 26 Mich. 209; Compton v. Blair, 27 Id. 397; Spicer v. Earl, 41 Id. 191; Goebel v. Linn, 47 Id. 489; Edwards v. Nelson, 51 Id. 121; Conkling v. Tuttle, 52 Id. 630.
Counsel for plaintiff cited, in support of this proposition, Vanderbilt v. Schreyer, 91 N. Y. 392.