Westinghouse Electric Supply Co. v. Pyramid Champlain Co.Westinghouse Electric Supply Co. v. Pyramid Champlain Co.
Cross appeals from an order of the Supreme Court (Plumadore, J.), entered October 1, 1992 in Clinton County, which, inter alia, denied defendant Pyramid Champlain Company’s motion to dismiss certain of defendant R. P. Brosseau & Company’s cross claims.
On June 11, 1987 the owner commenced a related action against the contractor charging the contractor with breach of one of the contracts for electrical work. The contractor answered and the supplier next brought the instant action against the contractor, the owner and others claiming, inter alia, that the contractor breached its contract for electrical supplies with the supplier and demanding, inter alia, payment for materials and equipment shipped to the contractor. The contractor’s answer contained cross claims against the owner and other defendants. The owner answered and asserted cross claims against the contractor for, inter alia, indemnification and damages flowing from the contractor’s alleged breach of contract with it. Subsequently, the owner served an amended answer with cross claims.
In January 1991 Supreme Court directed that all proposed amended pleadings be submitted to it by March 1, 1991. The contractor sent its proposed amended answer with cross claims to the owner on March 8, 1991. The owner rejected it for lateness and because of the failure to furnish "an affidavit of merit with respect to the proposed pleading”. Supreme Court directed the owner to accept the contractor’s March 8, 1991 proposed amended answer with cross claims. In January 1992 Supreme Court, inter alia, allowed the supplier leave to serve an amended complaint to assert that an agency relationship existed between the owners and the contractor. The order was silent as to whether the contractor could serve an amended answer with cross claims. In February 1992 the supplier served its amended complaint which the owner answered.
The contractor then served an amended answer with cross claims which the owner rejected because the contractor had not been granted permission to do so. Thereafter, Supreme Court, in an order entered October 1, 1992, denied the owner’s motion to dismiss the contractor’s cross claim Nos. 12 through 16. The owner had argued, inter alia, that the contractor did
The owner appeals from that part of the order which denied its motion to dismiss the contractor’s cross claim Nos. 14, 15 and 16, denied its motion compelling the supplier to furnish further responses to its second set of interrogatories and allowing the contractor to raise the issue of punitive damages at trial. The contractor cross-appeals from so much of the order as granted the owner’s motion to compel the contractor’s response to the owner’s first set of interrogatories.
Supreme Court correctly allowed the contractor to amend its answer and to assert additional cross claims against the owner without having formally moved for permission to do so. Pursuant to CPLR 3025 (d) the contractor had the right to amend its answer without moving (see, Boulay v Olympic Flame,
The owner’s contention that cross claim No. 14, which alleges that the owner negligently misrepresented the nature and extent of the work to be done by the contractor, must be dismissed is not persuasive. The owner contends that the contractor has failed to allege that a special relationship existed between it and the owner and because the allegations arise out of breach of contract and fail to allege any duty extraneous to the contracts. It is true that, in order to establish a claim for negligent misrepresentation, the contractor must demonstrate that the owner had a duty, based upon some special relationship with it, to provide it with correct information, that the information was false or incorrect and that it reasonably relied on that information (see, Clark-Fitzpatrick, Inc. v Long Is. R. R. Co.,
Also without merit is the owner’s argument that cross claim No. 15 alleging fraud should have been dismissed because the alleged misrepresented facts (1) pertain to future rather than to past or present existing facts, (2) do not allege the breach of a duty extraneous to the contracts, and (3) fail to allege a causative connection between the alleged misrepresentations and the harm flowing from such misrepresentations. The contractor claims that when the owner "prepared the electrical specifications and the timetable for completing the electrical work” it "knew or should have known that the specifications were incomplete and that the completion of the electrical work could not have been completed within the time table”. This sufficiently alleges "a representation of present fact, not of future intent” (Citibank v Plapinger,
The owner’s claim that cross claim No. 16 (for intentional interference with contractual relations) should have been dismissed because the acts on which it is based occurred at the latest in June 1987 and a claim was not interposed until
The owner’s argument that Supreme Court improperly gave the contractor permission to renew the issue of punitive damages at trial is also meritorious. Punitive damages are not recoverable in an action for breach of contract. In order to recover punitive damages for tortious conduct the contractor must allege facts indicating that the owner acted in a "wanton, willful or malicious manner” (RKB Enters. v Ernst & Young,
Supreme Court erred in denying the owner’s motion for an order compelling the supplier to respond to its second set of interrogatories (see, Hirschfeld v Hirschfeld,
The owner’s argument that Supreme Court improperly denied its motion to vacate the note of issue because the supplier’s failure to respond to the second set of interrogatories makes it impossible for the owner to prepare for trial is moot in light of a December 16, 1992 Supreme Court order striking the note of issue.
Finally, the contractor’s claim that Supreme Court erred in
Yesawich Jr., Mercure and Crew III, JJ., concur. Ordered that the order is modified, on the law, without costs, by reversing so much thereof as allowed defendant R. P. Brosseau & Company to renew the punitive damages issue at trial and denied defendant Pyramid Champlain Company’s motion to dismiss Brosseau’s cross claim No. 16 and compel plaintiff to further answer interrogatory Nos. 3 and 5 of Pyramid’s second set of interrogatories 3 and 5; Pyramid’s motion is granted to said extent, Brosseau’s cross claim No. 16 is dismissed and plaintiff is compelled to further answer interrogatory Nos. 3 and 5 of Pyramid’s second set of interrogatories; and, as so modified, affirmed.