90 F. 189 | 4th Cir. | 1898
This case comes up on appeal from the circuit court of the United States for the district of West Virginia. It arose from an intervention filed by the Reymann Brewing Company in the cause of the Washington Trust Company against the Wheeling Bridge & Terminal Railway Company, and seeks to establish a preferred claim against the property in the hands of the defendant company. This claim is for two" separate items,—one of $2,500, the value of certain property alleged to have been taken by the railway company in constructing its track; the other, of $600, for failure in fulfilling its contract, while building its track, to pave a certain alley. The Reymann Brewing Company was the owner of certain real property lying in a suburb of the city of Wheeling, called “Manchester.” On this property it conducted its business, — the manufacture, brewing, and selling of beer. Upon it were the buildings erected and used for these purposes. This realty consisted of four parcels, separated by streets or alleys from one another. The whole tract is bounded on the east by Warren street, on the west by Wheeling creek, on the north by Seventeenth street, or the city of Wheeling, and on the south by certain property of the heirs of Pebler. The four parcels are numbered 1, 2, 3, i; No. 1 being the south parcel, and the others following consecutively, making No. 4 the north parcel.
In the year 1889 Judge Cochran, the president of Wheeling &
“It was thereupon agreed Let ween the said Wheeling Bridge & Terminal Hallway Company and your petitioner that the said railway company might have its right of way according to the new location, and might; construct its trucks across the said four parcels of land according to the said new location, and In consideration thereof the said railway company agreed that it would at its expense remove the boiler ho-use of your petitioner upon the said parcel numbered o-ne to a. point on tlie said parcel further west than it had theretofore stood, so as to permit the tracks of the railway company to mu to the east of it; that it would make certain changes in the bridge owned by the said city of Wheeling, the eastern end of which rested upon the said continuation of said Seventeenth street; that it would, at its expense, pave the alley aforesaid, which lies between the said second and third parcels of your petitioner’s land (this alley being a public alley, but haying proper; y of your petitioner on both sides of it, and being especially used by your petitioner for access to the creek); that it would cross the last-mentioned alley with its tracks by a bridge having under it a sufficient clearance to*192 permit tiie passage of teams; and that it would pay to your petitioner the sum of twenty-five hundred dollars in money. As a part of the said agreement, it was further agreed that your petitioner should convey to said railway company the said ice house on the said parcel numbered four, and the land on which the said ice house was situated, and that with that land it should grant to the said railway company a right of way for persons, horses, and vehicles between that land and Warren street, so that access could he had 'to the said land from the last-mentioned street.” That it has not paid the $2,500, and has not paved the alley.
It estimates the latter at $600, and its money demand is for the aggregate of these sums, with interest
There was only one written agreement between the parties. That is as follows:
“This memorandum witnesseth that the Keymann Brewing Company of Wheeling, West Virginia, in consideration of one dollar paid by the Wheeling and Harrisburg Itailway Company of West Virginia hereby grants and conveys to said railway company, its successors and assigns, a right of way for its railway over and along said company’s lands situate on the easterly bank of Wheeling creek, in said city of Wheeling, Ohio county, in said state; said right of way to include the strip of land on and along the east bank of said creek from the buildings of said Keymann Brewing Company to the bed of the creek. This grant is accepted by said railway company with the agreement on its part that it shall, in constructing its tracks over said lands, preserve the facilities for storing ice in said company’s ice houses, or, if any changes are required therein, they shall be made at the cost of the railway company, and in such wise as not to be less useful and convenient to the brewing company; and any change made in the Seventeenth street bridge shall be such as shall not injure the access to the brewing property, and shall conform to the city ordinance granting a right of way over streets. &c., to said railway company. It is further stipulated that in constructing said road and tracks over said lands the foundations to buildings and to the brick stack shall not be interfered with, and all proper precautions shall be taken to protect said brewery property from injury. Said brewing company agrees to execute such other conveyance as may be necessary to assure to said railway company the right of way hereby intended to be described. Witness the corporate seal of said brewing company, and the attestation of its president, this 25th day of July, 1888, together with the seal and attestation of said railway company by its president.”
All that was done afterwards was in parol, and is testified to by the president and by the manager of the brewing company. The railway was completed in 1889. The petition was filed on December 9, 1895. Judge Oochran, who was president of the railway company at the time of this construction, died after this intervention was filed.
