13 Or. 546 | Or. | 1886
This appeal is from a decree rendered in a suit brought by the appellant to establish and foreclose a mechanic’s lien under the act of 1874, to provide for liens of mechanics, etc. The suit was against the respondent and one C. O. Blakely.
It is alleged in the appellant’s complaint that said Blakely, on the twenty-eighth day of August, 1884, entered into a contract with the respondent to construct for the latter a certain building on lots 5 and 6 in block 82 in the city of East Portland, which lots are at the north-west corner of Fourth and L streets in said city; that by the terms of the contract, Blakely was to furnish the material and construct the building in accordance with certain plans and specifications, and that the respondent was to pay him therefor in installments upon the completion of specified portions of the work; that the appellants, as material-men, sold to said Blakely for the building, and which was used in its construction, glass of the value of $428.72, which the latter agreed to pay; that by the terms of the original contract a certain payment of $1,512.50 was to be made to the said contractor, Blakely, when the finishing coat of mortar should be put on, and the cornices, cementing, and plumbing done; that said portion of said work was duly completed according to the provisions of said original contract, and duly accepted as such by said respondent, on the four
It appears from the testimony that the said written notice of the appellants’ claim was as follows:
Portland, Oregon, January 7, 1885.
To Mr. Charles Logus.
We hereby give you notice that' Mr. C. O. Blakely of East Portland, Oregon, has purchased of us material to the value of $428.78 for use in the construction of your building on the corner of L and Fourth streets in said city of East Portland, and that said amount is due and unpaid, and we hold you responsible for said amount.
Respectfully yours,
Whittier, Fuller, & Co.
By C. A. Plummer, Attorney in Fact.
This notice was served upon the respondent on the ninth day of January, 1885, after the appellants had made out and delivered a bill of the account to Blakeley and demanded payment thereof from him. It further appears from said testimony that the architect for the said building, on the tenth day of January, 1885, made out and issued a certificate which entitled the contractor Blakely to the said sum of $1,512.50, and accepted the portion of the work to be completed under the contract entitling the said contractor to such payment. The following is a copy of the said certificate:
To Charles Logus, Esq.
I hereby certify that Mr. C. O. Blakely, contractor, is entitled to the sum of $1,512.50, being fourth advance on account of contract for Logus Block, East Portland.
$1,512.50. . Otto Klumann, Architect.
The following indorsements appeared on the said certificate:
Received payment for above as following:
Per order of H. H. Hogue . . $500
Per order of W. H. Moore . . 565
Note of Charles Logus . . 400
$1,465
Balance per cash, $57.
Balance, $47.50.
And below was written the name C. O. Blakely. It also appears from the testimony that the appellants delivered the said material to said contractor, as alleged in their complaint, and that no part of the claim had- been paid; and it further appears therefrom that some time-after the ninth day of January, 1885, the respondent paid to the said contractor the sum .of $360.
The respondent was a witness in the case, and testified upon his cross-examination that the indorsements upon the said certificates were placed there by the architect Klumann, on the fourteenth day of January, 1885,. and that the name C. O. Blakely was subsequently signed thereto. It further appears from the said testimony that on said fourteenth day of January, 1885, said contractor quit work upon said building, claiming that he-was forced to abandon the contract by the respondent’s refusal to make advances in accordance with its terms:, that while he worked upon the same he pushed it vigorously.
The contract of August 28,; 1884, provided that the work of building said structure should be completed on or before the fifteenth day of November, 1884; that the said contractor should furnish all the materials therefor, and that each of the payments, except the final one, should only be considered as advances on account, and not as an acceptance of the work done or material supplied, and that they should only be made upon the presentation to the owner by the contractor of a written
The appellants on the trial introduced in evidence a duly certified copy of a notice of lien, in accordance with the provisions of said act of 1874, which was filed in the office of the clerk of the county of Multnomah on the fourth day of March, 1885, one month after the commencement of the suit, and about twelve or thirteen days after the building was furnished. ' The question to be determined herein is, whether the appellants had a lien either upon the fund or the property of the respondent. It is claimed by the respondent’s counsel that the appellants had no lien upon either, upon the grounds that the notice served upon the respondent was not in accordance with the requirements of the mechanic’s lien act referred to; that it could not have been upon the fund, as it was not paid over to the county clerk as provided by said act, and that it did not exist against the building and land upon which it was situated, for the reason that it depended upon the lien of the contractor, and that his lien failed in consequence of his abandoning the work; and further, that appellants’ suit to foreclose their pretended lien was prematurely commenced.
The appellants’ right and remedy in the premises being both statutory, a resort must be had to that source of law to -ascertain their nature and extent. The first section
Under these various provisions of the act, the appellants insist that their claim became a lien upon the building erected, and that they have the right to enforce it against the fund arising out of the said installment or against the premises. The prayer of their complaint was for a judgment against the defendants in the suit, and that their lien against said fund in the hands of the respondent be enforced, and for general relief.
