Vacated and remanded for dismissal by published opinion. Senior Judge MAGILL wrote the opinion, in which Chief Judge WILKINSON and Judge WIDENER concurred.
OPINION
Eight years after ceasing mining operations at Kittle Flats and receiving a final bоnd release from the State of West Virginia, LaRosa Fuel Company (LaRosa) received a Cessation Order from the Office of Surface Mining Reclamation and Enforcement (OSM), requiring it to reduce acid mine drainage from Kittle Flats. The Interior Board of Land Appeals (IBLA) vacated the order, ruling that OSM lacked jurisdiction to enter the order because of the final bond release. The district court agreed. The West Virginia Highlands Conservancy (Conservancy), an intervenor in the IBLA proceedings, appeals. We vacate the judgment of the district court and remand the case with instructions to dismiss it because it is not ripe for review.
I.
Beginning in 1973, the State of West Virginia issued four permits to LaRosa to mine at Kittle Flats, and required LaRosa to post bonds for the reclamation of Kittle Flats after the cessаtion of LaRosa’s mining operations. In July 1981 LaRosa requested the State to grant it a final bond release for each of its permits. After two years of negotiations, the State agreed that LaRosа should have no further liability or responsibility for Kittle Flats and granted a final bond release. The final bond release specifically provides that LaRosa “has fully complied with the provisions of the Code of West Virginia ... and the rules and regulations promulgated and adopted pursuant” thereto. J.A. at 382.
Before the final bond release, Congress enacted the Surface Mining Control and Reclamation Act of 1977 (SMCRA), 30 U.S.C. §§ 1201-1328, to “establish a nationwide program to protect society and the environment from the adverse effects of surface coal mining operations----” 30 U.S.C. § 1202(a). SMCRA created OSM within the Depаrtment of Interior for the purpose of administration and enforcement. See 30 U.S.C. § 1211(c). Pursuant to SMCRA, the Secretary of Interior, through OSM, devised and implemented an interim regulatory program, or initial program, for regulating surface coal mining and reclamation operations. See 30 U.S.C. § 1251; 30 C.F.R. Parts710-725. The parties do not dispute that Kittle Flats is an interim program site.
In 1988, the Secretary of Interior, through OSM, promulgated a termination of jurisdiction rule, 30 C.F.R. § 700.11(d), for the purpose of defining the moment in time at which OSM and state agencies lose jurisdiction over surface mining and reclamation operations. Pursuant to § 700.11(d)(1), OSM’s jurisdiction over a reclaimed surface coal mining site terminates when a “regulatory authority determines in writing that under the initial program, all requirements imposed under subchapter B of this chapter [ (30 C.F.R. Parts 710-725) ] have been successfully completed. ...” 30 C.F.R. § 700.11(d)(l)(i). When OSM’s jurisdiction over a site is terminated under § 700.11(d)(1), OSM may not reassert jurisdiction over that site unless the above-described written determination “was based upon fraud, collusion, or misrepresentаtion of a material fact.” 30 C.F.R. § 700.11(d)(2).
On several occasions between 1984 and 1991, OSM investigated and identified acid
In 1991, the Conservancy filed a citizen complaint with OSM, alleging that аcid mine drainage from Kittle Flats was contaminating and endangering the environment. After investigation, OSM agreed and, reversing its prior position, entered a Cessation Order against LaRosa, requiring LaRosa to reduce the drainage. On appeal, the IBLA vacated the Cessation Order, ruling that LaRosa’s final bond release constituted a sufficient “written determination” under § 700.11(d)(l)(i) to terminate OSM’s jurisdiction over Kittle Flats. The IBLA then remanded the case to OSM for the purpose of reasserting jurisdiction under § 700.11(d)(2).
OSM has not challenged the IBLA’s ruling, and is currently attempting to reassert jurisdiction. The Conservancy, in contrast, appеaled the ruling to the district court. After the district court affirmed the ruling, the Conservancy filed the present appeal.
II.
We do not address the merits of this appeal because we find that it is not ripe for review. When making a ripeness determination, we analyze both of the following questions: “(l)[is] the issue[ ] fit for judicial review and (2) will hardship fall to the parties upon withholding court consideration?” Arch Mineral Corp. v. Babbitt,
Typically, a “case is fit for judicial decision where the issues to be considered are purely legal ones and where the agency rule or action giving rise to the controversy is final and not dependent upon future uncertainties or intervening agency rulings.” Id. (quotations omitted). Such is the case here. The sole issue on appeal is whether the final bond release constitutes a sufficient writing to terminate OSM’s jurisdiction over Kittle Flats pursuant to § 700.11(d)(1). The critical facts relevant to this determination are undisputed, see id. (issue legal where “critical facts are not disputed”), and the IBLA “took final action when it issued an order setting forth its interpretation of [§ 700.11(d)(1) ] as applied to the specific facts alleged.” Id. at 668 (quotations omitted).
“But even when agency action is final and the issues presented are purely legal, a court may nonetheless properly deem a matter unfit for resolution if ... [t]he court ... determined ... that resolution of the dispute is likely to prove unnecessary.” State Farm Mut. Auto. Ins. Co. v. Dole,
We believe that “resolution of th[is] dispute is likely to prove unnecessary.” Dole,
Perhaps more important, it seems clear that the Conservancy will not suffer hardship if this court denies review. “[T]he purpose of the ‘hardship to the parties’ analysis is to ascertain if the harm that deferring review will cause the petitioner[ ] outweighs the benefits it will bring the agency and the court.” Eagle-Picher Indus., Inc. v. EPA,
The Conservancy has nоt identified any specific hardship that it will suffer if we refuse to consider this appeal. The Conservancy certainly has not shown that “irremediable adverse consequences may flow from a detеrmination that this case is not currently ripe for review,” or that “no review will ever be possible” if this appeal is dismissed. International Union, UAW v. Brock,
Finally, the Conservancy’s rights under SMCRA have been fully preserved despite the IBLA’s ruling and will not be affected by this Court’s refusal to consider this appeal. As explained above, if OSM successfully reasserts jurisdiction then the IBLA’s ruling in the present case “fade[s] into insignificance,” Aluminum Co. of Am.,
For the foregoing reasons, we conclude that the IBLA’s ruling is not ripe for review, and we vacate the district court’s grant of summary judgment and remand with instructions to dismiss.
VACATED AND REMANDED FOR DISMISSAL.
Notes
If the Conservancy believes that OSM is dragging its feet, it always has the option of filing a citizen suit against OSM for failing to compel LaRosa to comply with SMCRA. See 30 U.S.C. § 1270(a) (permitting citizen to file suit against United States or Secretary of Interior to compel compil-anee with SMCRA). Notably, the Conservancy has never availed itself of SMCRA’s citizen suit provision and is proceeding in this case solely as an intervenor in intra-Deparlment of Interior proceedings.