White Knight Development, LLC v. Dick B. Simmons, Sr., and Julie M. SimmonsWhite Knight Development, LLC v. Dick B. Simmons, Sr., and Julie M. Simmons
It is black-letter law that specific performance is an equitable alternative to legal damages. That is, a court may fashion a remedy including one or the other but not both. In this case, one party to a contract for the sale of real property breached, and the other sought specific performance and various categories of damages. The question we must answer is whether the trial court erred by awarding specific performance and a monetary award it described as “actual damages/consequential damages” related to the delay in performance. It did, in part.
We hold that, while an award of specific performance usually precludes a monetary award, there is a narrow set of circumstances in which a breach of a contract for the sale of real property may be remedied by specific performance and a monetary award of reasonable, foreseeable expenses directly traceable to the delay in performance and, in cases where the purchaser breaches, incurred in connection with the seller‘s care and custody of the property during such delay. This monetary award is an equitable one, the purpose of which is to restore the party seeking specific performance to the position it would have occupied had the other party‘s performance been timely by reimbursing it for property-related expenses incurred as a direct result of the delay between the time of the breach and the time of judgment. The court of appeals erred by deleting the judgment‘s monetary award entirely without distinguishing recoverable expenses from those that were unrecoverable because they were insufficiently tethered to the subject property and the delay in performance. Accordingly, we reverse the court of appeals’ judgment in part and remand the case for that court to review the monetary award consistent with the principles we announce today.
I. Background
In 2015, White Knight Development, LLC executed a contract to purchase land in a Bryan subdivision from Dick and Julie Simmons for $400,000. The property had been subdivided subject to restrictions, including set-back requirements, and residents voted to extend the restrictions, such that they would be effective until January 1, 2016, with the potential to extend them further if residents voted accordingly by January 1, 2018.
White Knight became concerned that the restrictions could interfere with its plan to develop the property. So the parties agreed to amend the contract to include a “buy-back” provision, giving White Knight the option to require the Simmonses to repurchase the property if residents again voted to extend the restrictions. It provides:
2. “Buy Back” agreement. In return for valuable consideration, Seller agrees that if any of the Restriction concerns . . . are reinstated at any time prior to January 1, 2018, Buyer has the option (but not the obligation) to demand that Seller repurchase the Property. If Buyer exercises this option, Seller shall be required to repurchase the Property for the purchase price stated in the Sale Contract, minus any unpaid balance owed by Buyer under its promissory note with Seller within a 45 day period after this “Buy Back” agreement is requested to be executed.
The sale closed in May 2016, with White Knight paying the $400,000 purchase price in exchange for the property deed.
White Knight sued for breach of contract and fraudulent inducement of a real estate contract (and other theories), seeking both specific performance of the buy-back provision and “damages incurred as a result of [the Simmonses‘] conduct, including but not limited to, fees charged by banks or other financial institutions (including extension fees), taxes, interests, and other costs.” The Simmonses responded that a condition precedent to the buy-back provision—extension of the property restrictions—never occurred because those restrictions had expired. They counterclaimed for a declaration that the restrictions are invalid.
The case was tried to the bench. White Knight presented evidence that it suffered financial setbacks it attributed to the Simmonses’ breach. It originally financed its purchase of the Simmons property with a loan from MidSouth Bank. After the Simmonses refused to repurchase, White Knight defaulted on the MidSouth loan and paid a forbearance fee to avoid foreclosure. It took out a second loan to pay MidSouth, using the Simmons property and an unrelated property as collateral. After defaulting on the second loan, White Knight took out a third loan to refinance the unrelated property and pay off the note on the Simmons property. White Knight later transferred title in the unrelated property to the second lender to avoid foreclosure. All throughout, it paid property taxes and loan interest using a company credit card. There was testimony that “White Knight‘s business essentially has come to a screeching halt” and the company is no longer functioning “in any capacity.”
