This action was instituted by the plaintiff for the foreclosure of a mechanics’ lien upon two certain sections of land in Fresno County owned by the California Land Company, one of the defendants herein. At the time the work was done, from which, as claimed ‘by plaintiff, the lien arose, the lands sought to be affected thereby were in the possession of the California Farms Company, another defendant herein, which was an unincorporated association of persons of whom the defendant Sherwood Green was a member and officer, having authority to act for such association; and which association was at the time of doing of said work in the possession of a larger tract of land of which said sections were a part under an option to purchase the same from the California Land Company. The work to be done by the plaintiff was set forth in a contract in writing bearing date of February 10, 1920, between it and the California Farms Company and consisted in the sinking of a test bore in search of water-bearing strata upon said sections of land to the depth of 1,000 feet. The contract proceeded to state that “if, within a depth of 1000 feet from the surface of the ground, sufficient apparent water-bearing strata are encountered which by mutual agreement would justify finishing the Well, then we are to ream out the Test Bore and sink a Well at this point, and case the same with 24" diameter Double 12 Gauge Hard Red Sheet Steel Casing for approximately the first 120 feet, then a Taper Connection from 24" to 12" and 12" diameter Double 12 Gauge Casing for the balance of the distance. . . . After the Casing has been installed, we fill in the annular space between the wall of the hole dug to receive the Casing and the Casing itself with selected washed Gravel,—making and completing what is known as the Western Well Works Inc. Patented Gravel Envelope Well, *751 constructed under Patent #1289320.” The contract further embraced the specifications for the well in case the test bore justified its completion and provided for the installation of a pump thereon having a capacity of from 1,000 to 2,500 gallons of water per minute. The work proceeded under this contract to the depth indicated therein, the plaintiff furnishing all of the derricks, materials, supplies, and labor for the doing of said work in accordance with the provisions of said contract. The California Farms Company did not, however, comply with the terms of its said agreement as to payments nor as to completion of the well, in consequence of which the plaintiff ceased operations and in due time filed and recorded its lien for the labor and materials furnished and used in the prosecution of the work of making said test bore; and thereafter commenced this action for the foreclosure of its said lien, joining the California Land Company, the California Farms Company, and Sherwood Green, and certain other persons alleged to compose said latter association as defendants in said action. In its complaint the plaintiff, after alleging the facts as to performance by it of said work under said contract with the California Farms Company and of the nonpayment by the latter therefor, proceeded to allege that the California Land Company had notice and knowledge of the doing of said work and the furnishing of said labor, materials, and supplies on and at all times after February 10, 1920, but that said California Land Company never gave notice by either posting or recordation that it would not be responsible for said work, labor, materials, or supplies. The defendants appeared separately and demurred to the sufficiency of the plaintiff’s complaint; the California Farms -Company and the defendant Green demurring both generally and specifically and the California Land Company presenting a general demurrer. These demurrers were overruled. The defendant California Farms Company defaulted by failing to answer after notice. The defendant Sherwood Green answered denying the making and entering into the contract by the California Farms Company or himself for the doing of said work. The California Land Company answered denying practically all of the averments of the complaint save and except the averment that said defendant claimed the right, title, and interest in said premises sought *752 to be affected by said lien adverse to the claim of the plaintiff and in that respect alleged itself to be the owner of said premises free and clear of the lien asserted by said plaintiff. It also specifically denied having any notice or knowledge of the doing of said work or of the furnishing of the said labor, materials, or supplies at any time prior to the institution of said action. The cause came on for trial upon the issues thus joined and upon its submission the court made its findings of fact herein and found that the plaintiff had performed the work of drilling the test bore upon the premises in question under the contract with the California Farms Company and as required by the terms of said contract and had furnished the labor, materials, and supplies necessary for said work as provided therein and that no part of the sum to be paid therefor by the said California Farms Company had been paid, save and except the sum of $500 on account thereof, and that in due course the plaintiff had filed its claim of lien upon said two sections of land for the balance remaining unpaid upon said contract. ' The court further found that no part of said premises sought to be impressed with said lien was necessary for the convenient use and occupation of the improvements placed thereon by said plaintiff, save and except a circle of ground one hundred feet in diameter around the spot where the derrick had been erected above the point where said test bore had been drilled. The court further found that the said test bore to be constructed and actually constructed under the terms of said contract between the plaintiff and the California Farms Company was not a well and did not come within the definition of any of the matters for which a lien is granted under the statutes of the state of California. The court also found that the defendant California Land Company had no notice or knowledge of the doing of said work and furnishing of said labor, materials, or supplies at any time prior to the service upon it of the summons and complaint in this action, and that the said defendant California Land Company never gave any notice, either by posting or recordation, that it would not be responsible for said work, labor, materials, or supplies. As conclusions of law from the foregoing findings of fact the court found that the plaintiff was entitled to a personal judgment against the defendants California Farms Company and Sherwood *753 Green for the sum of $3,494.86, but that as to the defendant California Land Company it was entitled to judgment that the plaintiff had no lien upon the premises described in its complaint. Judgment ¡was entered accordingly. The plaintiff’s motion for a new trial was denied, whereupon it took and prosecutes this appeal.
Judgment reversed.
Tyler, P. J., and St. Sure, J., concurred.
*759 A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on April 12, 1923.
All the Justices concurred.
