598 F.2d 759 | 3rd Cir. | 1979
OPINION OP THE COURT
On December 23, 1977, the United States Nuclear Regulatory Commission (NRC) suspended for approximately two years its decisionmaking process regarding proposals for the recycling of spent nuclear fuel and the use in nuclear reactors of plutonium recovered from that fuel. This suspension was announced in an order terminating informal rulemaking and related licensing proceedings concerning this subject. In part, the decision to place a moratorium upon these deliberations was taken in deference to President Carter’s stated objective of deferring domestic plutonium recycling while the United States initiated a multinational evaluation of alternative fuel cycles that would pose a lesser risk of international proliferation of nuclear weapons. Petitions for review were filed requesting us to set aside and enjoin the NRC’s order on the grounds that, in terminating these proceedings, the NRC violated the Atomic Energy Act (AEA)
I.
For over two decades, the federal government, initially through the Atomic Energy Commission (AEC) and later through the NRC, a successor agency to the AEC,
Recognizing that a decision to implement a wide-scale program for the commercial recycling of plutonium constitutes a major federal action significantly affecting the environment, and thereby necessitating an environmental impact statement (EIS) in order to comply with § 102(2)(C) of NEPA,
One of the concerns expressed while the rulemaking and adjudicatory proceedings were progressing was that dangers to world security might ensue from the commercial reprocessing of nuclear fuel. For example, the AEC staff’s first draft of GESMO, which was published on August 21, 1974,
President Carter disclosed his administration’s policy concerning plutonium recycling on April 7, 1977. Noting with alarm the serious proliferation risks of plutonium recycling, the President stated that part of the government’s response would be to “defer indefinitely the commercial reprocessing, and recycling of plutonium produced in the U.S. nuclear power programs,” and to sponsor an international nuclear fuel cycle evaluation (INFCE) program aimed at developing alternative processes with lower proliferation risks.
Almost immediately thereafter, a motion was filed to terminate the GESMO proceeding, and the NRC’s GESMO Hearing Board postponed further hearings.
Petitioners sought judicial review within the prescribed period of sixty days
Concerned that the December 23 Order might not be deemed final, the parties also took several protective actions after the May 8, 1978, Memorandum of Decision was issued. First, Allied-General petitioned the District of Columbia Court of Appeals for review. Subsequently, Westinghouse and Scientists filed new petitions for relief before this Court, docketed respectively as numbers 78-1895, 78-1894 and 78-1892. Allied-General’s petitions are before us following their transfer from the Court of Appeals of the District of Columbia,
To complete the dramatis personae of the immediate controversy, the National Resources Defense Council, Inc. (NRDC) and the States of New York, Texas and Wisconsin have intervened in support of the NRC’s decision, while a group of twenty electric utility companies led by Baltimore Electric and Gas Company have filed an amicus curiae brief urging that the order of the NRC be vacated and remanded for further consideration.
II. CHOICE OF FORUM
NRDC has moved to dismiss for want of jurisdiction those petitions that seek review of the December 23 Order, primarily on the ground that that order is not a reviewable “final order.”
Apparently, then, what NRDC hopes to achieve by its motions is to have this controversy transferred to the Court of Appeals for the District of Columbia pursuant to 28 U.S.C. § 2112(a). That section specifies which court is the proper forum for review of an administrative decision when petitions are filed in more than one court of appeals. It states in pertinent part:
If proceedings have been instituted in two or more courts of appeals with respect to the same order the agency . shall file the record in thát one of such courts in which a proceeding with respect to such order was first instituted. The other courts in which such proceedings are pending shall thereupon transfer them to the court of appeals in which the record has been filed. For the convenience of the parties in the interest of justice such court may thereafter transfer all the proceedings with respect to such order to any other court of appeals.
Presumably, NRDC believes that if it is concluded that the December 23 Order is not the NRC’s “final order” and that therefore we are not the court “in which a proceeding with respect to such order was first instituted,” we must necessarily transfer all the petitions to the District of Columbia Circuit, which would then decide whether to adjudicate the controversy or perhaps transfer it again to another forum.
Section 2112(a), however, is not jurisdictional in nature, but rather, is a somewhat unusual venue statute.
“[t]his provision contemplates judicial review of particular agency action by the same court. The parties are spared simultaneous participation in proceedings*767 in more than one circuit, and forum shopping is discouraged.26
Although this salutary provision does not by its terms provide a solution for every conceivable situation in which review of the same administrative action is sought in more than one circuit, courts have freely relied on its underlying principles to fashion appropriate approaches to related problems and “[t]o prevent unseemly conflicts that could result should sister circuits each take the initiative and issue conflicting decisions” as to where venue lies.
[o]ur main concern in handling cases such as this, is that one of the circuits involved take the initiative and decide the threshold question of proper forum rather than delay consideration of the merits due to an overabundance of procedural caution28
Accordingly, courts have held that even when the validity of the filing of the first petition is in dispute, all the petitions should be transferred to the court in which the disputed petition was filed, and that court should proceed to determine the order in which valid petitions for review were filed.
In view of the lack of first-filing in any one circuit, Section 2112(a) cannot be implemented through the mechanics set forth in its first sentence quoted above. Instead, we look to the ultimate provision of § 2112(a), which authorizes transfer of the proceedings to another circuit “[f]or the convenience of the parties in the interest of justice.” Judicial review in the forum determined by that standard is a stated congressional goal, and our obligation is- to honor the legislative will as expressed in the statute as a whole.31
Also in keeping with the purposes of the statute, courts have interpreted the term, “the same order,” so as to insure the consolidation in one court of petitions from sequential orders arising from the same administrative background and cumulative record.
