Plaintiff has appealed from the judgment of the Circuit Court of the City of St. Louis sustaining a motion to dismiss plaintiff’s petition on the ground that it fails to state a claim upon which relief may be granted.yL
We shall summarize portions of the petition, but shall quote other portions when necessary to set forth plaintiff’s claim.
On May 6, 1959, Westerhold Construction, Inc. (hereafter referred to as “contractor”) entered into a written agreement (hereafter referred to as the “construction contract”) with the Archdiocese of St. Louis of the Catholic Church (hereafter referred to as “owner”) whereby the contractor was to construct a church and rectory in accordance with drawings and specifications prepared .by defendant. On May 15, 1959, the contractor, as principal, and Maryland Casualty Company, as surety, executed a performance bond in the amount of $325,322.00, and a labor and material payment bond in the amount of $162,661.00, in favor of the owner, “as required by and pursuant to the terms of said written agreement,” and on May 6, 1959, as an inducement to said Maryland Casualty Company to execute said bond as surety thereon, by written agreement plaintiff agreed to indemnify and hold harmless said Maryland Casualty Company against any liability for damages, loss, cost, charges and expenses which it might sustain or incur by reason of having executed said bonds as surety. By the terms of the construction contract, the performance of the contractor was “under the supervision of and was subj ect to the inspection of defendant,” and payments by the owner to the contractor for work performed and materials furnished were required to be made “upon certification by defendant, as the architect, to said owner that payments requested by [defendant] from time to time during the progress of said job, for work stated to have been performed * * * and for materials furnished and delivered * * * had, in fact, been performed and delivered on the job, and that the amounts of such payments so requested, from time to time, correctly reflected the percentage of the work actually then performed and the percentage of materials then supplied and delivered on the job.” At various times prior to May 4, 1960, defendant certified to the owner that the contractor had completed work and had furnished materials “of the total value of $229,628.00,” and the owner, relying upon said certifications by defendant, had paid to the contractor the sum of $206,665.20, which represented 90% of the value of the work and material certified by defendant as having been performed and furnished. However, at the time of the said certificates made by defendant “the amount of work which actually had been performed by [the contractor] was substantially less than the value .thereof certified by defendant. as having been performed and furnished,” and *75 the said certificates “were false and inaccurate” as to the total value of the work performed and materials furnished by the contractor by an amount in excess of $23,000. Subsequently the contractor defaulted under the construction contract, and the owner, pursuant to the terms of the construction contract, declared the contractor to be in default and called upon Maryland Casualty Company, as surety, to complete and carry out the terms of the construction contract. The surety did complete the contract and in doing so incurred expenses in excess of $93,234.23, and made demand upon plaintiff for payment pursuant to plaintiff’s obligations under • the previously described indemnification agreement, and plaintiff was required to expend and pay to the said surety the sum of $17,-500.00 in full settlement of his liability as indemnitor, and was caused to incur other expenses in the amount of $2,250.00. The loss, damages, and expenses incurred by plaintiff as indemnitof “were directly and proximately caused by the carelessness, negligence and wrongful acts of defendant in that defendant as architect * * * wrongfully and negligently failed to inspect and supervise the work performed and the materials furnished and delivered by said [contractor] * * *; and negligently, carelessly and wrongfully performed his duties as said architect, in falsely and incorrectly certifying, for payment by the [owner], to amounts and values of work performed and materials furnished and delivered by said [contractor], in an aggregate sum substantially in excess of the amount of work performed and the amount of materials actually furnished and delivered, so as to result in a substantial overpayment to said [contractor], thereby leaving an amount yet to be paid under [the construction contract] substantially smaller than the amount of work left to be performed and the amount of materials left to be supplied and delivered, in order to comply with the terms and provisions of said [construction contract].” Defendant, in his capacity as architect, knew or should have known, by the exercise of ordinary and reasonable care, that the amounts so certified by him for payment were substantially in excess of the value of the work actually performed and the materials actually supplied and delivered, and he “thereby acted carelessly and negligently in the performance of his duties as such architect.” Plaintiff prayed judgment against defendant in the amount of $20,000. ⅛
The motion to dismiss the petition alleged not only that the petition fails to state a claim upon which relief may be granted, but also that the action is barred by limitations. The trial court sustained the motion on the first ground only. In his brief to this court, respondent has not attempted to demonstrate that if the petition does state a claim the action is barred by limitations. We consider this latter issue as not before us.
