2 Kan. App. 704 | Kan. Ct. App. | 1896
The opinion of the court was delivered by
In 1888 the firm of Torrence & Kenyon entered into a contract with the First National Bank of Seneca, Kan., to erect a two-story brick building on certain premises owned by the bank. At about the same time said firm employed P. D. Kenyon to superintend the construction and purchase material for the erection of said building ; they also entered into a contract with the Whittaker Brick Company to furnish the brick for this building. P. D. Kenyon performed all the conditions of his contract, as well as did the Whittaker Brick Company; but Torrence & Kenyon failed to pay these parties the amounts they had agreed upon, and on the 19th of August, 1889, they each filed their subcontractor’s statement for a lien.
On the 20th of February, 1890, P. D. Kenyon com
As stated by the plaintiff in error, the facts in this case are not identical with those in Groesbeck v. Barger, 1 Kan. App. 61, yet the question involved is the same, viz., the application of the several lien laws of this state to the lien claimed by plaintiff in error. Upon the authority of that case, the decision and judgment of the trial court must be affirmed. As held therein, the right to a lien must be determined by the law which was in force at the time the material was furnished — that is, the act of 1872 ; but the time within which the statement should be filed to obtain a lien must be governed by the law of 1889, which took effect March 1, 1889. As the last materials were furnished more than 60 days prior to the taking effect of the law of 1889, and the building was completed thereafter, such a construction must be placed upon the
The judgment will be affirmed.