In the present case, the Court of Appeals for the District of Columbia transferred Allied-General’s petitions to this Court notwithstanding the fact that it was not clear whether this Court is the one “in which a proceeding with respect to such order was first instituted.” In granting the NRC’s motion that the petitions be transferred, the District of Columbia Court reasoned in a per curiam opinion that,
[sjince the petitions for review filed in the Third Circuit were filed first, considering the time of filing alone, it seems to us that the (sic) court should decide whether the action of the Commission of December 23 or that of May 8 was its final order in these proceedings. See Abourezk v. FPC, 168 U.S.App.D.C. 246, 513 F.2d 504 (1975)33
It would do little to further the purposes of § 2112(a) were we now to decide that the May 8 Memorandum was the NRC’s “final order” and therefore transfer all the petitions to the District of Columbia Circuit in order that it may choose a forum. Only if Allied-General, which was the first to file a petition after the May 8 Memorandum (and which filed it in the District of Columbia Court), insisted that the winner of the race to the courthouse be ascertained would it possibly be in the interest of justice to determine the finality question. But in the District of Columbia Circuit, Allied-General did not oppose the NRC’s motion to transfer, and subsequently it expressed its willingness to have this Court adjudicate the validity of the NRC’s action. Allied-General is primarily interested in having the matter resolved expeditiously,
At oral argument, even counsel for NRDC conceded that the more practical, efficient, and just alternative would be for us to reach the merits. Nonetheless, NRDC did not withdraw its motio.n because it regarded the matter to be a jurisdictional defect that this Court could remedy only if it transferred the cases to the District of Columbia Circuit, which would then presumably retransfer the cases to us for disposition on the merits. We have already concluded that NRDC’s motion does not raise a jurisdictional deficiency because pe-. titions for review from both the December 23 Order and the May 8 Memorandum were timely filed in this Court. There thus being no reason to go through the process of transferring petitions back and forth between two circuits, while the parties as well as the public anxiously await resolution of this important controversy, NRDC’s motion will be denied, and we shall proceed to address the merits.
III. CHALLENGES BASED ON THE ATOMIC ENERGY ACT
A. The Reasons for the NRC Decision
As explained by the NRC in considerable detail in its May 8 Memorandum of Decision, the December 23 Order terminating GESMO and related licensing proceedings was prompted by the President’s policy initiatives as well as by the pendency of studies into alternative fuel cycles. With respect to the first reason for termination, the NRC noted in its Memorandum that although the proceedings in question concern domestic activities, it is appropriate for the NRC to weigh the foreign policy implications as well, because the AEA requires that the common defense and security be considered in making any domestic licensing decision.
The NRC carefully examined policy-based arguments tendered by various commentors that the proceedings ought to be continued, but was not persuaded by them.
Essentially, then, the NRC has imposed a moratorium, expected to last about two years, upon its decisionmaking process regarding plutonium recycling, and, as a result, has terminated the pending GESMO and related licensing proceedings. In the agency’s view, it had “the discretion to stop processing applications and to refuse to accept new ones when there are sound regulatory reasons to do so.”
In passing the Atomic Energy Act of 1954, Congress enacted “a regulatory scheme which is virtually unique in the degree to which broad responsibility is reposed in the administering agency, free of close prescription in its charter as to how it shall proceed in achieving the statutory objectives.”
(c) a program for Government control of the possession, use, and production of atomic energy and special nuclear material, whether owned by the Government or others, so directed as to ... . provide continued assurance of the Government’s ability to enter into and enforce agreements with nations or groups of nations for the control of special nuclear materials and atomic weapons; . [and]
(e) a program of international cooperation to promote the common defense and security . . . ,49
To further these statutory objectives, § 161(p) of the AEA
establish by rule, regulation, or order, such standards and instructions to govern the possession and use of special nuclear material, source material, and byproduct material as the Commission may deem necessary or desirable to promote the common defense and security or to protect health or to minimize danger to life or property . . . .51
A third provision, § 103,
Given this broad delegation of authority to the NRC to choose the necessary means by which to implement the general policy objectives of the AEA, we cannot say that the NRC must inexorably proceed with the processing of license applications and the development of a final GESMO when in its judgment to do so would endanger the attainment of its statutory objectives. Indeed, it would appear to be fully congruent with the broad delegation of authority in the AEA, which allows the NRC to determine the conditions, rules and regulations pursuant to which licenses shall be issued as well as the scope and format of licensing
Our conclusion that, an agency that is invested with such extensive powers to effectuate its far-reaching mandate may impose a moratorium upon its decisionmaking process when sound regulatory reasons exist for doing so is, we believe, consonant with the Supreme Court’s approach in Permian Basin Area Rate Cases, 390 U.S. 747, 88 S.Ct. 1344, 20 L.Ed.2d 312 (1968). There, the question was whether the Federal Power Commission (FPC) had authority to impose a two and one-half year moratorium upon filings of rate schedules while it implemented a new regional ratemaking scheme. The Court noted that it “has repeatedly held that the width of administrative authority must be measured in part by the purposes for which it was conferred . .”