The construction contract is not attached to and made a part of the petition. From the allegations in the petition we cannot determine whether defendant was a party to the construction contract in the sense that he signed it along with the contractor and owner, or whether there was a separate contract between the owner and defendant. In any event, defendant’s duties, or at least those duties material to the issue in this case, were set forth in the construction contract, and he purported to perform them pursuant thereto. No issue on this appeal is made concerning the source of his contractual obligations, or that they were other than alleged. Under the standard form of contract prepared by the American Institute of Architects the architect is designated as an arbitrator, see 12 Vanderbilt Law Rev. at p. 718 et seq., and in some contracts the architect’s certificate as to work performed is stated to be conclusive. See § 2 of Annotation,
*76
By the terms of the construction .contract defendant was to inspect and supervise the performance of the work by the contractor, and payment to the contractor was authorized upon a certificate by defendant that the work actually had been done and the materials actually had been furnished by the contractor for which payment was sought. The construction contract also required that the contractor furnish a performance bond and a labor and material payment bond, and this was done by Maryland Casualty Company. While it is not specifically alleged that in issuing the bonds Maryland Casualty Company relied on the provisions of the construction contract providing for inspection and supervision of the work by defendant and also relied on the provisions for payment by the owner only upon certificates of defendant, it is a fair inference from the facts alleged that Maryland Casualty Company knew of those provisions and appreciated the fact that “to guarantee the performance of a contract where progress payments are adequately safeguarded is a less hazardous risk than to guarantee the performance of a contract where there are no safeguards.” Hall v. Union Indemnity Co., 8th Cir.,
Plaintiff is not the surety, but is the indemnitor of the surety. Plaintiff does not specifically allege that the indemnity agreement provided that he would be subrogated to claims by the surety against the architect. However, he does allege that as indemnitor of the surety he was compelled to satisfy, at least in part, the liability of the surety. Generally speaking, an indemnitor of a surety compelled to satisfy the liability of a surety is subrogated to all rights to which the surety would have been subrogated. 83 C.J.S. Subrogation §62; 50 Am.Jur. Subrogation § 36. In compliance with our rule to construe the petition liberally and to accord to it every reasonable inference from the facts alleged, Myers v. City of Palmyra, Mo.,
Plaintiff’s petition is based on negligence, and the immediate issue is (whether in the absence of privity of contract the facts stated in the petition imposed upon defendant a legal duty to the surety to exercise ordinary care in executing the certificates called for in the construction contract, so that he would not authorize payments to the contractor in excess of the amount provided for in the construction contract?
In the article by Bohlen, Fifty Years of Torts, 50 Harvard Law Review, 1225, at p. 1232, it was pointed out that the requirement of privity stems from an English case decided in 1842, Winterbottom v. Wright, 10 M. & W. 109, 152 Eng.Rep. 402, which announced that one who was not a party to a contract could not recover for its negligent performance, or that a defendant who had contracted with another owed no duty to a plaintiff who was not a party to the contract where there was no privity or direct transaction between them. This doctrine was illustrated by Roddy v. Missouri Pac. Ry. Co.,
This rule requiring privity has not been followed blindly and without exception. As stated in Prosser on Torts 2nd ed. § 84, p. 498, when the application of the rule would produce a result contrary to the requirements of essential justice and sound public policy it has been whittled away by exceptions. In fact, throughout the years so many exceptions have been engrafted upon the rule that it has been said, perhaps too broadly, that the exceptions have “swallowed the rule.” LaPlant v. E. I. DuPont de Nemours & Co., Mo.App.,
We agree with the proposition that any extension of the limits of liability in this field should be done on a case-to-case basis, with a careful definition of the limits
*78
of liability, depending upon the differing conditions and circumstances to be found in individual cases. Two New York cases, written by the same judge, illustrate this. In 1922 Judge Cardozo wrote the landmark case of Glanzer v. Shepard,
^ We shall now examine the factual situation of this case to determine whether there exists the reasons for the application of the rule requiring privity of contract.
