90 Mo. App. 106 | Mo. Ct. App. | 1901
This is a bill in equity to cancel and enjoin the collection of certain taxbills issued by the city of St. Louis to the Gilsonite Roofing and Paving Company for improving Whittier street. Originally there were several plaintiffs, owners of the property abutting on the improvement, but all of them have withdrawn from the contest except Joseph Wheless. The contract between the city and the Gilsonite Roofing and Paving Company contained the following clause:
“The work embraced in this contract shall begin within one week after written notice so to do shall have been given to the contractor by the street commissioner, and carried on regularly and uninterruptedly thereafter (unless the said commissioner shall otherwise in writing specially direct), with such a force as to insure its full completion within two months thereafter; the time of beginning, rate of progress, and time of completion being essential conditions of this contract. And if the contractor shall fail to complete the work by the time above specified, the sum of five dollars per day for the first ten days, and the sum of ten dollars per day for each and every day thereafter until such completion, shall be deducted from the moneys payable under this contract.”
On the seventh day of August, 1899, the street commissioner of St. Louis gave the contractor the following notice:
“You are hereby notified to commence work on Whit*109 tier street, between Washington avenue and Einney avenue, within one week from the receipt of this notice. You are required to complete the whole work on or before October 14, 1899.”
Work was begun on the tenth day of August, finished on the twelfth day of October, and fully accepted by the city as being in compliance with the contract and taxbills issued to pay for it.
The only point made against the validity of the tax-bills is that by virtue of the contract the performance of the work extended two days over time; that inasmuch as it was begum on August 10 it should have been completed by October 10. Respondent insists on the other hand, that it had until October 14, or two months from the time fixed for it to begin work by the notice from the street commissioner, in which to complete it. The .question involves the construction of the aforesaid clause of the contract and the determination of whether or not there was a substantial compliance with its provisions. It will be observed that the date when the improvement was to be begun, and also the continuity with which it was to be pursued, were left to the discretion of the street commissioner, and the contractor had to be governed by his directions. It is conceded by appellant that, according to the contract and notice, the paving company might have deferred the commencement of the work until August 14 and if it had done so and finished by October 14, its whole duty would have been done. But his contention is that inasmuch as it chose to begin on August 10 it was bound to finish on October 10. This construction is strained. Both the city and the contractor treated the contract as meaning that two months from the date fixed by the notice of the street commissioner for the beginning of the work, was the limit within which it must be completed. The language fairly bears such
Even granting the appellants’ view of the meaning of the contract is sound, there is grave doubt if it was not substantially complied with; but we do not find it necessary to go into that question.
The judgment is affirmed.