Nothing brought to our attention by petitioners regarding the AEA or its history has convinced us that the NRC has less discretion to impose a moratorium in appropriate circumstances than does the FPC, or that the NRC has failed to comply with any procedural requirements in deferring consideration of wide-scale plutonium recycling. We agree with petitioners that under § 103, once an applicant complies with the provisions of the AEA and Commission rules and regulations, the NRC must issue a license unless it determines that “the issuance of a license to such person would be inimical to the common defense and security or to the health and safety of the public.”
Nor are we persuaded by petitioners’ contention that in suspending the license application proceedings the NRC violated § 189(a) of the AEA,
C. The NRC’s Exercise of its Discretion to Impose a Moratorium Upon its Decisionmaking Process and to Terminate GESMO and Related Licensing Proceedings
Inasmuch as we conclude that the NRC may, in its discretion, delay processing applications and refuse to accept new ones when there are sound reasons for doing so, we must now examine whether in the present case this discretion was abused or was exercised in a manner not in conformity with Statutory dictates. Petitioners raise four grounds upon which the NRC’s decision may be faulted.
m First, petitioners suggest that under the due process clause they should have been afforded an adjudicatory-type hearing before the NRC issued the December 23 Order. However, cases upholding the imposition of temporary “freezes” upon the processing of license applications by the FCC
Next, petitioners assert that in fact the NRC did not place a moratorium upon its decisionmaking process regarding plutonium recycling but really terminated it forever and thus effectively denied the license applications, subject only to the possibility of future reconsideration. In support of this interpretation of the NRC decision, petitioners point out that despite Commissioner Kennedy’s objections,
This contention fails to distinguish between the GESMO and related licensing proceedings, on the one hand, and the ultimate issues of whether to grant the licenses and whether to commit the United States to plutonium recycling programs on the other hand. The December 23 decision terminated the GESMO and related licensing proceedings because in the judgment of the NRC the ultimate issues could not be resolved on their merits within the next two years. At the same time, the NRC committed itself to reexamine this decision in light of future developments, and to determine at a later date what course of action should then be taken on the license applications and the overall question of wide-spread plutonium recycling. Presumably, whatever course the NRC does adopt in the future will lead to a final determination whether or not to issue the requested licenses. In view of the flexibility that the NRC has in fixing the scope and format of its proceedings, as well as the real possibility that the GESMO and licensing proceedings as originally scheduled will be an inappropriate vehicle for arriving at a decision on the ultimate issues, we cannot say that the NRC abused its discretion in “terminating” rather than “deferring” the present proceedings and in refusing to bind itself to a future plan. Furthermore, as we understand it, such a decision may properly be regarded as a statutorily permitted moratorium on the decisionmaking process regarding the ultimate issues, which are still before the agency. Finally, under the circumstances, the expected two-year duration of this moratorium cannot be deemed unreasonable.
Of course, the NRC may not completely terminate license application proceedings without passing on the merits of the applications, simply by declaring an open-ended moratorium. It is required by statute to fix the conditions and regulations pursuant to which licenses will be granted, and to award such licenses if the prerequisites are met, unless it makes a finding of inimicality to the common defense and security or to the public health and safety.
Petitioners also maintain that the NRC impermissibly terminated the GESMO and related licensing proceedings at the request of the President and in deference to his foreign policy pronouncement. They charge that in failing to act independently of the Executive Branch, the NRC contravened Congress’ express intent that the Commission be completely free from presidential influence and control.
Although petitioners’ argument is resonant with constitutional subtleties concerning the “twilight zone”
Actually, the AEC was established by Congress with the hope and aim of making it the most sensitive agency of Government, more independent than any other, and to be protected from Congress itself, and from all other interference, including Executive interference.68
Independence, however, does not mean that the Commission must ignore or reject positions espoused by the President, by Congress or by other parties. The Commission was “charged with a most sensitive and most vital responsibility,”
As previously set forth, the NRC is directed in many provisions of the AEA to consider “the common defense and security.” Any contemplation of these sensitive matters necessarily touches upon areas that are also within the domain of the President and of Congress.
There is no evidence that the President improperly interfered with the NRC’s decisionmaking process, or that the NRC capitulated to the President. Instead, the agency appears to have examined the President’s position, and agreed with the President’s contention that continuation of the proceedings would adversely affect the President’s nonproliferation efforts. Then, after determining that Congress had not exercised its constitutional powers in this area in a contrary manner, neither through the AEA nor through subsequent legislation, the NRC decided that it would be prudent to terminate the proceedings for a time so that the President might pursue his objectives. Given this record, we cannot say that the NRC abused its discretion or acted arbitrarily, capriciously, or not in accordance with the law when it rested its decision in part on a desire not to obstruct the goal of securing international nonproliferation.
