80 Neb. 682 | Neb. | 1908
Under the provisions of the act of 1905 (Comp. St. 1905, ch. 78, secs.-83-85p) the county board of Lancaster county
1. It appears that, when this suit was brought the members of the county board and the county attorney did not agree as to the policy which should be adopted in defending the same; and the county board, acting in pursuance of the provision of the statute authorizing it to employ addi
2. The excuse of the county board for terminating a confessedly advantageous contract nearly four months before its expiration was that the season’s work was practica1^ over, and that the board desired to let the contract for the ensuing year at a date early enough to enable the new contractor to prepare himself for beginning work in the spring. This end might have been attained by negotiating for the new contract before the expiration of the old one.' This suggestion is met by the statement that a former county attorney had advised the board that it was better to cancel an existing contract before advertising for new proposals, and that the board believed it to be neces
8. It is apparent that the county board cannot have, Avith different parties, two yearly contracts, any portion of Avhich covers the same period, and that, if the contract expiring April 26, 1907, Avas in force on the 2d day of March in that year, the county board had no power to enter into the contract Avith the defendant, the Nebraska Construction Company, to begin on the latter date. It is urged that on March 2 the contract expiring April 26 was practically ended, and that no necessity for any further Avork thereunder Avas likely to arise, and that, if such necessity did occur, the contractor could not be compelled to undertake any Avork Avhich he might not be able to complete within the year. We do not think the statute susceptible of any such construction. The purpose of the law was to have a contract in existence for a year, under which Avork,
4. The defendants contend that the plaintiff has failed to show damage in common with the taxpayers of the county by reason of an unnecessary expenditure of the public funds, and argues that, if no other work would have been done under the contract expiring April 26, 1907, it was a matter of indifference to the taxpayers whether it was allowed to stand until it expired or not. We think the plaintiff had the right, on the 2d day of March, 1907, to assume that the necessity for work might, and probably would, arise before the 26th day of April, and that it would, in default of any action taken by him, be done under the contract entered into on the 2d day of March. The prices under this contract being very much higher than under the contract expiring April 26, damage would necessarily and naturally result to the taxpayers of the county. The fact that no such work was done may properly be attributed to the injunction obtained by the plaintiff in this action.
5. It appeared from the evidence that at the time of the making of the Sheeley contract on the 26th day of April, 1906, there was existing a former contract with the same parties, which would not have expired by its own limitation for about 15 days, but which the board had assumed to terminate before that date. It was contended
We therefore recommend that the judgment of the district court be affirmed.
By the Court: For the reasons set forth in the foregoing opinion, the judgment of the district court is
Affirmed.