The trial court found the Simmonses breached the contract. In so doing, it concluded that the Simmonses were precluded from asserting there were no valid restrictions on the property under the doctrine of quasi-estoppel. The trial court awarded White Knight specific performance of the buy-back provision, ordering the Simmonses to repurchase the property for $400,000. It also awarded White Knight $308,136.14 in “[a]dditional actual damages/consequential damages” for various costs incurred during the three-and-a-half year period from the date of breach (December 23, 2017) to trial.1 It itemized the monetary award in its findings of fact and conclusions of law:
- $103,667.73 for expenses “related to” the Simmons property, including property taxes, forbearance and refinancing fees, and interest payments for the MidSouth loan and the two other loans it acquired to avoid defaulting on the MidSouth loan;
- $45,619.83 for property taxes owed in 2020 ($4,862.23 for the Simmons property and the rest for other properties);
- $8,211.57 in penalties related to past due property taxes for 2020 ($875.20 for the Simmons property and the rest for other
properties); - $59,318.00 in “operating loan interest” for White Knight “to continue business“;
- $74,802.00 in “loan interest related to another property that had to be refinanced to avoid foreclosure of the Simmons property; and
- $16,518.00 in “credit card interest” for White Knight to “continue business.”
The trial court found that—due to the Simmonses’ breach—White Knight had to extend its financing with MidSouth Bank, pay a forbearance fee to avoid foreclosure, and secure financing from additional lenders. Finally, it found that White Knight‘s “credit was
damaged” and it “suffered significant additional expenses due to other projects that were not able to be completed due to continued expenses.”
Both parties appealed. White Knight contended that the trial court erred by not finding in White Knight‘s favor on its fraud claim, which was not addressed in the trial court‘s judgment. The Simmonses presented several issues, including a challenge to the quasi-estoppel finding and the awards of both specific performance and damages.
The court of appeals modified the judgment to delete the $308,136.14 monetary award but otherwise affirmed. 703 S.W.3d 136, 150 (Tex. App.—Waco 2023). The court acknowledged a principle we embrace today: that monetary compensation may be awarded alongside an award of specific performance “in narrow circumstances—when it is deemed necessary to place the parties in the same position as if the contract had been performed.” Id. at 149 (quoting Davis v. Luby, No. 04-09-00662-CV, 2010 WL 3160000, at *4 (Tex. App.—San Antonio Aug. 11, 2010, no pet.)). But the court of appeals then went in search of an express statement by the trial court that the monetary award was equitable in nature. Finding none, it concluded that White Knight was not permitted to “receive relief in the form of specific performance of the contract and then also receive damages for its breach.” Id.; see also id. (finding noteworthy the absence of any “indication in the findings or judgment that the amounts the trial court awarded to White Knight were to adjust the equities so that the parties were put in the position in which they would have been had the transaction been closed as contemplated“).
We granted White Knight‘s petition for review.2
II. Relevant Law
A. Standard of review
We employ dual standards of review in this case. The threshold question—whether it is permissible to award certain monetary relief alongside equitable relief in the form of specific performance—is a legal one we answer de novo. See Credit Suisse AG v. Claymore Holdings, LLC, 610 S.W.3d 808, 819 (Tex. 2020). By contrast, “the nature and contours of an equitable award are within trial court discretion.” Id.; see also Wagner & Brown, Ltd. v. Sheppard, 282 S.W.3d 419, 428-29 (Tex. 2008).
B. Specific performance
“Specific performance is an equitable remedy that may be awarded for breach of contract” as an alternative to legal damages. Pathfinder Oil & Gas, Inc. v. Great W. Drilling, Ltd., 574 S.W.3d 882, 887 (Tex. 2019); see also Hays St. Bridge Restoration Grp. v. City of San Antonio, 570 S.W.3d 697, 707 (Tex. 2019) (“Damages and specific performance are alternatives to one another.“). Specific performance is not a separate cause of action but rather a substitute for monetary damages when such damages would be inadequate. Ifiesimama v. Haile,
522 S.W.3d 675, 685 (Tex. App.—Houston [1st Dist.] 2017, pet. denied); Scott v. Sebree, 986 S.W.2d 364, 368 (Tex. App.—Austin 1999, pet. denied); see also Sharyland Water Supply Corp. v. City of Alton, 354 S.W.3d 407, 423 (Tex. 2011) (concluding that specific performance was foreclosed because “an adequate remedy at law exists“).