As a final ground for attacking the NRC’s exercise of its discretion in the present case, petitioners contend that the NRC impermissibly relied upon the INFCE and NASAP studies in deciding to terminate GESMO and the related licensing proceedings. This is so, they argue, because assertions about these studies are made in the Memorandum without support in the record, in violation of 5 U.S.C. § 556(e),
IV. CHALLENGES BASED ON THE NATIONAL ENVIRONMENTAL POLICY ACT
Aside from attacking the NRC’s decision of December 23 on the ground that it violated the AEA, petitioners charge that the NRC was required under § 102(2)(C) of NEPA
The statutory phrase “actions significantly affecting the quality of the environment” is intentionally broad, reflecting the Act’s attempt to promote an across-the-board adjustment in federal agency decision making so as to make the quality*777 of the environment a concern of every federal agency. The legislative history of the Act indicates that the term “actions” refers not only to construction of particular facilities, but includes “project proposals, proposals for new legislation, regulations, policy statements, or expansion or revision of ongoing programs ”74
Petitioners also cite National Helium Corp. v. Morton, 455 F.2d 650 (10 Cir. 1971), for the proposition that it makes no difference for purposes of NEPA whether the decision is to terminate rather than to institute a program. And, petitioners point out, it is well settled that a post hoc rationalization will not satisfy NEPA’s procedural mandate.
Turning to the December 23 Order, petitioners insist that inasmuch as any decision whether or not to authorize wide-scale plutonium recycle goes to the heart of the substantive policy of § 101(b)(6) of NEPA
It is already apparent from our analysis of petitioners’ challenges under the AEA that we view the December 23 Order suspending the decisionmaking process and terminating GESMO and related licensing proceedings in a different light. Contrary to petitioners’ contentions, we have already concluded that the NRC has not yet decided against authorizing wide-scale plutonium recycling and to deny the license applications. Rather, it has ordered a cessation, for a period expected to last approximately two years, of its decisionmaking process on these issues. We believe it evident that the NRC was not required to prepare an EIS before taking this step, for a number of reasons:
The December 23 Order must be seen in the context of the entire course of events contemplated by the NRC. After it received a number of applications for licensing of plutonium recycling facilities, the NRC realized that it was faced with policy choices that would have a significant impact on the environment, and that it was therefore necessary to prepare an EIS before making any decision whether to authorize the wide-scale reprocessing of spent fuel or to grant the requested licenses. GESMO was to be that EIS, and was to be completed prior' to any decision so that it could introduce into the NRC’s decision-making process input on relevant environmental issues, as mandated by NEPA.
It is also important to note that petitioners’ argument in this respect would produce a completely illogical result. As just mentioned, GESMO itself was to be an EIS. The December 23 Order, which terminated the GESMO proceedings, was based in part on the NRC’s judgment that it could not make an informed decision — as it is required to do under NEPA
V. CONCLUSION
A pressing problem in this last quarter of the twentieth century is a dwindling supply of energy resources coincident with a rising demand for that supply. Increased reliance has been placed on nuclear fuel as one of the more promising sources of energy, at least for the next few years. Nuclear energy, however, presents problems of its own. As recent events have demonstrated, radiation danger to the general population cannot always be contained. Moreover, there exists the risk that nuclear materials and knowledge will be used for nonpeaceful purposes.
Far-reaching policy choices must inevitably be made regarding energy resources,
Congress has delegated authority in the delicate area of nuclear energy to a number of agencies, among them the NRC. The NRC is charged with the responsibility of protecting the common defense and security as well as the public health and safety, while overseeing the licensing of nuclear facilities. Some of the decisions it makes to further its statutory mandate may be unpopular in the nuclear industry, among environmentalists, or with other groups of citizens. But Congress has decreed that the agency be independent from outside control, and it would subvert this design were we to invalidate the challenged NRC action when it appears to be consonant with statutory dictates and not an unreasonable exercise of its discretion.
Accordingly, the petitions for review will be denied.
. 42 U.S.C. §§ 2011-2296 (1976).
. 42 U.S.C. §§ 4321-4347 (1976).
. The AEC was dissolved by the Energy Reorganization Act of 1974, 42 U.S.C. §§ 5801-5891 (1976), and its licensing and related regulatory functions were transferred to the newly-created NRC. See 42 U.S.C. § 5841(f) (1976). Other functions were taken over by the Energy Research and Development Administration and other federal departments.
. The government began encouraging research and development in this field in 1957, and since then has spent approximately $100 million on the project. In 1960, Nuclear Fuel Services, Inc. began construction of a reprocessing plant at West Valley, New York, which operated commercially between 1966 and 1971. Allied-General Nuclear Services started construction of a reprocessing plant at Barnwell, South Carolina, in 1971, pursuant to a permit granted by the AEC. Also, three commercial light water-cooled nuclear power reactors have been authorized to operate with mixed oxide, or recycled, fuel.
The importance of the technology involved in this research, as well as the problems created, can be appreciated with a rudimentary understanding of the nuclear fuel cycle. Currently, the vast majority of nuclear power plants in this country, which now generate about 12 percent of the nation’s electricity, are fueled by slightly “enriched” uranium dioxide fuel. As it enters a reactor, the uranium in the fuel consists of about 3 percent uranium-235 and 97 percent uranium-238. A controlled nuclear chain reaction is then initiated, causing uranium-235 atoms to fission into lighter atoms and releasing heat that generates steam to drive the plant’s electric generators. The chain reaction also transmutes some uranium-238 atoms into plutonium, and some of the plutonium also fissions. The fission products tend to impede the chain reaction, and before the uranium and plutonium are entirely expended, the spent fuel must be removed from the reactor and replaced with fresh fuel. The spent fuel, however, contains elements of uranium and plutonium which, if separated from the waste, reprocessed, and fabricated into new, mixed oxide nuclear fuel, would constitute a significant new source of energy. Besides alleviating the problem of safely disposing of radioactive waste, the recycling of plutonium would help conserve the world’s limited uranium resources. For these reasons, the Commission and private industry have been exploring the commercial feasibility of constructing and operating the facilities necessary to implement this conversion process. However, the recycling of plutonium also presents a danger. As part of that process, plutonium must be isolated from the radioactive waste before being re
. See note 4 supra.