The entire arrangement, that is, the construction contract containing the provisions for payment to the contractor upon certificates from the architect, the architect’s contract with the owner, and the bonds required by the terms of the construction contract, was based upon several interrelated agreements designed to accomplish one objective, the construction of the church building and the rectory. While, strictly speaking, there may not have been privity of contract between' the architect and the surety, this was a transaction in which the relation was so close, to use Judge Cardozo’s words, “as to approach that of privity.” The requirement in the construction contract that payments by the owner were to be made to the contractor only upon certificates issued by the architect that the work had been performed and the materials had been furnished was “as much for the protection of the surety
*79
as the owner.” Hall v. Union Indemnity Co., 8 Cir.,
We consider that the above demonstrates that the first of the reasons advanced in Winterbottom v. Wright for the rule of privity (unlimited liability to an unlimited number of persons) is absent in the factual circumstances of this case. We are also of the opinion that the second reason (that the parties to contracts would be deprived of control over their contracts) does not exist under the pleaded facts. In the event the parties in privity mutually agree to change provisions of the contract between them inuring to the benefit of the surety, which changes result in increasing the risk of the surety, the surety is discharged from his liability under his surety agreement either wholly or to the extent of his increased risk. Southern Real Estate & Financial Co. v. Bankers’ Surety Co., Mo.,
The reasons for the rule or requirement of privity of contract are not applicable to the facts and circumstances of this case, and as a matter of logic we perceive no reason why in such a situation privity should be required unless it be that the rule is an ancient one. Mr. Chief Justice Fortescue is reported in 3 Holds-worth, A History of English Law, to have once said: “Sir, the law is as I say it is, and so it has been laid down ever since the law began; and we have several set forms which are held as law, and so held and used for good reason, though we cannot at present remember that reason.” We are not inclined to consider ourselves so restrained and bound. While we agree that ancient rules developed in the crucible of experience should not lightly be cast *80 aside, we are also of the opinion that when the reason for a rule ceases to exist, or when the reason for a general rule does not apply to a particular factual situation, the court should not blindly follow such rule for no more justifiable reason than that it is ancient and traditional. See also Holmes, The Path of the Law, 10 Harvard Law Review, 457, 469.
For these reasons we consider the rule requiring privity of contract to be inapplicable, and that we should determine the sufficiency of the petition by the application of ordinary rules of negligence.
It is clear that an obligation may be assumed by contract out of which may arise a duty to others than parties to the contract. Helm v. Inter-Insurance Exchange for Automobile Club of Missouri,
Turning now to the facts of this case, as determined from the allegations of the petition, defendant had the contractual duty to certify, for purposes of payment by the owner to the contractor, the correct amount of work satisfactorily performed and the correct amount of materials furnished. The defendant negligently and incorrectly certified to the owner that more work had been performed, and that more materials had been delivered than in fact had been performed and delivered. As a result of this negligent certification, when the contractor later defaulted and the surety was required to complete the project, there was less money in the hands of the owner available to be used by the surety to pay for completing the project than there would have been if defendant had performed his contractual duties without negligence, and the surety had to make up the difference. In the exercise of ordinary care this result was easily foreseeable. In fact, the purpose of the inspection and certification by the architect was to prevent exactly what happened.
'⅞⅝-We have been referred to only one case, and we have found no other, which is closely parallel to the facts of this case. In State of Mississippi, for use of National Surety Corporation v. Malvaney,
Defendant admits that the Malvaney case is “relevant to the question” but he contends that it is inapplicable because (1) the plaintiff in that case “was the contracting surety who was known and intended to be a party to the transaction,” and (2) the court relied on a Mississippi statute which, in effect, made the surety a participant in the construction contract, and the architect’s actual or constructive knowledge of that law was held to impose a special duty on him to protect the position of the surety. We consider these to be no more than differences which do not distinguish that case from this. Plaintiff in this case stands in the position of the surety, and has no claim or right which could not be asserted t'by the surety. The surety was known, and the contract provisions pertaining to payments based on certificates of the architect were for the surety’s benefit. In the Malvaney case the owner was a public school, and the statute referred to required a performance bond by a surety. The requirements of the statute as to what the bond was to provide are not materially different from what plaintiff alleges the bond in this case provided. The defendant there was “charged with knowledge” of the requirements of the law, and for the purposes of this appeal we cannot assume that defendant did not know, or was not required to know, the terms of the contracts.
Defendant also asserts that his negligence was not the proximate cause of plaintiff’s loss, but that the default of the contractor was an intervening cause. The purpose of the inspection and the certificates of the architect was to protect the owner and the surety against payment of money to the contractor for work not performed and materials not delivered in the event of default. No loss to the owner or to the surety could ever result if there had been no default. The occurrence of the incident for which the contract provisions were designed to guard against should not be considered to be an intervening cause.
“The determination whether in a specific case the defendant will be held liable to a third person not in privity is a matter of policy and involves the balancing of various factors, among which are the extent to which the transaction was intended to affect the plaintiff, the foreseeability of harm to him, the degree of certainty that the plaintiff suffered injury, the closeness of the connection between the defendant’s conduct and the injury suffered, the moral blame attached to defendant’s conduct, and the policy of preventing future harm.” Biakanja v. Irving,
The judgment is reversed and the cause remanded.
PER CURIAM.
The foregoing opinion by STOCKARD, C., is adopted as the opinion of the Court.
Notes
. In a subsequent appeal,
