31 N.Y.S. 186 | N.Y. Sup. Ct. | 1894
This action was brought to recover an amount claimed to be due upon a contract between the plaintiff and his deceased partner, on the one part, and the defendant, on the other, for furnishing the materials and performing the labor required for the construction and completion of a 48-inch brick sewer in Oakwood avenue, from Oakwood Cemetery to Kennedy street; in Kennedy street, from Oakwood avenue to Cortland avenue; in Cortland avenue, from Kennedy street to South avenue; and in South avenue, from Cortland avenue to the Onondaga creek. The contract between the parties was in writing. The plaintiff alleged that it had been fully and completely performed according to its terms, except where changes-were made by the defendant’s engineer and surveyor under the powers conferred upon him by such contract. After the plaintiff’s firm had commenced and constructed a portion of the sewer described, an investigation was had by the officers of the defendant, whereby it was discovered that some portions of the work were not in strict compliance with the provisions of the contract; but it also appeared that, where there were changes or deviations, they were made by the direction and under the immediate supervision of the engineer and inspector of the defendant. After such investigation the defendant’s common council duly passed a resolution, which was approved and signed by the mayor, requiring the contractors to complete the portion already built in accordance with the terms of the contract, except, however, that they were not required to change the grade of the work as it then existed; the invert portion was to remain as then laid. The contract was thereby declared to be amended and modified to that extent, and the remaining portion of the sewer was to be constructed in accordance with the terms of such contract, without modification. The contractors thereupon resumed the work, which had been suspended during the investigation, completed the remainder in substantial accordance with the terms and provisions of the contract, and also performed some extra work for the defendant. On July 25, 1892, and after the final completion of such sewer, the defendant’s commissioner of public works made the plaintiff’s final estimate or account, by which it appeared that there was $7,933.41 due upon such contract, and for extra work done by the contractors, and attached thereto the following certificate:
“I hereby certify that for a distance of 1,453 feet from Onondaga creek the work was done in accordance with a resolution adopted by the common council 29 July, 1890. The next 1,000 feet was done in accordance with the contract and specifications, except in the matter of grade. At the beginning of the 1,000 feet the sewer is about two feet above the grade established by the original map, and at the end of the 1,000 feet it is at said grade. The remaining portion of the sewer was completed in accordance with the contract and specifications.”
The proof disclosed that the 1,000 feet mentioned in the foregoing certificate was constructed under and by the direction of the defendant’s city engineer and inspector. It also appeared that the-grade of the 1,000 feet, so far as it was not made to conform to the original contract, necessarily had to be changed, or there could be no connection with or outlet through the portion already con
The appellant contends that the common council had no authority to modify the contract between the parties, and that, therefore, the court erred in not granting its motion for a nonsuit. We think this contention cannot be sustained. Meech v. City of Buffalo, 29 N. Y. 198; Moore v. City of Albany, 98 N. Y. 396; Mulholland v. Mayor, etc., of New York, 113 N. Y. 631, 20 N. E. 856; Brady v. City of New York, 132 N. Y. 415, 30 N. E. 757; Voght v. City of Buffalo, 133 N. Y. 463, 31 N. E. 340. Nor do we think the case of Bonesteel v. Mayor, etc., of New York, 22 N. Y. 162, aids the defendant. That case is clearly distinguishable from the case at bar, as is pointed out in Moore v. Mayor, 73 N. Y. 248. In the latter case it was, in substance, held that although a municipal corporation may set up, as a defense to an action upon a contract alleged to have been made by it, its own want of power to contract, yet, as against those innocently dealing with it, and in good faith parting with property and expending money for its benefit, it may be estopped from availing itself of irregularities in the exercise of power conferred. Smith v. City of Utica (Sup.) 6 N. Y. Supp. 792. Thus we are led to the conclusion that the court committed no error in refusing to nonsuit the plaintiff upon the ground already considered, and that it properly submitted to the jury the question whether the common council, with a full knowledge of all the facts in relation to the condition of the portion of the sewer complained of, had modified the contract between the parties, and waived any objections that existed as to the manner of its performance, in so far as it did not conform to the original contract, and whether,
The appellant also contends that the action was improperly brought, that by the contract the plaintiff agreed that no payment should be made until the cost was assessed upon and collected from the taxpayers liable to local taxation for the construction of the sewer, and that an action for the contract price cannot be maintained. In Reilly v. City of Albany, 112 N. Y. 30, 42, 19 N. E. 508, where a similar question arose, Ruger, C. J., in delivering the opinion of the court, said:
“When the contractor had performed his work according to his contract, he had no duty remaining to discharge, and then had a right to rely upon the implied obligation of the city to use with due diligence its own agencies in procuring the means to satisfy his claims. It could not have been supposed that he was not only to earn his compensation, but also to set in motion and keep in operation the several agencies of the city government, over whom he had no control, to place in the hands of the city the funds necessary to enable it to pay its obligations. That was a power lodged in the hands of the city, and the clear intent of the contract was that it should exercise it diligently for the purpose of raising the funds necessary to pay for the improvement. For an omission to do so, it would become liable to pay such damages as the contractor might suffer by reason of its neglect of duty.” Cumming v. Mayor, etc., of Brooklyn, 11 Paige, 596; Sage v. City of Brooklyn, 89 N. Y. 189; McCormack v. City of Brooklyn, 108 N. Y. 49, 14 N. E. 808; Donnelly v. City of Brooklyn, 121 N. Y. 9, 24 N. E. 17.
We think the doctrine of these cases justified the trial court in holding that this action could be maintained.
Again, it is contended that the court erred in declining to charge:
“If the jury find that the completion of the contract, as originally made, has not been certified by the city engineer or commissioner of public works, the plaintiff cannot recover.”
It will be perceived that this request related to the original contract, and did not include the contract as modified by the common council. We think the court was justified in refusing to charge as requested.
The only remaining question raised by the appellant relates to the rejection of evidence. On the cross-examination of the plaintiff the defendant offered to show that he procured the vote of one member of the common council for the resolution modifying the contract by corrupt means. To evidence which, it was claimed, would tend to show that fact, the plaintiff objected on the ground that it was incompetent, immaterial, and irrelevant, and that the resolution was duly adopted and approved by the mayor in accordance with the law. This objection was sustained, and the defendant excepted. It may be observed, in p.assing, that this offer was made, and proposed evidence excluded, during the cross-examination of the plaintiff, who was a witness in his own behalf. The court might well have excluded the evidence upon the ground that the defense of fraud should be proved, if at all, after the plaintiff rested. Moreover, it was conceded upon the trial that an investigation as to the question of bribery or fraud was had in December, 1890, so that if there was any fraud on the part of the