55 Mo. App. 554 | Mo. Ct. App. | 1893
The only substantial question arising on this appeal is, whether the court erred in submitting, by an instruction to the jury for their finding, an issue not made by the pleadings. The point arises in this manner: The petition charges the following facts. The plaintiff, being about to build a.
The answer of the defendant denies these allegations, and states, in substance, that the indemnity bond mentioned in the petition was waived by the plaintiff in consideration that the defendant would disburse under plaintiff’s order the money arising from the loan, and applicable to the building, for the payment of material-men, laborers, and others; that the defendant did disburse all the money under plaintiff’s orders, so that no lien accrued by reason of any neglect on the part of defendant; that the liens were the result of the contracting by plaintiff for a more expensive house than the money would pay for, the amount of the liens representing less than such excess.
It will be thus seen that the issue presented by the petition is, that the defendant violated its contract obligations in failing to take an indemnity bond from the contractor, and in paying him in the aggregate over eighty per cent, of the amount of his expenditures, in consequence whereof certain liens were filed against the building, which liens the plaintiff was compelled to discharge. The answer of the defendant was a simple denial, an assertion that an indemnity bond was waived, and, as evidencing such waiver, an affirmative allegation that all moneys expended were expended upon plaintiff’s orders. Touching the waiver of the indemnity bond by the concurrent action of the plaintiff and defendant there was no substantial controversy, and the court assumed that such waiver had been fully established. There was no evidence tending to show that the liens were the result of the defendant’s dereliction, and the court did not submit that question to the jury. There was no evidence that the defendant had paid to the contractor more than eighty per cent, of his expenditures, the showing on that subject being at best conjectural, and no evidence whatever that an excessive payment to the contractor had anything whatever to do with the filing of these liens. There was irrefragable evidence that all the money paid out by the defendant, except the sum of $218, was paid out upon the plaintiff’s orders. In regard to this $218 the evidence was conflicting. This money had been paid to the contractor by the defendant, and the plaintiff admitted that one subsequent payment for $274 was made to the contractor by the defendant upon his, the plaintiff’s order, given with a full knowledge of the previous payment of $218.
This being in substance all the evidence bearing upon the point of inquiry, we must hold that the court
“The court further instructs the jury that, if they find from the evidence that defendant paid out the $8,500 in question, $2,350 at the direction of plaintiff on his lot in question, and the balance, except $218.39, under and in pursuance of the orders signed by plaintiff and offered in evidence, then the court instructs you in reference to the second count in plaintiff’s petition, he is not entitled to recover for anything, unless it be for $218.39 paid by defendant to Clayton .on or about August 11, 1891; and if you find and believe from the evidence that said sum of $218.39 was paid by defendant to Clayton at the direction or request of plaintiff, or that, after such payment had been made, plaintiff ratified and acquiesced in such payment, then you will find in favor of defendant on said second count. But if you find and believe from the evidence that said payment was not made at the direction or request of plaintiff, and that he did not afterward ratify or acquiesce in the same, and further find from the evidence that said sum, when paid, was in excess of eighty per cent, of the sum which had actually been expended upon said building in question, and that it was the understanding and agreement of the parties that defendant should not pay to-said Clayton or to his subcontractors and material-men at any time more than eighty per cent, of the sum actually expended on said building, then the jury will find for the plaintiff on said second count for the sum of $218.39 and interest thereon at the rate of six per cent, per annum since the date of filing this suit, viz., February 23, 1892.”
It has always been the law of this state that the . plaintiff must recover, if at all, on the cause of action stated in his petition.' It is only when the variance
An insufficient averment in a petition may be helped out by an answer supplementing it; Krum v. Jones, 25 Mo. App. 71; Henry v. Sneed, 99 Mo. 407; but, in such an event, the recovery is still on the petition and not on the answer. Where the petition states one contract, and the answer states another and wholly different contract, denying the contract stated in the petition, we are aware of no rule which would entitle the plaintiff to a recovery upon a bare showing that the defendant had not complied with the contract stated in the answer. The case last put presents a case of failure of proof and not of variance, and is governed by section 2238 of the Revised Statutes and not by the provisions of sections 2097.
The plaintiff claims that this point has not been properly saved. The bill of exceptions recites that the defendant excepted to the instructions using the noun in the plural. The motion for new trial, complains of this particular instruction, and of the fact that the case was submitted to the jury upon an issue of fact not raised by the pleadings. The practice in many states requires specific exceptions to the charge of the judge, and disregards exceptions taken to instructions as a whole, unless the whole charge is erroneous. The
It results that the judgment must be reversed and the cause remanded. So ordered.