Whiteside v. Lebcher

7 Mont. 473 | Mont. | 1888

Galbraith,- J.

This was an action brought by the appellants to enforce a mechanic’s lien against the property of the respondent. They were the subcontractors of one Greenwood, who had a contract with the respondent for the construction of the building against which, as well as the premises on which it was built, the lien was sought to be enforced. The cause was tried by the court sitting without a jury. The court made and filed its findings of fact and conclusions of law, and upon these rendered judgment for the appellants, and decreed that it should be a lien upon the property described in the complaint. There was a motion for a new trial, which was by the court sustained. From the order sustaining this motion this appeal is taken.

For any of the causes mentioned in the statute, which materially affected the substantial rights of the respondent, a new trial should be granted. Several of these causes are urged by the respondent; but if it shall appear that any one of them is such a cause, the order of the court granting a new trial should be sustained. One of these is, substantially, “ insufficiency of the evidence to support the verdict or decision.” It is urged by the respondent, in support of the court’s action, that one of the findings of fact made by the court, which was material to the issue, is not supported by any evidence. This finding is as follows: “7. That on or about October 7, 1885, and just previous to furnishing certain lumber and materials to be used in said building, to the amount and value of $631, plaintiffs notified said Chester B. Lebcher of their intention to furnish the same, and of the probable-value thereof, to wit, $631; and that said *476Chester B. Lebcher then and there provided that he would .see plaintiffs paid for the same; and that thereafter plaintiffs furnished lumber and materials to the amount of and value of $631.34, and the same were used in the construction of the said building.” The mechanic’s lien law relating to this subject, and in force at the time of the transaction in controversy, was as follows: “Every subcontractor wishing to avail himself of the benefits of this chapter shall give notice to the owner or proprietor, or his agent or trustee, before or at the time he furnishes any of the things aforesaid, or performs any of the labor, of his intention to furnish or perform the same, and the probable value thereof.” Rev. Stats. Mont., div. 5, sec. 821. “And the employer shall become surety of the contractor to the subcontractor for the amount due for such work and labor or things, not, however, exceeding the value thereof as notified under section 821.” Rev. Stats., div. 5, sec. 823. It was essential, under these provisions of the statute, that the respondent should have been notified, before or at the time the materials were being furnished, of the probable value thereof, and a certain sum as the probable value thereof then specified. This sum must be shown by the testimony. It is not sufficient that the evidence should merely show that the respondent was notified of the “ probable value ” of the materials, without also proving the amount of such value. This requirement of the statute must be strictly complied with in order to entitle the subcontractor to his lien. These two provisions explain each other. The latter certainly contemplates that a sum certain is meant in the first provision; for its language is, “not, however, exceeding the value thereof as notified under section 821.”

That a notification that the value of the materials is a certain specific sum was intended, is apparent when *477we consider that under these provisions the subcontractor is not entitled to a lien in excess of the “ value as notified under section 821.” But it seems to us that it is apparent that the proper construction of the above provision from section 821 is that a sum certain should be proved without reference to the context. The words “ probable value ” mean that the employer should be notified of some particular sum, approximating the value of the materials, above which he is not entitled to a lien. Of course, the intention of the legislature is more apparent when the two provisions are construed together. We have examined the testimony contained in the record, and the following is all thereof relating to this subject: Fred Whiteside, one of the appellants, testified as follows: I told him we were furnishing the materials, and about the value of them.” A. L. Peters, a witness for the appellants, testified on direct examination: “Pie also gave him the amount then due, and the probable cost of that still to be furnished”; and on cross-examination: “I do not remember the figures plaintiff gave defendant for probable value; I do not know that he stated any amount.” Chester B. Lebcher, the respondent, testified: “ Question. Did either of the plaintiffs ever state to you the probable value of the materials to he furnished to Greenwood, the contractor, for the building in question? Answer. No, sir.” There is no testimony tending to show that the respondent was notified of any particular sum at which the materials were valued, as required by law. The above finding of fact is therefore not sustained by the evidence, and upon this ground alone the court properly granted a new trial.

It is urged, also, by the respondent in his brief, that he complaint is insufficient, and does not state facts sufficient to support the judgment, because it contains no allegation that the appellants notified the respondent of the particular sum at which the materials were valued, *478before or at the time of furnishing them, as required by law. The objection that the complaint does not support the judgment may be raised for the first time in this court. This is substantially the same objection which is made to the foregoing finding of fact by the court. In this respect the complaint is deficient. This is one of the allegations which the complaint should contain to warrant the enforcement of the lien; and in this particular the complaint does not support the judgment.

Other reasons are urged by the respondent to sustain the action of the court in granting a new trial; but in view of the foregoing causes, we think that the motion for a new trial was properly granted, and it is unnecessary to enter upon their consideration. There is an objection, however, to the sufficiency of the description of the property against which the lien is sought to be enforced, contained in the notice of lien, which we will briefly notice. The description is as follows: “The building hereinafter described, which said debt is claimed to be a lien against the said building, and the lot of ground upon which said building was erected and now stands; that said lot is known and described as lot 8 in block 32 of the town of Miles City, county and territory aforesaid, as platted and filed for record in the office of the recorder of deeds of said county and territory.” This description, for the purposes of this action, we deem sufficient. The premises on which the building is erected is sufficiently described; and as long as the building remains thereon, and there is nothing in the record to indicate the contrary, it also is sufficiently identified.

' The order granting a new trial is affirmed, and the cause remanded.

Judgment affirmed.

McConnell, C. J., and McLeary, J., concur.