256 F. Supp. 163 | W.D. Okla. | 1966
MEMORANDUM OPINION
This is an action by the plaintiff, Western Contracting Corporation, against the defendant, Sooner Construction Company, for breach of an alleged subcontract between the parties on a runway project
From the evidence the Court finds that Sooner orally quoted certain unit prices on asphalt paving to Western prior to Western submitting its bid on the project for the prime contract. Western was successful on its bid. Thereafter, Sooner confirmed its orally quoted prices to Western by a letter dated March 25, 1963.
Western points to several actions of Sooner after the July 15, 1963, meeting which it says supports the claimed oral subcontract and that they evidence an implied subcontract and create an estop
Sooner does not deny these activities but asserts that they were of little consequence and except for furnishing the hot mix were only normal preparations in anticipation of eventually getting the subcontract which was under negotiation. As to the hot mix, Sooner asserts that this was a small quantity ordered by Western for their own work and not work under the subcontract and which was furnished as requested by Western in the interest of good relations and the anticipated subcontract. Sooner did not furnish a payment and performance bond, move onto the job or do any work called for by the subcontract.
It does appear from the evidence that Sooner was having some trouble with getting the Corps of Engineers to approve their mix under the specifications and the problem here apparently was never finally resolved between them before negotiations terminated between Sooner and Western.
In late September, 1963, certain developments took place. Sooner sent a signed subcontract to Western to which it attached certain amendments, six in number, one of which called for full payment for each of the three phases of the work to be done by Sooner within 45 days of completion by Sooner of each phase in lieu of Sooner’s requirement in its written confirmation of payment by the 10th of the month and Western’s requirement in the written subcontract it prepared and submitted of the 10'% retainage and the final payment in 45 days. Western wrote Sooner a letter advising Sooner that it was delinquent in the performance of its subcontract and that if Sooner did not correct this default in performance within five days Western would exercise its rights under the subcontract. Then on September 29 or 30, 1963, a meeting was held in Oklahoma City which brought a Mr. Shaller down from Iowa for Western. Shaller as manager of heavy construction for Western was over Hastie. At this meeting the six amendments were discussed one by one and Shaller disapproved the amendment about full payment in 45 days following each phase completion as well as two other amendments and in his own hand wrote “out” opposite each of the three amendments so disapproved. Shaller approved the other three amendments. In the language of Shaller, finally at this meeting “things were terminated”. Under date of October 2, 1963, Western made a subcontract with Metropolitan Paving Company for larger unit prices as to all items (the price for hot mix surface — the largest item — was $8.53 per ton) and sues herein for the difference amounting to $16,957.08 plus interest, overhead and profit and other expenses.
An implied contract is one deemed to have been reached by the parties even though not expressed by a document or documents, because of subsequent conduct and actions regarding the subject matter involved. In Board of County Com’rs of Seminole County v. Southwest Natural Gas Co., 192 Okl. 594, 138 P.2d 525 (1943), it has been held:
“ * * * ‘ [A] n implied contract in the proper sense, arises where the intention of the parties is not expressed, but an agreement in fact, creating an obligation, is implied or presumed from their acts, or, as it has been otherwise stated, where there are circumstances which, according to the ordinary course of dealing and the common understanding of men, show a natural intent to contract. It has been said that such a • contract must contain all the elements of an express contract, it rests on consent, it is to every intent and purpose an agreement between the parties, and it cannot be found to exist unless a contract status is shown. Such a con*168 tract does not arise out of 'an implied legal duty or obligation but out of facts from which consent may be inferred.’ * * *.
“ ‘As the law will not imply a promise, where there was an express promise, so the law will not imply a promise of any person against his own expressed declaration, because such declaration is repugnant to any implication of a promise.’ ”
15 Oklahoma Statutes, Section 71 pro*vides:
“An acceptance must be absolute and unqualified, or must include in itself an acceptance of that character, which the proposer can separate from the rest, and which will include the person accepting. A qualified acceptance is a new proposal.”
Anderson v. Garrison, Okl., 402 P.2d 873 (1965) provides:
“In order that a counter-offer and acceptance thereof may result in a binding contract, the acceptance must be absolute, unconditional, and identical with the terms of the counteroffer.”
Also, Nabob Oil Co. v. Bay State Oil & Gas Co., 208 Okl. 296, 255 P.2d 513 (1953).
It is true that the parties may have a binding agreement, provided they have reached one, even though they have the understanding that the agreement should be formally drawn up. This depends upon the intention of the parties.
Fry v. Foster, 179 Okl. 398, 65 P.2d 1224 (1937) holds:
“Where parties to an agreement make its reduction to writing and signing a condition precedent to its completion, it will not be a contract until this is done, and this is true although all the terms of the contract have been agreed upon. But, where parties have assented to all the terms of the contract, and they are fully understood in the same way by each of them, the mere reference in conjunction therewith to a future contract in writing will not negative the existence of a present contract.”
The doctrine of estoppel is applied to promote justice and fair dealing and when by words or conduct of one party another party has been induced to rely upon the same to his injury.