The receiver, in his answer to the petition, set up the laches on the part of the brewing company. He also pleaded the statute of frauds to the parol agreements. He denies that there was ever any agreement to pay the $2,500 for the ice house, or to pave the alley, as alleged, or any other agreement than that set out in writing as above. He avers that the building of the railroad was greatly for the interest of the brewing company, in putting its goods to market, and that this was the real consideration for the grant of the right of way.
On the coming in of the answer, the court referred the cause to a master. He made his report — the finding is in favor of the petitioner — on both claims. He also finds that the brewing company has a vendor’s lien on the right of way, and also upon the land on which
This proceeding is by intervention in a proceeding in equity. It is brought to enforce a lien on realty in the hands of the court of equity, and in the charge of its receiver. Tw'O questions wTere involved in it: First, was there any sum of money due to the intervener? Xext, was it secured by lien, and, if so, how is this lien to be enforced? Proceeding'to the adjudication of these questions according to the established procedure of a court of equity, a reference was to a master, who reported the facts bearing upon both questions. The determination of the first question was essential to the adjudication on the other. The right of the court to ascertain the amount of money due, in the mode adopted, cannot be questioned. It is constantly exercised in the enforcement of the lien by mortgage. The lien of the vendor is substantially a mortgage. Lewis v. Hawkins, 23 Wall. 127. It will be observed that this is not the ordinary claim against an insolvent railroad company, praying payment thereof out of funds in the hands of, and under ¡he control of, the receiver. It is the assertion of a lien superior to the lien under which the receiver was appointed, and in every respect paramount to him. Tn this respect the case at -bar differs entirely from Gue v. Canal Co., 24 How. 263. How the lien, if it be established, shall be enforced is a question for the court. As it would («ver a very important part of the road, and its control by the receiver is essential to the keeping the road a going concern, the court may well conclude that the whole property is interested in preserving it, and so the general fund could be used in extinguishing the lien. If there be funds on hand, the result of earnings, they could be used. If (he properly is so insolvent as to produce no earnings, provision may be made for the extinguishment of the lien out of the proceeds of sale, so as give a good title to the purchaser. The sale of the part of the road covered by the lien would be resorted to- only in the last extremity. But, if reduced to tbis necessity, the court could order it. Lewis, Em. Dom. § 620; Finnell v. Railway Co. (Ky.) 36 S. W. 653; Varner v. Railway Co., 55 Iowa, 677, 8 N. W. 634; Hobbs v. Trust Co., 30 U. S. App. 393, 15 C. C. A. 604, and 68 Fed. 618. It is not a question of a preferential claim, in the sense of a claim having superior equities to the mortgage debt. It is the payment of the claim which outranks the mortgage, independent of it, unaffected by the proceedings for foreclosure.
“The taking possession of (that is, exercising control and dominion over) the property was referable entirely to the contract. It was an act done with respect to the property by the consent of the vendor, which would not have been done if there had been no contract. This consent gave to the act, which otherwise would have been tortious, its character as one of part performance.”
But it is by no means clear that the case of the intervener rests on a parol contract or contracts. The memorandum of 25th July, 1888, giving the right of way over the lands of the brewing company, has this acceptance of the grant by the railway company:
“This grant is accepted by said railroad company with the agreement on its part that it shall, in constructing its tracks over said lands, preserve the facilities for storing ice in said company’s ice houses, or, if any changes are required therein, they shall be made at the' cost of the railroad company, and in such wise as not to be less useful and convenient to the brewing company.”
The memorandum also, in its general provisions, says:
“All proper precautions shall be taken to protect the brewery property from injury.”
Evidently this memorandum contemplated changes in the location of the tracks. The prominent idea was the right of way over the lands. There were changes in the precise location of the tracks on parcels 1, 2; and 3. These are not denied. When the result of these changes appeared on parcel Ho. 4, it was discovered that it made the ice house on that parcel useless, and destroyed the facilities of getting ice into the house, and from the creek. The railway company could have made the changes required thereby. But the evidence shows that these would have been costly and troublesome, so far as the ice house was concerned; and, instead of making them, the company preferred to pay the money, $2,500, and it agreed to make a necessary change for facilitating the getting of ice from the creek by paving the alley, at a cost of $600. The case of the inter-vener rests on this written agreement. The parol evidence is as to the measure of damages.
It is also insisted that the intervener has been guilty of laches, and so has lost its right. Now, the case, as made, is the entry upon and the use of the right of way by the railway company, under a contract that, in constructing its tracks over the land, it shall preserve the facilities for storing ice in said company’s ice houses, or. if any changes
The decree below' provides for the execution of a deed by the brewing company. This company assigns no error in that respect. The