. 42 U.S.C. § 4332(2)(C) (1976).
. The decision to compile GESMO was announced on February 12, 1974, and published in 39 Fed.Reg. 5356 (1974).
. See 39 Fed.Reg. 30186 (1974).
. See NRDC v. NRC, supra, 539 F.2d at 832-33.
. In November, 1975, after an earlier announcement and the receipt of comments, the NRC published a policy statement declaring that a study of safeguard alternatives would be included in GESMO and weighed in NRC’s final decision on the subject of wide-scale commercial recycling of plutonium. That statement also specified the procedures and schedule to be followed for GESMO hearings and set forth criteria under which interim licensing of non-experimental, recycle-related activities would be considered. See 40 Fed.Reg. 53056 (1975), corrected, 40 Fed.Reg. 59497 (1975). Various environmental groups sought review of this policy statement in the Court of Appeals for the Second Circuit. That court affirmed the NRC’s hearing procedures but held that the interim licensing of recycle-related activities on a commercial basis violated NEPA. The Supreme Court vacated and remanded that judgment for consideration of mootness after the NRC’s order of December 23, 1977. See NRDC v. NRC, supra.
. Statement by the President on Nuclear Power Policy, reprinted in 12 Weekly Comp, of Pres. Doc. 1624, lé26 (1976).
. Statement by the President on Nuclear Power Policy, reprinted in 13 Weekly Comp, of Pres. Doc. 502, 503 (1977). It was also announced that “(t)he plant at Barnwell, South Carolina, will receive neither federal encouragement nor funding for its completion as a reprocessing facility.” Id. The Administration’s policy was subsequently discussed at length by Dr. Nye, Deputy to the Undersecretary of State, in Nonproliferation: A Long-Term Strategy, 56 Foreign Affairs 601 (April, 1978).
. On April 12, 1977, the Hearing Board ordered that hearings be postponed until further notice. That same day, the Public Interest Research Group (PIRG) submitted a motion to terminate GESMO, upon which the NRC staff deferred action pending receipt of guidance from the Hearing Board or the NRC. See App. 44a-47a. On May 3, 1977, the NRC directed, the Hearing Board to certify the PIRG motion to the NRC. See 42 Fed.Reg. 22964 (1977).
. See 42 Fed.Reg. 22964 (1977).
. Mr. Eizenstat’s letter stated in pertinent part:
The President believes that our goal of stopping the spread of nuclear weapons capability among non-weapons states can be significantly improved by a halt in purex reprocessing. Last April 7, he stated that the U.S. should “defer indefinitely the commercial reprocessing and recycling of the plutonium produced in U.S. nuclear power programs”. The Administration has proposed an accelerated research and development program to examine alternative fuel cycles not involving direct access to plutonium. The President has also asked other countries to join us in an International Nuclear Fuel Cycle Evaluation to examine alternative approaches to advanced nuclear technologies. The GESMO proceedings and related licensing requests may impact these non-proliferation initiatives. While the studies and analyses done by the Commission staff, if available in published form, may be of value to the International Nuclear Fuel Cycle Evaluation, the President believes that his non-proliferation initiatives would be assisted both domestically and internationally if the Commission were to terminate the GESMO proceedings. Specifically, the President believes that the following actions would be helpful in achieving the Administration’s goals:
* Publication of the Commission’s assessment of safeguards issues.
* Termination of staff reviews and hearings relating to recycle activities. (Continuation of these activities could lead other nations to question the United States commitment to deter commercial reprocessing and plutonium recycle.)
* Denial of interim licensing of fuel cycle facilities.
* Denial of interim licensing for use of mixed oxide fuel in reactors, except in small quantities for experimental purposes.
The letter is reprinted at 42 Fed.Reg. 57186 (1977).
. See 42 Fed.Reg. 57185 (1977). The notice described four possible courses of action: (1) terminating GESMO and denying the related license applications; (2) continuing as before; (3) taking an intermediate course of action,
. See 42 Fed.Reg. 65334 (1977).
. See 43 Fed.Reg. 20575 (1978).
. See 28 U.S.C. § 2344 (1976).
. See note 33 and accompanying text. infra.
. Our jurisdiction under 28 U.S.C. § 2342 and 42 U.S.C. § 2239 “to enjoin, set aside, suspend (in whole or in part), or to determine the validity of’ the NRC’s termination of the GESMO and related licensing proceedings is limited to “final orders” of the Commission. NRDC contends that the December 23 Order is not a “final order” within the meaning of 42 U.S.C. § 2239(b) and 28 U.S.C. § 2342(4) because the administrative process was not consummated until the reasons for the NRC’s proposed action were published, in the May 8 Memorandum. In addition, NRDC argues (1) that there was no “entry” of a final order within the meaning of 28 U.S.C. § 2344 until May 8, 1978, when the NRC issued its Memorandum of Decision, and (2) that the December 23 pronouncement was not an “order” within the meaning of 42 U.S.C. § 2239(b) and 28 U.S.C. § 2342 inasmuch as it omitted a statement of reasons, as required by the Administrative Procedure Act (APA), see 5 U.S.C. §§ 553(c) and 557(c), and the NRC regulations, see 10 C.F.R. §§ 2.760(1), 2.770, 2.806. This argument is predicated on the erroneous premise that the provisions governing review of administrative orders adopt the same defini
. Moreover, in this Court, a “premature appeal taken from an order which is not final but which is followed by an order that is final may be regarded as an appeal from the final order in the absence of a showing of prejudice to the other party.” Richerson v. Jones, 551 F.2d 918, 922 (3d Cir. 1977) (emphasis in original).
