OPINION ORDER
As far as the Court and the parties can discern, this case presents a novel issue under Illinois law.
The ultimate issue: Whether a third party beneficiary contract action may be asserted by an unpaid subcontractor against a public entity where such entity has failed to procure from a general contractor a payment bond as required by the Illinois Bond Act.
The case is before this Court on cross motions for summary judgment. Under Count III of their complaint, Plaintiff Western Waterproofing Company, Inc., prays for judgment in the amount of $129,-000. Under Count VI of their complaint, Mid-Continental Restoration Company, Inc., prays for judgment in the amount of $22,-456. Defendant Springfield Housing Authority prays for judgment dismissing Counts III and VI of Plaintiffs’ complaint.
Summary judgment will be granted where there is no genuine issue as to any material fact and the movant is entitled to a judgment as a matter of law. Fed.R. Civ.P. 56(c).
The pertinent facts of this suit are undisputed. Plaintiffs were subcontractors for a federally funded construction project of the Defendant, Springfield Housing Authority (SHA). In January 1985, the SHA entered into an agreement with Bildoc, Inc. (Bildoc), for the waterproofing and weatherization of five hi-rise apartment buildings. The general contractor, Bildoc, then entered into contracts with various subcontractors which included Plaintiffs Western Waterproofing Company, Inc. (Western) and Mid-Continental Restoration Company, Inc. (Mid-Continental). Both Plaintiffs contributed labor and materials toward the completion of the project. Both were to receive payment 63 days from completion of the project. Work was completed and final payment, less retainage in the amount of $12,481.16, was made to Bildoc on December 13, 1985.
Western was to be paid $129,000 under its agreement with Bildoc. Mid-Continental was to be paid $22,456 under its agreement with Bildoc. Neither Plaintiff has received any payments for work performed.
Plaintiffs filed their complaint on May 2, 1986. They secured a default judgment against Defendant Bildoc based on Counts I and IV of the complaint in a judgment order entered July 11,1986. The Plaintiffs have been unable to collect on this judgment. Plaintiffs then resumed proceedings in this case in February 1987 against the SHA. Plaintiffs confessed SHA’s motion to strike Counts II and V of the complaint. Thus, Counts III and VI of the complaint, which allege that the Plaintiffs are third party beneficiaries of SHA’s contract with Bildoc, remain unlitigated and are the subject of the cross motions for summary judgment.
I.
The basis of the Plaintiffs’ claim as a third party beneficiary of the contract between SHA and Bildoc stems from the following provision in the general contract:
PERFORMANCE AND PAYMENT BOND
A performance bond in the amount of total amount of contract for cost of installation of windows will be furnished to the authority as a separate cost item and will be added to the contract price. After the first shipment of windows and payment thereof by SHA, the Contractor *903 shall provide SHA with a Waiver of Lien against all materials on site.
The SHA failed to procure from Bildoc either a performance bond or a payment bond. Both parties agree that had a payment bond been secured the Plaintiffs, as subcontractors, would have collected monies due them under such bond. The parties further agree that subcontractors have no rights under a performance bond. Thus, the initial bone of contention is, what exactly was required under the contract. If only a performance bond was required, as stated in the body of the provision, then Western and Mid-Continental as subcontractors have no claim. If, however, a payment bond was also required as stated in the heading of the provision, then Plaintiffs have stated a colorable claim.
The nature of the bonds involved is as follows. Generally, as a condition of the construction contract between an owner (SHA) and a general contractor (Bildoc), the owner requires the contractor to obtain a surety bond. “There are two kinds of surety bonds, performance bonds and payment bonds. A performance bond simply insures that the contractor will perform the work as contracted.... A payment bond, on the other hand, requires that the contractor pay all subcontractors and material-men before the owner will make final payment.”
Taylor Woodrow Blitman Const. Corp. v. Southfield Gardens Co.,
It is the SHA’s contention that although the above quoted “section is entitled Performance and Payment Bond, it requires only a Performance Bond. There is nothing that requires Bildoc to supply a Payment Bond under the contract.” The Court disagrees with this interpretation for two reasons. First, under 29 Ill.Rev.Stat. ¶ 15 (1985), An Act in Relation to Bonds of Contractors Entering into Contracts for Public Construction (Bond Act),
all officials, boards, commissions or agents of this State, or of any political subdivision thereof in making contracts for public work of any kind to be performed for the State, or a political subdivision thereof shall require every contractor for such work to furnish, supply and deliver a bond to the State, or to the political subdivision thereof entering into such contract, as the case may be, with ■ good and sufficient sureties. The amount of such bond shall be fixed by such officials, boards, commissions, commissioners or agents, and such bond, among other conditions, shall be conditioned for the completion of the contract, for the payment of material used in such work and for all labor performed in such work, whether by subcontractor or otherwise.
Id.
(emphasis added).
1
The Act contains mandatory language directing the requirement of a payment bond to protect materi-almen and subcontractors.