L. C. Jones Trucking Company v. Cargill, Okl., 282 P.2d 753 (1955) holds:
“ ‘A person relying on an estoppel must have exercised such reasonable diligence as the circumstances of the case require, and if he conducts himself with a careless indifference to the means of information reasonably at hand or ignores highly suspicious circumstances, which should warn him of danger or loss, he cannot invoke the doctrine of estoppel.
‘No estoppel arises where the party setting it up is under as great obligation to inform the person sought to be estopped of the real facts as the latter is to inform himself. There can be no estoppel where the truth is known to both parties, or where they both have equal means of knowledge.’ ”
The essential elements of such estoppel are:
1. An act or failure to act.
2. Intent that the act or failure to act will be relied upon but there must be reasonable grounds to believe that such action or failure to act is calculated to induce reliance.
3. Justifiable reliance requiring that the party claiming the estoppel shall have acted in good faith, relying on the estoppel and in the belief of its truth, and,
4. Prejudice resulting from the act or failure to act complained of herein.
But a contract may not be formed or created by estoppel. 31 C.J.S. Estoppel § 151, p. 742. Rather, the contract is deemed to have been made and its existence cannot be denied because of the conduct and actions of the party to be estopped.
Thus, the importance of what actually took place on July 15, 1963, be
The Court, therefore, finds and concludes from the evidence that Sooner quoted a price of $7.82 a ton on hot mix surface provided payment was received for the same by the 10th of the month— otherwise the price would be $8.32 a ton; ■that the weight of the evidence indicates that this alternative quote and payment condition of Sooner was not changed or discussed on July 15, 1963; that Western in submitting a subcontract to Sooner set out the $7.82 per ton price but did not meet the payment condition attached to the same; that Sooner immediately and admittedly by several telephone conversations objected to this feature of the subcontract as submitted; that Sooner after the July 15, 1963 meeting and after
Plaintiff is, therefore, not entitled to the judgment it seeks. To the contrary, the defendant is entitled to judgment against the plaintiff for the mix it furnished the plaintiff for its work for which the defendant has never been paid.
Counsel for the defendant will prepare a judgment in conformity with the foregoing and submit the same to the Court pursuant to Rule 58, F.R.Civ.P., and Rule 22 of this Court.
. Received after Bidding Haskell Lemon Construction Co,
Road Building and Paving Phone Windsor 6-3357 P. O. Box 7118 OKLAHOMA CITY, OKLAHOMA
Western Contracting Corp. March 25, 1963 Sioux City, Iowa
RECEIVED Mar 28 1963
Western Contracting Corporation 400 Benson Building Sioux City, Iowa Gentlemen:
Congratulations on receiving the Tinker Field contract. I hope that it will prove to he a most successful job for you.
We would like very much to make a contract with you to do your asphalt paving work on this job. This letter is to confirm the prices which we quoted you at Fort Worth.
Item 9. Prime 48,150 gallons @ .19 Furnish, deliver and apply..no brooming or blotting.
Item 10. Tack coat, 260 gal. @ .37
Item 11. Tack coat, 318 gal. @ .37
Item 13. Hot mix surface 17,220 T. @ $8.32, less 50# ton discount for payment by 10th of month
Item 14. Asphalt (85-100) 215,350 gal. @ .13
No quotation on item 12, 15, 16, 17 as they may be deleted.
We will be happy to help you in any way possible on this contract. We would appreciate your contacting us when you establish your job office here. We hope the job will prove to be both pleasant and profitable and that we will have the opportunity of working with you.
Yours very truly,
/s/ Haskell Lemon
Haskell Lemon
Haskell Lemon Construction Co.
. This is the testimony of Hastie on these points:
“Q After you submitted Plaintiff’s Exhibit A to Mr. Lemon, you say on July 18th, did you then have any further discussion with him?
A Yes, he called me on the phone on several occasions and we discussed certain of the terms of this submitted .subcontract.
Q And what terms did you discuss, if you remember?
A One of them was the retainage; he wanted the retainage reduced. The original retainage was ten percent in the total amount of the contract, and we agreed verbally to reduce that to ten percent of the first fifty percent of the contract.
Q To ten percent of the first fifty percent?
A Yes, and thereafter no further retainage.
Q And you did agree that Plaintiff’s Exhibit A could be amended to that extent?
A Yes, we did.
Q And did you have any, other conversation with him about any of the other terms?
A Another one of the terms that he wanted changed was that we would add a clause that he would not be responsible for keeping up with our schedule in the event of strikes, fire, flood, or things beyond his control.
Q And did you agree to that?
A Yes, we did.
Q Were there any other items that he discussed with you?
A Another one was that he wanted us at the end of each phase of the work — you understand there were three phases in this work.
Q What were the phases?
A We called them Phase One, Phase Two, and Phase Three.
Q What were they?
A They were portions of the asphalt shouldering on one of the taxiways. Phase One took a certain amount; Phase Two some more; then Phase Three the balance. And he wanted us to pay him in full for each phase of the work within forty-five days of its completion.
Q Did you agree to that?
A What I told him we could do would be if the Corps of Engineers would agree to pay us in full for each phase as it was completed, then we would pay him in full.
Q And did he agree to that?
A I don’t recall he ever gave any answer to that.”