. See American Public Gas Ass’n v. FPC, 180 U.S.App.D.C. 380, 555 F.2d 852 (1976); NLRB v. Bayside Enterprises, Inc., 514 F.2d 475 (1st Cir. 1975); Eastern Air Lines, Inc. v. CAB, 122 U.S.App.D.C. 375, 354 F.2d 507 (1965). See generally 16 Wright, Miller, Cooper & Gressman, Federal Practice and Procedure § 3944 (1977) (hereinafter Wright & Miller).
. See Public Service Commission for the State of New York v. FPC, 153 U.S.App.D.C. 195, 472 F.2d 1270 (1972); Wright & Miller, supra note 23, at 339.
. NLRB v. Bayside Enterprises, Inc., supra, 514 F.2d at 476.
. American Civil Liberties Union v. FCC, 158 U.S.App.D.C. 344, 346, 486 F.2d 411, 413 (1973). See Wright & Miller, supra note 23, at 332.
. See Abourezk v. FPC, 168 U.S.App.D.C. 246, 247, 513 F.2d 504, 505 (1975) (statement of Bazelon, C. J., on denial of petition for rehearing en banc).
. Id
. See, e. g., id.
. See, e. g., United Steelworkers of America v. Marshall, 592 F.2d 693 (3d Cir. 1979); American Public Gas Ass’n, supra.
. American Public Gas Ass’n, supra, 180 U.S. App.D.C. at 385, 555 F.2d at 857.
. See, e. g., BASF Wyandotte Corp. v. Costle, 582 F.2d 108 (1st Cir. 1978). See also Wright & Miller, supra note 23, at 332-34.
. Allied-General Nuclear Services v. NRC, Nos. 78-1144 & 78-1422, typed opinion at 3 (D.C.Cir. July 26, 1978) (per curiam).
. See Abourezk, supra, 168 U.S.App.D.C. at 247, 513 F.2d at 505.
. We note, however, that it is at least fairly plausible to conclude that the December 23 Order was the NRC’s “final order,” because that pronouncement contains essential attributes of finality. See Port of Boston Marine Terminal Ass’n v. Rederiaktiebolaget Transatlantic, 400 U.S. 62, 71, 91 S.Ct. 203, 209, 27 L.Ed.2d 203 (1970) (judicial review possible when it “will not disrupt the orderly process of adjudication”); Chicago & Southern Air Lines v. Waterman Steamship Corp., 333 U.S. 103, 113, 68 S.Ct. 431, 437, 92 L.Ed. 568 (1948) (administrative orders are reviewable when “they impose an obligation, deny a right or fix some legal relationship as a consummation of the administrative process”); Isbrandtsen Co. v. United States, 93 U.S.App.D.C. 293, 297, 211 F.2d 51, 55, cert. denied, 347 U.S. 990, 74 S.Ct. 852, 98 L.Ed. 1124 (1954) (“a final order need not necessarily be the very last order in an agency proceeding," so long as it meets the conditions of finality); Wright & Miller, supra note 23, at 315-16. Cf. Baltimore & Ohio R. Co. v. United States, 201 F.2d 795 (3d Cir. 1953) (this Court entertained petition for review, but vacated and remanded order to agency so that it may develop a record capable of review). Indeed, in contrast to the December 23 decision, the May 8 Memorandum had no practical consequence. On the other hand, there is something to be said in favor of the position that when the agency promises to provide in a short time a statement of reasons, its order is not “final” until the statement is published, particularly since the practice of separating the order and its underlying reasons has received judicial sanction, see Baltimore & Ohio Chicago Terminal Railroad Co. v. United States, 583 F.2d 678, 688 (3d Cir. 1978). That way, parties will not feel compelled to file unnecessary “protective” orders out of uncertainty, see Outland v. CAB, 109 U.S.App.D.C. 90, 93-94, 284 F.2d 224, 227-28 (1960), and those parties that delayed in filing petitions for review in reliance upon the agency’s promise to issue a statement of reasons in due course will not be penalized for so relying.
. This is demonstrated by Allied-General’s Response to NRDC’s motion to dismiss its petition for review of the December 23 Order, filed in docket number 78-1993 in the District of Columbia Court. There, Allied-General stated, on pages 2-3:
From our standpoint the jurisdictional issue is not a point of consequence; we filed the two successive Petitions for Review precisely to avoid the jurisdictional question which the Commission’s method of proceeding had given rise to. We hope the jurisdictional matter is decided promptly by this Court, along with the Commission’s Motion to Transfer, so that all parties soon will know in what circuit the*769 judicial review is to be had. We also hope that the jurisdictional issue will not give rise to conflicting decisions in different circuits that might introduce further complications unrelated to the merits.