Fodge v. Board of Educ. of the Village of Oak Park, Dist. 97,
Under Illinois law, “statutory provisions applicable to a contract ... are deemed to form a part of that contract and must be construed in connection therewith.”
DC Electronics, Inc. v. Employers Modern Life Co.,
The second reason a payment bond and not simply a performance bond is held to be required under the contract is that ambiguous contractual language is to be construed against the drafter of the language.
Duldulao v. St. Mary of Nazareth Hosp. Center,
II.
Having established that a payment and performance bond was necessary under the contract, the Court must now decide whether Plaintiffs are third party beneficiaries under the contract and are, therefore, able to assert the bond provision. The Court determines that they are.
There is no question that had a payment bond been procured Plaintiffs would have been third party beneficiaries under it. The question arises here, however, whether Plaintiffs are third party beneficiaries under the contract provision to procure a bond where none has been procured. The answer in Illinois appears to be that they are.
The general rule with respect to third party beneficiary actions in Illinois is well settled. If the contract is entered into for a direct benefit of a third person, not party to the contract, such third person may sue for breach thereof. The test is whether the benefit to the third person is direct or incidental. If direct, he may sue on the contract; if incidental, there is no right of recovery.
Carson Pirie Scott & Co. v. Parrett,
In
Town & Country Bank of Springfield v. James M. Canfield Contracting Co.,
A materialman may be a third party beneficiary of a promise by a general contractor to obtain a surety bond for the prompt payment of all laborers and ma-terialmen, and, in the context of a government contract, an unpaid material-man of a subcontractor was allowed to sue the general contractor who had failed to provide such a bond as he had covenanted in the construction contract.
Avco,
III.
Defendant, SHA, argues that even if a payment bond was required and even if Plaintiffs are third party beneficiaries under the general contract, SHA is immune from liability under the Illinois Bond Act.
2
Defendant cites two cases in support of this proposition.
Emulsicoat, Inc. v. City of Hoopeston,
Both
Emulsicoat
and
Noslo
present fact situations similar to that of the instant case — an unpaid subcontractor brought an action against the government which failed to secure a payment bond from the general contractor. However, each case was brought on a negligence theory — not in contract. The
Emulsicoat
court held that although the Bond Act provided a remedy for unpaid subcontractors “the legislature [took] meticulous care to see that the traditional immunity was not infringed....”
Emulsicoat,
A further reason for refusing Defendant protection under the Bond Act can be found in the legislative intent in enacting the act.
It was unquestionably because there is no right to a mechanic’s lien against a public work and because it has been repeatedly held by the courts of review of this State that provisions such as are contained in the principal contract in this case, which are relied upon as constituting cross complainant a third party beneficiary, were not effective for that purpose and did not afford a commonlaw right of action against a surety upon a public construction performance bond, that the statute [Bond Act] was enacted requiring public bodies and officials in making contracts for public work to see that bonds were furnished by the contractors which would protect material-men and subcontractors.
Fodge,
*906 IV.
Defendant raises two additional arguments. First, Defendant asserts that Plaintiffs have waived any redress against SHA in its subcontract under a provision in which the subcontractor agreed that “no mechanic’s liens or claims will be filed or maintained against the project or premises....” The Court does not read this waiver to include a third party beneficiary contract action against the owner who was not party to the subcontract.
Second, Defendant argues that Plaintiffs are estopped from making a claim against SHA. Defendant argues that the estoppel arises from conversations between representatives of Plaintiffs’ companies and the Executive Director of the SHA wherein the representatives urged the Director to make prompt payments to Bildoc such that Bildoc could pay Plaintiffs. Citing
Stewart v. O’Bryan,
Ergo, for the reasons given above, the Court ALLOWS Plaintiffs’ motion for summary judgment. As this Court is presently holding the retainage funds, in the amount of $12,480.82, from the SHA-Bildoc contract, such funds are hereby ordered released to Plaintiffs in the following amounts: Western Waterproofing — $10,-608.70; Mid-Continental Restoration Co.— $1,872.12. The retainage funds are divided in this manner pursuant to agreement between the Plaintiffs. The Court further awards Western Waterproofing Company judgment in the amount of $118,391.30 (for a total award of $129,000 as prayed in Count III of their complaint) plus interest and costs of suit. The Court further awards Mid-Continental Restoration Company $20,583.88 (for a total award of $22,-456 as prayed for in Count VI of their complaint) plus interest and costs of suit. Conversely, Springfield Housing Authority’s motion for summary judgment is DENIED.
Notes
. It has been held that a housing authority is a political subdivision and therefore subject to the provisions of the Bond Act.
Housing Authority of Franklin, Illinois ex rel. Smith-Alsop Paint & Varnish Co. v. Holtzman,
. Defendant also asserted immunity under the Tort Immunity Act of Illinois. This is clearly wrong. Ill.Rev.Stat. ch. 85, If 2-101 (1985) states: "Nothing in this act affects the liability, if any, of a local public entity or public employee, based on: (a) Contract_”