By the language of said section 4, it might be inferred that the payment or deposit of the said installment due by the employer was peremptorily required, but upon a close examination of all the sections referred to, it will, I think, be observed that such payment or deposit was only intended as a privilege to the employer, and that by making them he would be able to discharge pro tanto the lien given by the first section of the act, and that it was optional upon his part whether he would pursue that course or not. There can be no question that the appellants acquired a lien upon the building and premises Avhen they furnished the said material, provided they gave the notice required by the provisions of said act. The first section secured a lien to the original contractor for theAVork and labor done and the materials furnished by him in the construction of the building, and the contract he made with the respondent to construct it inured to the benefit of the appellants, and secured a lien in their favor whenever they gave the written notice referred. to, if it conformed to the said provisions. The provisions of said section 5 cannot be construed. in any other
It becomes important, then, to consider whether the said written notice of January 7, 1885, is such a one as provided for in section 4 of the act. The respondent’s counsel contend that it is not, that it is defective in form and substance; that it does not contain the words “over and above all payments or offsets.” But I do not think the statute necessarily requires that those words should be inserted in the notice. It says that a notice shall be given of the amount of the claim over and above all payments or offsets. And I would suppose that if the claimant had done so in fact, it would answer the requirement. Section 7 of the act, as has been shown, makes the presentment of a false claim in such a case, or the willful omission to allow all credits which may be justly allowable, a ground of forfeiture of the lien. The fact whether a claim is false or true must be ascertained by proof. The claimant’s saying it was true does not make it so, nor, in this case would it make the matter more certain. The appellants say by the notice that the contractor had purchased of them material to the value of $428.78 and that said amount was due and unpaid. What stronger assurance could they have given him of the amount of their claim than this, aside from actual proof? The respondent had ample opportunity to verify the claim. He had only to inquire of the contractor, who alone was interested in the matter. It made no difference with the respondent how much the claim was, his liability was limited to the contract price of the construction of the building.
Again, the amount of the claim as stated in the notice was the amount as established by the proof. It wás
The appellants having, under the facts and circumstances before referred to, acquired the character of lien described, it only remains to be determined whether or not they have lost it. The respondent’s counsel make the following points upon the question, viz.: “That the contractor must perform his contract, or there must be some act of the owner preventing the performance, amounting to a breach of it.” But in this case, the contractor had not, when the appellant’s lien attached, broken his contract. Nor did he ever break the contract for the performance of the specific work, for the completion of which the appellants furnished the material. At that time it was subsisting. The appellant’s lien had attached and the contractor’s subsequent acts could not divest them of their rights. In Shaver v. Murdock, 36 Cal. 298, a case wherein the owner and contractor had made a subsequent contract affecting the rights of the subcontractors, Judge Sprague, in delivering the opinion of the court, says: “And the parties to such contract, as well the owner as the original contractor, are equally presumed and bound to know that, with reference to the entire work embraced in the original contract, persons occupying thereto the relation of subcontractors, laborers, or material-men, possess an interest in the money to become due the original contractor from the owner under such contract; with the right and privilege, under the statute, of securing and enforcing a lien upon the structure and premises to the extent of such interest, which no subsequent agreement or acts of the parties to the original contract can, without timely notice to or consent of such third parties, impair or divest.” The theory that the failure of an
The next point taken by the respondent’s counsel is, that the suit was premature, for the reason, they say, ■that the contract must be completed before it can be maintained, etc. What has already been said upon the former point will apply to this as well. The two are, in fact, the same. The proposition is correct when rightly applied. If the contract for the construction of the building is entire and incomplete, the lien will not mature until its completion. So also if the contract of the laborer or material-man is incomplete, it will not mature. Had the appellants made a contract to deliver material, they could not rightfully have claimed the benefit of a
Some objections have been made to the accounts filed by the appellants with the clerk of the county, under section 18 of the act. It is claimed that there is a misdescription of the property, and that the account was filed after the commencement of the suit. I think, upon an inspection of the account, it will be seen that the property is described with sufficient certainty. That it was filed after the complaint in the suit was filed, there can be no objection. The appellant’s lien accrued by the delivery of the material and' service of the notice of claim. In order, however, to prevent the lien from lapsing, the appellants were required by said section 18 of the act to file such an account. The compliance with that provision did not establish the lien. It merely continued it and kept it alive. The language of the section indicates that beyond question. “ Every subcontractor, etc., who shall' acquire any lien, etc., shall, etc., .... and in default thereof, shall lose his lien.” This is the substance of the requirement, and it is to be performed within thirty days after the completion of the structure, whereas the suit provided by section 10 of the act may be commenced whenever the original contractor (employer) or his assigns shall fail or refuse to make such payment or deposit as is provided by section 4. The labor may have been performed, or the material furnished, and generally is, upon the faith of the installment to become due; and it would do violence to the language of the act to hold that his lien depended upon the completion of the entire edifice, or that its enforcement was