. 43 Fed.Reg. at 20576-78. As examples of provisions referring to the common defense and security as an element to be considered in domestic licensing decisions, the memorandum cited §§ 53(b), 57(c)(2), 103(b)(3), (d), 104(d), 161(b), (i)(2) and 182(a) of the AEA.
. Congress explicitly supported the alternative fuel cycle studies proposed by the President in § 105 of the Nuclear Non-Proliferation Act of 1978, Pub.L.No.95-242, 92 Stat. 120, which was pending in the Senate at the time of the December 23 decision (having already passed the House of Representatives) and was enacted before the May 8 Memorandum was released. Section 105 states:
The President shall take immediate initiatives to invite all nuclear supplier and recipient nations to reevaluate all aspects of the nuclear fuel cycle, with emphasis on alternatives to an economy based on the separation of pure plutonium or the presence of high enriched uranium, methods to deal with spent fuel storage, and methods to improve the safeguards for existing nuclear technology.
22 U.S.C. § 3224 (Supp.1979). In addition, Congress endorsed the non-proliferation goals of the Administration, as well as its efforts to encourage international cooperation, in §§ 2 and 3 of that Act, 22 U.S.C. §§ 3201-02. See 43 Fed.Reg. at 20577-78, where the Memorandum also acknowledges that individual members of Congress have expressed opposition to the President’s April 7 policy statement.
. See 43 Fed.Reg. at 20577.
. The NRC recognized that the United States’ initiatives to discourage other nations from reprocessing spent fuel would be undermined if at the same time it continued to pursue domestic commercial reprocessing, since American arguments that the marginal economic benefits are outweighed by the grave security dangers would lose their credibility. See id.
. 43 Fed.Reg. at 20578.
. See 43 Fed.Reg. at 20579. The NRC dismissed the argument that the proceedings ought to be continued in order that a much-needed energy source may timely be developed. It did so on the grounds that the overriding risk of proliferation justifies some delay, that a two-year delay to deal with this risk outweighs the economic costs entailed, and that in any event significant progress probably could not be made in the proceedings while the other studies were still underway. As to the contention that the resources already invested in the proceedings would be wasted if they were terminated, the NRC responded that if the proceedings were ultimately resumed, appropriate portions of the record could be reintroduced, and that it would be even less productive to continue the proceedings and then to be required to revise the record in a substantial fashion. Finally, the NRC rejected suggestions that the GESMO proceedings be continued to develop information for purposes of comparison to other fuel cycles on the ground that it is not within its province to perform general energy studies. In addition to treating these policy-based arguments, the NRC Memorandum also dealt with contentions that it is legally required to continue the proceedings.
. See 43 Fed.Reg. at 20578-79.
. See id. The Memorandum continued: “At the present time it is not possible to determine whether our proceedings will then be reinstituted or whether some other course will be adopted.”
. 43 Fed.Reg. at 20579.
. The scope of our review, which is delimited in 5 U.S.C. § 706(2) (1976), is narrow. We may overturn the NRC’s decision if it violates any constitutional or statutory provisions, but may not otherwise substitute our judgment for that of the agency or set aside its decision unless it is unreasonable. See Bowman Transportation, Inc. v. Arkansas-Best Freight System, Inc., 419 U.S. 281, 284-86, 95 S.Ct. 438, 42 L.Ed.2d 447 (1974); Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 413-15, 91 S.Ct. 814, 28 L.Ed.2d 136 (1971).
. Siegel v. AEC, 130 U.S.App.D.C. 307, 312, 400 F.2d 778, 783 (1968). See also Public Service Co. of New Hampshire v. NRC, 582 F.2d 77, 82 (1st Cir.), cert. denied, 439 U.S. 1046, 99 S.Ct. 721, 58 L.Ed.2d 705 (1978); North Anna Environmental Coalition v. NRC, 174 U.S.App. D.C. 428, 431 432, 533 F.2d 655, 658-59 (1976).
. Section 1 of the AEA, 42 U.S.C. § 2011 (1976).
. 42 U.S.C. § 2013 (1976).
. 42 U.S.C. § 220l(p) (1976).
. 42 U.S.C. § 2201(b) (1976).
. 42 U.S.C. § 2133 (1976).
. 390 U.S. at 776, 88 S.Ct. at 1364.
. 15 U.S.C. § 717o (1976), which provides that the Commission “shall have power to perform any and all acts, and to prescribe such orders, rules and regulations as it may find necessary or appropriate to carry out the provisions of this” Act.
. 390 U.S. at 776, 88 S.Ct. at 1365.
. Id. at 780, 88 S.Ct. at 1367.
. Indeed, as petitioners point out, this reading of § 103 is supported by the section’s legislative history. The Joint Committee on Atomic Energy made it clear that with respect to license applications under § 103, the “Commission is required to issue licenses to all qualified applicants without other discretion on its part.” S.Rep.No.1699, 83d Cong. 2d Sess. 19 (1954), U.S.Code Cong. & Admin.News 1954, pp. 3456, 3475.
. 42 U.S.C. § 2239(a) (1976).
. Section 309 of the Communications Act of 1934, 47 U.S.C. § 309 (1976), which requires that the FCC either summarily grant a license application by finding it to be in the public interest, or conduct a hearing. Despite the
. See note 59 supra.
. See Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, 435 U.S. 519, 98 S.Ct. 1197, 55 L.Ed.2d 460 (1978).