A party recovering for breach of contract must elect to seek either legal damages or specific performance. Goldman v. Olmstead, 414 S.W.3d 346, 361 (Tex. App.—Dallas 2013, pet. denied). If the party seeks legal damages, it “has elected to treat the contract as terminated by the breach and to seek compensation for that breach.” Id. Conversely, a party seeking specific performance rather than damages “affirms the contract and requests the trial court to effectuate the agreement.” Id. Whether a plaintiff seeks legal damages or specific performance, the goal is to put the plaintiff back to the position it would have been in had there been no breach. See MSW Corpus Christi Landfill, Ltd. v. Gulley-Hurst, L.L.C., 664 S.W.3d 102, 106 (Tex. 2023); Goldman, 414 S.W.3d at 361-62. Contract law precludes the nonbreaching party “from recovering damages for breach of contract that would put [it] in a better position than if the contract had been performed.” Sky View at Las Palmas, LLC v. Mendez, 555 S.W.3d 101, 113 (Tex. 2018) (quoting Metal Bldg. Components, LP v. Raley, No. 03-05-00823-CV, 2007 WL 74316, at *19 n.22 (Tex. App.—Austin Jan. 10, 2007, no pet.)).
C. Reimbursement of Expenses Incident to Specific Performance
Our courts of appeals have consistently held that a court “may order, in addition to specific performance, payment of expenses incurred by plaintiffs as a result of a defendant‘s late performance.” Paciwest, Inc. v. Warner Alan Props., LLC, 266 S.W.3d 559, 575 (Tex. App.—Fort Worth 2008, pet. denied).3 This remedy has been permitted only “in narrow circumstances—when it is deemed necessary to place the parties in the same position
have occupied if the contract had been performed at the time it was to be performed:
A decree for specific performance seldom brings about performance within the time that the contract requires. In this respect, such a decree is nearly always a decree for less than exact and complete performance. For the partial breach involved in the delay or in other existing non-performance, money damages will be awarded along with the decree for specific performance.
12 CORBIN ON CONTRACTS § 63.23 (rev. ed. 2012) (emphasis added). When the trial court awards this remedy due to the breaching party‘s delay, the award “enforce[s] the equities of the parties in such a manner as to put them as nearly as possible in the position they would have occupied had the conveyance been made when required by the contract.” Heritage Hous., 674 S.W.2d at 366.4
III. Analysis
We agree with our courts of appeals that an equitable award of property-related expenses incurred due to the breaching party‘s delay in
performing is recoverable alongside specific performance in limited circumstances.5 In announcing this rule, we do not alter the centuries-old principle that specific performance is an alternative to legal damages. See
Here, the trial court ordered the Simmonses to specifically perform the buy-back obligation and repurchase the property. But this
specific performance was insufficient to put White Knight in the position it would have occupied if the buy-back obligation had been performed as agreed. See 12 CORBIN ON CONTRACTS § 63.23 (“A decree for specific performance ... is nearly always a decree for less than exact and complete performance.“). A monetary award is a necessary supplement to remedy the breach by returning the parties to the positions they would have occupied had the contract been performed when performance was due. This award thus “relate[s] the performance back to the contract date [and] equalizes any losses occasioned by the delay by offsetting them with money payments.” Heritage Hous., 674 S.W.2d at 366. It allows the contract to be enforced retrospectively, and the compensation is “incident to [the] decree for specific performance and does not amount to legal damages for breach of contract.” Goldman, 414 S.W.3d at 362.
Because the award of specific performance does not render an equitable monetary award categorically impermissible, we conclude the court of appeals erred by reversing the entire award based solely on the trial court‘s label of “actual damages/consequential damages” without substantive analysis of its components. See Byram, 2009 WL 1896076, at *4 (examining the “economic substance” and “economic effect” of a monetary award to characterize it as an equitable delay cost, even though the parties characterized it as “lost rentals“). The trial court‘s findings of fact and conclusions of law support a conclusion that a portion of the award was intended to account for the delay in performance and to adjust the equities accordingly rather than to award legal damages precluded by the equitable award of specific performance.