. Commissioner Kennedy concurred in the December 23 Order, but preferred the use of the term “defer” for “terminate” to describe the NRC’s action. In a concurring statement to the May 8 Memorandum he explained his position;
Deferral of these proceedings would have avoided the unfortunate appearance that the Commission has made a final decision not to act upon license applications which are properly before it. Additionally, deferral would have left the Commission less susceptible to the argument that the Commission is improperly deferring to a Presidential request affecting not only a rulemaking hearing but also specific licenses which are being treated in an adjudicatory context.
43 Fed.Reg. at 20582. Although the majority of the NRC did not specify its reasons for “terminating” rather than “deferring” the pending proceedings, it may be assumed that the majority was swayed by comments from the Executive Branch and the interested parties arguing that anything less than complete termination may lead foreign countries to question the sincerity of United States overtures to deter commercial reprocessing. See, e. g., app. at 76a (PIRG), 110a (NRDC), 172a (New York), 178a (Eizenstat letter).
. 43 Fed. Reg. at 20579.
. See § 103 of the AEA, 42 U.S.C. § 2133 (1976).
. Expressions of congressional intent that the Commission be independent of the Executive Branch may be found throughout the debates surrounding the passage of the AEA, which took place against the backdrop of the Dixon-Yates controversy. That controversy arose when the President attempted to instruct the Commission to enter into a contract with particular utilities for the provision of electricity to certain Commission facilities. On legislative sentiment, see, e. g. 100 Cong.Rec. 9743 (1954) (remarks of Senator Hill); id. at 10297-98 (colloquy of Congressmen Murray and Holifield); id. at 11532 (remarks of Senator Magnuson); id. at 11536 (remarks of Senator Gore). Aside from resting on the legislative history of the AEA, petitioners insist that Congress made its intent evident in the provisions of the AEA by narrowing the circumstances under which the AEA may decline to grant a license. This argument, which focuses on § 103, is treated in
. See, e. g. 42 U.S.C.A. §§ 2077(b), 2153(b), & 2155 (1976 & 1979 Pocket Part).
. See Youngstown Sheet & Tube Co. v. Sawyer (Steel Seizure Case), 343 U.S. 579, 637, 72 S.Ct. 863, 96 L.Ed. 1153 (1952) (Jackson, J„ concurring).
. 100 Cong.Rec. 11532 (1954).
. 100 Cong.Rec. 9743 (1954) (Senator Hill).
. Youngstown, supra, 343 U.S. at 635, 72 S.Ct. at 870.
. See, e. g., Youngstown, supra; Oetjen v. Central Leather Co., 246 U.S. 297, 38 S.Ct. 309, 62 L.Ed. 726 (1918); United States v. American Telephone & Telegraph Co., 185 U.S.App.D.C. 254, 260-261, 567 F.2d 121, 127-28 (1977). See generally, L. Henkin, Foreign Affairs and the Constitution (1972); Comment, United States v. AT & T: Judicially Supervised Negotiation and Political Questions. 77 Colum.L.Rev. 466, 473-76 (1977).
. Section 556(e) provides:
The transcript, of testimony and exhibits, together with all papers and requests filed in the proceeding, constitutes the exclusive record for decision in accordance with section 557 of this title and, on payment of lawfully prescribed costs, shall be made available to the parties. When an agency decision rests on official notice of a material fact not appearing in the evidence in the record, a party is entitled, on timely request, to an opportunity to show the contrary.
. 42 U.S.C. § 4332(2)(C) (1976).
. 156 U.S.App.D.C. at 404, 481 F.2d at 1088 (footnotes omitted).
. See, e. g„ Cady v. Morton, 527 F.2d 786, 794 (9th Cir. 1975).
. 42 U.S.C. § 4331(b)(6) (1976).
. See Shiffler v. Schiesinger, 548 F.2d 96, 100-101 (3d Cir. 1977) (preparation of EIS is part of decisionmaking structure through which substantive objectives of NEPA may be realized).
. See, e. g., Final GESMO-I, vol. 1, Summary at i (NRC, 1976); Draft GESMO, vol. 2 at 1-2 (AEC, 1974); 39 Fed.Reg. at 5356 (1974). That an EIS was required before a decision could be reached on plutonium recycling was confirmed in NRDC v. NRC supra.
. See text accompany notes 6-7 supra.
. 427 U.S. at 406, 96 S.Ct. at 2728.
. Id at 406, 96 S.Ct. at 2728.
. Id. (emphasis in original). In a later footnote, the Court elaborated:
[Section 102(2)(C)] contemplates a consideration of environmental factors by agencies during the evolution of a report or recommendation on a proposal. But the time at which a court enters the process is when the report or recommendation on the proposal is made, and someone protests either the absence or the adequacy of the final impact statement. This is the point at which an agency’s action has reached sufficient maturity to assure that judicial intervention will not hazard unnecessary disruption.
Id. at n.15, 96 S.Ct. at 2728.
. Because of our disposition of petitioners’ contentions, and our holding that as a matter of law no EIS is required at this stage of the administrative process, we need not decide at this time the standard of review this Court might apply when it reviews an agency determination that a proposed action had only an insignificant impact on the environment and that accordingly an EIS is unnecessary. See NAACP v. Medical Center, Inc., 584 F.2d 619, 635 n.19 (3d Cir. 1978); Shiffler v. Schlesinger, supra, 548 F.2d at 104-05 n.5.
. See 42 U.S.C. § 4332 (1976).