Having determined that an equitable monetary award of some amount was both permissible and supported by the trial court‘s findings, we address the proper scope of such an award. One basic principle cabining an award of equitable expenses is that the expense must result from and be directly traceable to the breach and resulting delay. See Stuart v. Bayless, 964 S.W.2d 920, 921 (Tex. 1998) (noting damages must be “directly traceable to the wrongful act and result from it“); Arthur Andersen & Co. v. Perry Equip. Corp., 945 S.W.2d 812, 816 (Tex. 1997) (same). This principle necessarily precludes recovery of any expense the nonbreaching party would have incurred even if performance had been timely. See USX Corp. v. Union Pac. Res. Co., 753 S.W.2d 845, 856 (Tex. App.—Fort Worth 1988, no writ) (rejecting recovery of an
Next, the expenses must have been reasonably foreseeable at the time of contracting—i.e., “in the contemplation of both parties at the time they made the contract.” Basic Cap. Mgmt., Inc. v. Dynex Com., Inc., 348 S.W.3d 894, 901-02 (Tex. 2011) (quoting Hadley v. Baxendale, 9 Exch. 341, 354, 156 Eng. Rep. 145, 151 (1854)). The foreseeability inquiry tests whether the breaching party would have foreseen the type or category of expense the nonbreaching party would incur, not necessarily its amount. See Am. Akaushi Ass‘n v. Twinwood Cattle Co., ___ S.W.3d ___, 2025 WL 450750, at *35 (Tex. App.—Houston [14th Dist.] Feb. 11, 2025, no pet. h.) (“Uncertainty as to the amount of legal damages is permissible, while uncertainty as to the fact of legal damages is fatal to recovery.” (emphases added)). Here, the Simmonses reasonably could foresee that White Knight would be responsible for paying property taxes on the Simmons property after the time for performance given the Simmonses’ refusal to repurchase, even if the applicable tax rate and total amount owed were not known. But other expenses included in the monetary award—e.g., interest paid on loans to continue business operations and property tax paid on properties other than the one that was the subject of the repurchase agreement—were far more attenuated, unforeseeable, and thus unrecoverable.
When line-drawing regarding foreseeability proves difficult, helpful guidance may be gleaned from the Uniform Commercial Code‘s definition of “incidental damages” that a seller (who, like White Knight here, must hold property for longer than anticipated by the contract) may recover upon the buyer‘s breach. Under the UCC, a seller‘s incidental damages include commercially reasonable expenses incurred in the care and custody of goods after the buyer‘s breach.
Besides the UCC‘s definition of “incidental damages,” cases from our courts of appeals awarding expenses incident to specific performance yield helpful insights for evaluating foreseeability. For example, in Claflin v. Hillock Homes, Inc., the court of appeals affirmed
an award of specific performance to the home builder along with “the carrying charges—the interest paid by [the builder] on its interim building financing between the date of the breach and the [lawsuit]—on the original building construction loan” after the defendant refused to purchase a home it contracted to buy. 645 S.W.2d 629, 635 (Tex. App.—Austin 1983, writ ref‘d n.r.e.). The builder had planned on paying off the loan with the proceeds of the sale, id. at 632, and “presented evidence that it was virtually impossible to rent the home because there was no rental market for the residence,” id. at 636.
In Byram, after the seller wrongfully refused to convey real property, the purchaser, a lessee in possession of the property, obtained both specific performance and reimbursement for the rent he paid to use the property during the delay period. 2009 WL 1896076, at *1. The rental payments—which the plaintiff incurred due to the defendant‘s failure to convey the property—were recoverable (similar to a seller‘s “care and custody” expenses) because the plaintiff was required to pay rent to avoid eviction. See id. at *4-5.
Conversely, the court of appeals in Shafer v. Gulliver reversed an award reimbursing the purchasers for lost interest on their earnest money payments, closing fees, and closing payments. No. 14-09-00646-CV, 2010 WL 4545164, at *9-10 (Tex. App.—Houston [14th Dist.] Nov. 12, 2010, no pet.). The court reversed because the compensation recovered—“[l]ost interest from what [the purchasers] should have earned on their money“—“does not fall within those categories of damages a party may recover in addition to specific performance.” Id. at 10.
*
*
*
We conclude a trial court does not abuse its discretion by awarding an equitable monetary award (regardless of its label) alongside a decree of specific performance for breach of a contract for the sale of real estate so long as the monetary award is necessary to place the parties in the same position as if the contract had been performed in full and on time. Each category of expenses awarded must be (1) directly traceable to the defendant‘s delay in performance, (2) foreseeable at the time of contracting, and (3) commercially reasonable. When, as here, the nonbreaching seller is in possession of the land during the delay, any expense awarded must also be incurred in connection with the care and custody of the particular property in dispute.
We reserve for another day the question of this rule‘s precise application and potential refinement of its requirements in cases involving different facts. When those cases do arise, we trust our trial courts and courts of appeals to faithfully apply the equitable principles announced today in fashioning and reviewing such a remedy.
IV. Conclusion
The court of appeals erred by reversing the monetary award without addressing whether any portion of it was warranted. Accordingly, we reverse the court of appeals’ judgment in part and remand the case to that court to review the award under the principles we announce today.
Rebeca A. Huddle
Justice
OPINION DELIVERED: June 13, 2025